Drylining quote template for your clients

Last updated 2026-11-08 · 6 min read

Short answer

A drylining quote to a client should set out the package, the drawings and revisions priced, a priced summary by system, inclusions, exclusions, your assumptions about access and programme, the attendances you expect, payment terms and how long the price holds. Copy the template below and fill in every section, even when the answer is "none".

The quote is more than a price. It is the record of what you agreed to do, and it is what you go back to when the job changes. A clear exclusion in the quote is worth far more than an argument on site.

What should a drylining quote include?

Cover these sections, in this order, on every quote:

  • Project and package. The project, the client and exactly which work you are quoting for.
  • Documents priced. Drawing numbers and revisions, schedules and specification sections.
  • Priced summary. One line per system or section, with quantity, rate and total.
  • Inclusions. What the price covers, beyond the obvious.
  • Exclusions. What it does not cover, named, not implied.
  • Assumptions. Access, working areas, programme and how many visits you have allowed for.
  • Attendances. What you expect the main contractor to provide.
  • Variations. How changes will be valued.
  • Programme. Your duration and any lead-in.
  • Payment. Application dates, payment terms and retention.
  • Validity. How long the price holds.

What does the template look like?

Copy this table into your quote document and fill in the right-hand column.

SectionWhat to writeYour entry
Project and packageProject, client, package and areas covered
Documents pricedDrawing numbers and revisions, schedules, specification sections
InclusionsWork covered beyond the summary lines
ExclusionsWork not covered, each item named
AssumptionsAccess, working areas, visits, hours
AttendancesHoist, skips, welfare, power, lighting, storage
VariationsHow changes are valued
ProgrammeDuration, lead-in, sequence
PaymentApplication dates, terms, retention
ValidityHow long the price holds

Then add the priced summary, one row per system or section:

RefSystem or sectionUnitQtyRateTotal

What does a filled-in quote look like?

Here is an example of the sections, with the prices left out:

SectionExample entry
Project and packageOffice fit-out, levels 2 and 3: partitions, wall linings, deflection heads and door openings
Documents pricedDrawings A-200 to A-214 rev C, partition schedule rev B, specification section K10
InclusionsDeflection heads, acoustic sealant to rated walls, towers for our own use, distribution from the loading bay
ExclusionsFire stopping to service penetrations, ceilings, door sets, decoration, out-of-hours work
AssumptionsClear, dry floors handed over complete, one continuous visit per floor, normal working hours
AttendancesHoist, loading bay, skips, welfare, power and lighting by the main contractor
VariationsValued at the summary rates where they apply, otherwise at the daywork rates attached
ProgrammeTwo weeks per floor after handover, two weeks' notice to start
PaymentMonthly applications, terms and retention as the subcontract
Validity30 days from the date of the quote

For illustration only: if the priced summary totals an assumed £48,600 and fire stopping is excluded, write that exclusion in the quote itself, not only in a covering email. If the main contractor later asks for fire stopping, it is a change at a price, not something you are taken to have included.

How should you present the price?

Give a priced summary with rates, not only a lump sum, where the tender allows it. Rates give both sides an agreed basis for valuing changes, and the guide to recording variations shows how to use them once the job starts.

The summary should come straight from your build-up. The guide to pricing a drylining job sets out what the price behind it should hold.

Keep the validity honest. Your price should not hold longer than the merchant quotes it is built on.

What should you check before you send it?

Read the quote as the main contractor will:

  • Do the drawing revisions match the ones you measured from?
  • Do the summary lines add up to the total?
  • Does every exclusion match something the tender might expect you to include?
  • Are the payment terms and retention consistent with the subcontract you have been sent?
  • Is the quote dated, addressed to the right person and given a reference?

Payment terms deserve a careful read, because they affect your cash as much as the price does. The guide to payment applications and retention covers what to look for.

FixMargin is software for UK drylining and interiors subcontractors. The costed BoQ behind your price, call-offs and purchase orders are on the Starter plan and above, so a priced job can carry straight into buying. You can start with the calculator on a free account.

Frequently asked questions

Can I download this quote template?

There is no download. Copy the tables on this page into your own quote document or spreadsheet.

How long should a drylining quote be valid?

No longer than your merchant quotes are valid, and say so on the quote. If materials are quoted for 30 days, a 90-day price leaves you carrying the risk for the other 60.

Should I quote rates or a lump sum?

Give rates in the summary where the tender allows. They give both sides an agreed basis for valuing changes and remeasuring the work.

What if the main contractor sends its own tender form?

Fill it in, and attach your inclusions, exclusions and assumptions as part of the offer. Refer to them on the form so they form part of what is accepted.