Unit conversion in drylining quotes: per sheet, per m2, per pack
Last updated 2026-11-05 · 5 min read
To compare drylining prices quoted per sheet, per m², per length or per pack, convert them all to one working unit per item. Divide a sheet price by its area, a length price by its metres, and a box price by its fixings, then multiply by the rate per m². Round up to whole packs only at the end.
Your BoQ is in square metres and linear metres. Your merchant sells by the sheet, the length, the box, the roll and the bag. Somewhere between the two, someone has to convert, and that is where a clean estimate can go wrong without anyone noticing.
The maths is not hard. The problem is lots of small sums, done quickly, on items that all look alike.
Which working unit should you use for each item?
Pick one unit for each type of material and stick to it across every quote:
- Boards: per m2
- Studs, channels and trims: per linear metre
- Screws and fixings: per single fixing
- Insulation: per m2
- Tape: per linear metre
- Jointing compound: per kg, or per m2 once you know the coverage
The unit does not matter as much as using the same one everywhere. Write the conversion down next to each item so that someone else can check it.
How do you convert a price per sheet to per m²?
Work out the sheet area in square metres, then divide the sheet price by it.
Sheet area is length times width, in metres. A 2.4 m by 1.2 m board is 2.88 m2. A 3.0 m by 1.2 m board is 3.6 m2. A 2.4 m by 0.9 m board is 2.16 m2.
So:
- Price per m2 = price per sheet / sheet area
- Sheets needed = area in m2 / sheet area, rounded up
The classic slip is assuming every line is the same size. Two merchants can quote what looks like the same board in different sizes. If you compare the sheet prices directly, the bigger sheet looks dearer when it may be cheaper per m2.
How do you convert per length and per pack to per metre?
Metal is sold by the length, and often in bundles.
- Price per metre = price per length / length in metres
- Price per metre from a pack = pack price / (number in pack x length of each)
Check whether the quoted price is per length or per bundle. The description may not make it obvious, and it is a costly thing to misread. If a rate looks far too low or far too high against the other quotes, this is the first thing to look at.
Remember that a stud's length is not the same as the height of your wall. If your walls are 2.7 m high and you buy 3.0 m studs, you pay for the offcut unless you can use it elsewhere. Price what you buy, not only what you fix.
How do you convert a price per box to per m²?
Fixings arrive in boxes, so the box quantity matters. Two boxes of similar screws can hold different numbers.
- Price per screw = box price / number in box
- Cost per m2 = price per screw x screws per m2
Take the number of screws per m2 from the manufacturer's data for the system, as it depends on the build-up. Do not assume it.
How do you convert insulation, tape and compound?
Insulation is usually sold in packs, with the pack's area marked on it or in the data sheet. Pack area varies by product and thickness, so look it up each time.
- Price per m2 = pack price / m2 in pack
- Packs needed = area / m2 in pack, rounded up
Jointing compound depends on coverage. Find the manufacturer's stated coverage, then work out a cost per m2 of board finished. Tape works the same way: find the metres on the roll and estimate metres of joint per m2.
When should you round up?
You can only buy whole sheets, packs and boxes, so do the sums on the true quantity first, and add waste, then round up to what you must buy.
A worked example, for illustration only. Say you have 54 m2 of single-layer board to cover, using 2.88 m2 sheets. 54 / 2.88 = 18.75, so that is 19 sheets before any waste allowance. Add your waste figure to the 54 m2 first, then divide and round up.
On a large job, rounding each area separately can overstate what you need. Work out the total, then call it off by area.
How do you check your conversions?
Before a price goes out, do the sum backwards on the largest lines: quantity bought x price per bought unit should equal the line total. Compare the rate per m2 across merchants too. A rate that is several times out usually means a unit mistake, not a bargain.
FixMargin is software for UK drylining and interiors subcontractors. On a free account you can load one price list and confirm or map the items it does not recognise, and a sample project is there after signup. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Should I price boards per sheet or per m2?
Compare per m2, then buy by the sheet. Check what the job really needs in whole sheets.
Why does my rate look too low?
Often a pack price has been read as a single-item price, or the reverse. Check the unit on the quote.
Where do I find coverage figures?
In the manufacturer's data sheet for that product.