Tender register template
Last updated 2026-11-10 · 6 min read
A tender register is one list of every enquiry you receive, priced or not. For each one it records the client, project, package, return date, whether you priced it and why, who priced it, the value and margin submitted, and the outcome. It keeps deadlines in view, shows your estimating workload and records results.
Most subcontractors keep tenders in an inbox and the estimator's head. That works until two returns land on the same day, a clarification gets missed, or nobody can say what happened to a price sent in spring. A register fixes all three for the cost of a few minutes per enquiry.
What columns should a tender register have?
| Column | What to record |
|---|---|
| Ref | Your own tender number, used on every file and email |
| Received | Date the enquiry arrived |
| Client | The main contractor or client inviting the price |
| Project and package | Project name, location and the package you are asked to price |
| Source | Open invitation, approved list, framework or repeat client |
| Return date | Date and time the price is due |
| Decision | Price, decline, or ask for more information, with one line of reason |
| Estimator | Who is pricing it |
| Submitted | Date sent, and the revision if you resubmit |
| Value | The price submitted, before VAT |
| Margin priced | The margin built into the price |
| Status | Pending, won, lost, withdrawn or declined |
| Outcome date | When you heard |
| Feedback | What you were told, including your position if they say |
| Follow-up | Next date to chase, with a name |
Fill in the first eight columns the day the enquiry arrives. The rest are added as the tender moves on.
What does a filled-in register look like?
For illustration only, with assumed figures.
| Ref | Client | Project and package | Return date | Decision | Value | Margin priced | Status | Feedback | Follow-up |
|---|---|---|---|---|---|---|---|---|---|
| T-118 | Contractor A | Office refurbishment, partitions and linings | 14 Nov | Price: repeat client, fits programme | £186,000 | 14% | Pending | 28 Nov | |
| T-119 | Contractor B | Student housing, drylining package | 18 Nov | Decline: start date clashes with two live jobs | Declined | Thanked, asked to stay on list | |||
| T-120 | Contractor C | Clinic fit-out, partitions | 21 Nov | Ask: drawings incomplete, query raised | Pending | 15 Nov | |||
| T-114 | Contractor A | Retail unit, partitions and linings | 31 Oct | Price | £42,500 | 16% | Lost | Second of four, about 4% above the lowest | Ask for next enquiry |
Notice that the declined enquiry still has a line. Over a year, the reasons in the decision column show how much work you turn away and why, which is as useful as knowing what you won.
How do you decide whether to price an enquiry?
Pricing takes estimating time, and every tender you price badly in a rush is worse than one you decline. Before you start, answer these and write the answer in the decision column:
- Is the package the kind of work you do well, at a size you can resource?
- Does the programme fit around your live jobs and committed gangs?
- Do you know the client, and how have their valuations, payments and contra charges been?
- Are the documents complete enough to price properly?
- Is there enough time to the return date to price it and check it?
- Are the subcontract terms you have been sent acceptable, or will you need to qualify them?
If a tender goes ahead, the drylining tender checklist covers the checks before you submit, and your quote template sets out the offer itself.
How do you keep the register current?
- One person owns it, even if several people price
- Log every enquiry the day it arrives, including the ones you will decline
- Check the return dates at the start of each week, and give each estimator their list
- Record revisions and clarifications as they are sent, with the date
- Chase outcomes on the follow-up date, and log what you are told
Ask for feedback every time you lose. Many main contractors will tell you whether you were close, and some will tell you where your scope or exclusions made the price hard to compare.
What can the register tell you later?
Once a few months of outcomes are logged, the register is the data behind your tender win rate. You can see how often you win by client, sector and size, how many tenders it takes to win one job, and whether the margin you price at affects the result. The guide to tracking your tender win rate works through those numbers.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Can I download this tender register template?
There is no download. Copy the table on this page into your own spreadsheet, one row per enquiry.
Should I log tenders I decline?
Yes. The reasons show how much work you turn away and why, and declining politely keeps you on the client's list.
How long should I keep tender records?
Keep at least the register itself for several years. Old prices and outcomes are useful when the same client or type of job comes back.
Who should own the tender register?
One person, usually the estimating lead or office manager. Shared ownership tends to mean nobody updates it.