Payment applications and retention for drylining subcontractors
Last updated 2026-11-05 · 4 min read
A payment application is your claim for the value of work done to a date. For a drylining subcontractor it should show the contract value, work completed by area or item, agreed variations, materials on site where allowed, the retention deducted and previous payments. Send it on the dates your subcontract sets, and track retention until it is released.
Getting paid is part of the margin. A job priced well can still strain your cash if applications go in late, leave out variations, or nobody chases the retention at the end. The work here is routine, and it pays to make it a habit.
What is a payment application?
It is your statement of the value of work done up to a valuation date, usually monthly. The main contractor assesses it and pays the amount they agree, less retention and previous payments.
Your subcontract sets the rules: the valuation dates, when the application is due, how long they have to pay, and what notices either side must give. Read those terms at the start of the job and put the dates in your calendar. If anything is unclear, take proper advice rather than guess.
What should an application include?
Keep it clear enough that someone can check it quickly:
- The contract sum and your reference
- Work done, by area, floor or BoQ item, with the percentage or quantity complete
- Agreed variations, and submitted ones shown separately
- Materials on site, if your subcontract allows them to be claimed
- The gross value to date
- Retention deducted, and previous payments
- The amount now due
Attach evidence for anything that might be questioned: measured quantities, photos, and signed daywork sheets.
How is retention worked out?
Retention is a percentage of the gross value held back by the main contractor, usually released in parts: some at practical completion and the rest after the defects period. The percentage and the release points are in your subcontract.
For illustration only: if the gross value to date is £40,000 and retention is 5%, £2,000 is held back. If previous payments total £30,000, the amount due is £40,000 - £2,000 - £30,000 = £8,000. On a £120,000 job at 5%, £6,000 of your money can sit unpaid until the end of the defects period.
How do you make sure retention comes back?
Retention is easy to forget because it is due months after you leave site. Keep a list of every job with retention held: the amount, the release dates and who to contact. Diary the dates, and apply for each release in writing when it falls due.
What are the common mistakes?
Missing the application date, so a month's work waits for the next cycle. Leaving variations off because they are not yet agreed. Claiming more than the work on site supports, which damages trust. And not checking the payment against your application, so short payments go unnoticed.
FixMargin is software for UK drylining and interiors subcontractors. A working estimator went from signup to a priced bill of quantities in under 15 minutes, with no help. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
How often should I apply for payment?
On the dates your subcontract sets, usually monthly. Put every valuation date in your calendar at the start of the job.
Can I claim for variations that are not agreed yet?
Show them separately as submitted, with evidence. Only agreed value is secure, but listing them keeps them visible.
What percentage is retention?
It is set in your subcontract. A figure such as 3% to 5% is common, so check your own terms.