A drylining take-off starts from the system specification, not the drawing. Measure each partition, lining and ceiling type separately in m², then the linear items such as heads, deflection and corners, and the numbers such as doors. Turn each system into its components, allow for sheet and pack sizes, and check the totals before pricing.
A drylining take-off turns a drawing and a specification into a list of things you can buy. Get it right and the rest of the job has a firm base. Get it wrong and every later number, from the merchant quote to the call-off, carries the same mistake.
Here is a straightforward way of working from system spec to material list.
Why start with the specification, not the drawing?
It is tempting to start measuring straight away. Read first.
Find the partition and lining types on the drawings, and look each one up in the specification. For each type, note the manufacturer's system reference if one is given, and the performance required: fire, acoustic, height and any duty rating.
If the spec only gives a performance and leaves the system to you, choose one from the manufacturer's current published data, and be ready to show why. British Gypsum publishes this in its White Book, and other manufacturers publish their own guides. Use the current edition, because specifications change.
Before measuring, write out the build-up for each type in plain words: frame, layers of board each side, insulation, and any special detail.
How do you measure each type separately?
Work through the drawings one system type at a time, and mark up as you go so that you can see what you have covered. For each run, record:
- Length
- Height, using the true height to the slab or the ceiling line as specified
- Faces of board, since one wall may have different linings on each side
Then group the runs by type and height. Height matters because it can change the stud size or layout a system allows, so check the system's limits for each height.
Decide on a rule for openings, and apply it consistently. If you are pricing a bill, check how it is measured. If you are measuring your own, remember that deducting a door opening from the board does not mean you buy less board, because you still cut around it.
Which linear items and numbers do you measure?
Square metres alone do not make a material list. Also take off:
- Head and floor channels
- Deflection head details, where required
- External and internal corners, and beads
- Door openings, with their extra studs or reinforcement
- Board ends and junctions with other partitions
- Abutments that need sealant or acoustic detailing
- Access panels, and fixing support for anything heavy on the wall
Fixing support is easy to miss. Sinks, handrails, screens and wall units all need something behind the board. Check who is providing it.
How do you turn each system into components?
For each system, work out the quantity of each component per unit of measure. The manufacturer's data will give you most of this: stud centres, board layers, screw types, screw quantities, and the sealant or tape required.
Then list them in a build-up:
- Boards, by type, thickness and size
- Studs and channels, by size and length
- Screws, by type and length
- Insulation, by type and thickness
- Tape, jointing compound and beads
- Sealant and any fixings into the structure
For example only: on a 10 m wall, 2.7 m high, boarded on both faces with one layer, you have 27 m2 of wall and 54 m2 of board. At an assumed 600 mm stud centres, that is about 18 studs including the end. Head and floor channel comes to 20 m. Your real figures must come from the system data and the layout on site.
How do you allow for how the material is sold?
Next, turn the theoretical quantities into what you will buy. Add a waste allowance, by material, based on your own past jobs. Then convert to whole sheets, lengths and packs.
Think about lengths. If your height is close to a stock length, you may have little offcut. If it is not, you may be paying for a lot. Consider ordering board in a length that suits the height, since it can reduce joints as well as waste, if the merchant can supply it.
If the sheets will not fit in the goods lift, that decides the size you order.
How do you check a take-off before pricing it?
A good take-off can be checked by someone else. Keep your marked-up drawings, and note the revision you measured from.
Then run some simple checks:
- Does the total of each type look sensible for the building?
- Do studs per m2 and screws per m2 look right against similar jobs?
- Has each type on the drawing appeared in your list?
- Has anything been measured twice, such as a wall shared by two rooms?
Finally, list what you could not resolve, and send those questions out before the tender date.
FixMargin is software for UK drylining and interiors subcontractors, with 917 live British Gypsum systems. A working estimator went from signup to a priced bill of quantities in under 15 minutes, with no help. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Can I change a specified board for a cheaper one?
Not without checking. Tested performance depends on the build-up, so check the manufacturer's data and get the change approved.
How should I measure wall height?
Follow the drawings and spec, and check whether the partition goes to the slab or stops at a ceiling.
How much waste should I allow?
Use the waste you have measured on your own past jobs, set by material. Add it to the theoretical quantity first, then round up to whole sheets, lengths and packs.