Recording variations on drylining jobs

Last updated 2026-11-08 · 6 min read

Short answer

To record a variation on a drylining job, capture the instruction when it is given: who asked, what changed, where and when, in writing. Record what you actually did with dated photos and quantities, price the whole cost including labour, materials and disruption, and keep every variation in one log that feeds the job cost.

Variations are a normal part of drylining work. Drawings get revised, a wall moves, a service clashes with a partition, or the site manager asks your gang to box in something that was never in your price.

The work usually gets done. Whether it gets paid for depends on what you recorded at the time. A variation you cannot evidence is often a favour you did for free.

What counts as a variation?

A variation is any change from what you priced. That might be extra work, omitted work, a change to the specification, a change in sequence or working hours, or a revised drawing issued after your offer.

This is why your offer needs to state which drawing revisions you priced and what you assumed. Without that starting point, it is hard to show that anything has changed.

What does your subcontract say about variations?

Every subcontract sets its own rules. Before you start on site, find out:

  • Who can instruct a change
  • Whether the instruction has to be in writing
  • Any time limits for giving notice or submitting a price
  • How dayworks are agreed and at what rates

The wording differs from job to job. If a clause looks unclear, or a lot of money is at stake, take proper advice. Do not assume the last contract said the same thing.

How do you capture the instruction when it happens?

Most variations start as a conversation on a landing. That is fine, but it should not end there.

The same day, confirm it in writing to the person who gave it. A short email is enough: what was asked, by whom, when, where on site, and a request for a formal instruction if your subcontract needs one. For example:

'Confirming your request this morning to form an additional bulkhead on level 2, gridline C. We will treat this as a variation and send a price. Please confirm the instruction.'

If you can, get that confirmation before starting. On some jobs you will be pressed to carry on. Make that a conscious decision, and keep the paper trail either way.

What should you record about the work?

Evidence is what wins these conversations. Keep:

  • Dated photos of the area before, during and after
  • The revised drawing, with its revision letter
  • Measured quantities, including how you got them
  • Names of the operatives and the hours they spent
  • Materials used, with delivery notes or invoices
  • Plant and access that were needed

For work paid as daywork, get the sheets signed by the main contractor's representative as soon as you can, ideally the same day or the same week. A sheet presented a month later is much easier to argue with.

How do you price the whole cost of a variation?

A variation costs more than the materials and the hours in the room. Think about:

  • Labour, at a rate that reflects the real conditions
  • Materials, including part packs and extra deliveries
  • Access equipment that stays longer
  • Supervision and management time
  • Rework of anything you had already finished
  • Disruption to the gangs working elsewhere
  • Overheads and profit

For illustration only: an extra bulkhead takes 2 operatives 5 hours each. That is 10 hours at an assumed £30 an hour, or £300 of labour. Add £120 of materials and £60 for a tower kept on for two more days, and the cost is £480. An assumed 15% for overheads and profit adds £72, so the price submitted is £552. Your own rates come from your subcontract and your records.

If the change affects your programme, say so now. Delay and disruption are much harder to raise once the job is over.

Omissions need care as well. If work is taken out, you may have already bought material for it or planned your labour around it. Note that when you agree the omission.

What goes in a variation log?

Every job needs one list, kept up to date. For each variation, record:

  • Your reference number
  • Description and location
  • Date of instruction, and who gave it
  • Date the price was submitted
  • Value submitted and value agreed
  • Status: instructed, priced, agreed, paid or disputed
  • Where the evidence is stored

Send the log with each application for payment, so that nothing quietly drops off. Review it at site meetings. If an item sits unanswered, chase it while people still remember the work.

How does a variation feed into the job cost?

Variations change both sides of the job: the income and the cost. Book the costs against the variation, not the base work, otherwise your original price looks worse than it is, and you lose sight of whether the extras made money.

Only count agreed value as secure. Show what is submitted but not yet agreed separately, so that you do not spend margin you might never get.

FixMargin is software for UK drylining and interiors subcontractors. A working estimator went from signup to a priced bill of quantities in under 15 minutes, with no help. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Can I claim for a verbal instruction?

That depends on your subcontract. Confirm every verbal instruction in writing at once, and check what the contract requires.

What is the difference between daywork and a priced variation?

Daywork is paid on recorded time and materials. A priced variation is agreed as a figure, usually in advance.

How much detail is enough?

Enough that someone who was not there could understand what changed and check the cost.