How to price a drylining job in the UK
Last updated 2026-11-08 · 6 min read
To price a drylining job in the UK, read the drawings, specification and subcontract first, then measure by system rather than by wall. Build the material cost from your own merchant prices, price labour from outputs you have seen on site, add access, waste and preliminaries, then overheads and profit, and write down every assumption.
Pricing a drylining job is mostly about not missing things. Rates matter, but jobs usually lose money through what never made it into the price: a second lift of access, a board type nobody noticed, or a programme that turns one visit into five.
This is a sensible order to work in, whether the package is one floor or a whole fit-out.
What should you read before you measure?
Start with the drawings, the specification, any partition or ceiling schedule, and the tender letter. Read the preliminaries too. They tell you who provides the hoist, the skips, the welfare and the power, and that can move your price more than a change of board.
Keep a running list of questions as you read. If the drawings and the spec disagree, ask. If you cannot get an answer before the deadline, price your assumption and say so in your offer.
Check the boundaries of your package. Fire stopping, door sets, decoration prep, bulkhead framing and access panels often sit in a grey area between trades. Decide what is in and what is out, and put it in writing.
Why measure by system, not by wall?
Group your quantities by system type. A wall with two layers of board each side is a different job from a single-layer partition, even if the drawing shows the same line.
Split each system by height as well, because taller walls usually need different stud sizes, more access and slower work. Keep linear items such as head details, beads and trims separate from the square metres. Note the awkward items on their own: small rooms, curved work, risers and bulkheads. They eat labour and hide inside a big total.
How do you build the material cost?
For each system, list the components and work out how much of each you need per square metre. Use the manufacturer's data for quantities, not memory, and check the current edition.
Then price each component from your own merchant quote or price list. Watch the units. Boards may be quoted per sheet or per square metre, and fixings by the box. Convert everything to one unit before you add it up.
Add a waste allowance that reflects the job. A long, open floor with repeated heights will not waste the same as a building full of short returns. Your own past jobs are the best guide here, so keep the numbers.
How do you price labour?
Labour is where most estimates go wrong, because it is the biggest guess. Use outputs from your own jobs where you have them, and split them by activity: framing, boarding, taping and jointing.
Ask how the work will actually run. Will the gang work one long stretch, or come back three times around other trades? Is there a ceiling grid to work around? Stop and start time is real cost.
Include supervision, and be honest about whether a working chargehand is really producing at full rate.
What sits around the work that you must price?
These items are easy to leave out because they are not on the drawing:
- Access: towers, podiums, hoist waiting time
- Moving material from the delivery point to each floor
- Storage and protection of boards on site
- Waste removal, if it is yours
- Mastic, sealant and small sundries
- Snagging and return visits
- Paperwork, drawings and site management time
How do overheads and profit differ from margin?
Add overheads and profit last, and know which number you are looking at. Markup is a figure added on top of cost. Margin is the share of the selling price you keep. They are not the same number, and mixing them up quietly lowers your return.
The sum is simple: margin equals selling price minus cost, divided by selling price. Run it on the final figure every time.
For illustration only: a job costed at £8,500 and sold at £10,000 keeps £1,500, which is a 15% margin. Add a 15% markup to the same £8,500 cost instead and you sell at £9,775, which is a margin of about 13%.
Think about retention and payment terms as well. A job that pays late costs you money to carry, even if the margin looks right on paper.
Which assumptions should you write down?
Your offer should list what is included, what is excluded, the drawing revisions you priced from, how long your prices hold, and the access you have assumed. If the job changes later, this list is what lets you claim a variation.
How do you check a price before it goes?
Divide your total by the square metres and compare it with similar jobs. If it looks off, find out why. Check that the largest quantities came through correctly, and that a second person has looked at the price if you can manage it.
FixMargin is software for UK drylining and interiors subcontractors, with 917 live British Gypsum systems. A working estimator went from signup to a priced bill of quantities in under 15 minutes, with no help. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Should I price per square metre or as a lump sum?
Build it up from rates either way. Whether the client sees a rate or a lump sum depends on the tender, but you need the build-up behind it.
How much should I allow for waste?
There is no single right figure. It depends on board sizes, heights and layout, so use records from your own similar jobs.
How long should my material prices hold?
Check how long each merchant's quote is valid, and do not promise longer than that.
Gyproc and Gypframe are trade marks of Saint-Gobain. FixMargin is not affiliated with British Gypsum.