Drylining tender checklist: what to check before you submit

Last updated 2026-11-08 · 5 min read

Short answer

Before you submit a drylining tender, check that you priced the latest drawings and specification, that the take-off covers each system, height band and linear item, that rates come from your own outputs and current merchant prices, and that access, programme, exclusions and payment terms are stated. Then read the total back against the job.

Most tender mistakes are not in the arithmetic. They are in what was left out, what was assumed and never written down, or a revision that arrived after the take-off was done. A short checklist, run the same way on every tender, catches most of them.

Have you priced the right documents?

Start with what you were sent:

  • Drawing register checked, and every drawing priced is the latest revision
  • Specification read in full, including the preliminaries and the drylining section
  • Partition and lining types matched between drawings and specification
  • Fire and acoustic requirements noted for each type
  • Tender queries sent, and every answer received is reflected in the price
  • Addenda and late revisions logged, with the date each one arrived

If two documents disagree, price the one you can defend and say so in the offer.

Is the take-off complete?

Read the take-off against the drawings one more time:

  • Every partition and lining type measured, grouped by height band
  • Openings deducted the same way throughout, as your measurement rules say
  • Linear items listed: deflection heads, reveals, corners, abutments, bulkheads
  • Numbered items listed: door openings, access panels, pattresses and boxing in
  • Areas that are not yours left out, and noted as excluded

The guide to drylining take-off covers measuring by system in more detail.

Are the rates built properly?

Each rate should be one you could explain line by line:

  • Materials taken from the manufacturer's data for the system, with waste from your own jobs
  • Labour from your own outputs, split by activity
  • A day rate that carries the full cost of the operative, not wages alone
  • Taller height bands priced with lower outputs or separate access
  • Linear and numbered items priced on their own lines

Are the merchant prices current?

  • Quotes requested against the full bill, not a sample of lines
  • Every line priced in the same unit as the take-off
  • Quote validity covers the tender period and the likely start date
  • Delivery charges, minimum orders and any long-lead items noted

Have you priced the job around the work?

The work is only part of the cost. Check:

  • Access: towers, podiums, scaffold and who provides each
  • Distribution: hoists, lifts and moving materials to each floor
  • Storage and waste removal, and who pays for skips
  • Supervision for the length of the programme
  • Programme: the number of visits, phasing and any out-of-hours work

What should the offer say?

The offer protects the price. Make sure it states:

  • What is included, by system and area
  • Exclusions, such as items by others or work outside your scope
  • Assumptions, such as wall condition, access and the programme you priced
  • Validity of the price
  • Payment terms, retention and how variations will be valued

The guide to setting out a drylining quote covers the layout.

How do you check the final total?

Read the total back against the job before it goes. Compare the cost per m² of floor area, or per m² of partition, with similar jobs you have priced. A figure far out of line usually means something was missed or counted twice.

For illustration only, with assumed figures: the take-off has 1,250 m² of partition at £42.00 per m², which is £52,500.00. Linings add £6,300.00 and numbered items £4,200.00, so the total is £63,000.00. Reading the take-off back against the specification finds 85 m of deflection head not yet priced. At £14.00 per m that adds £1,190.00, so the tender total becomes £64,190.00.

A second person reading the tender before it goes catches more than the estimator reading it again. The guide to pricing a drylining job covers the build-up behind the total.

FixMargin is software for UK drylining and interiors subcontractors. The free calculator works out material quantities for supported partition and wall lining systems, and the library does not yet cover every manufacturer. A free account includes 50 take-offs a month. You can try the calculator on your own walls.

Frequently asked questions

What is most often missed in a drylining tender?

Linear items such as deflection heads and reveals, access and distribution, and late drawing revisions. Each one should have its own line in the checklist.

Should exclusions be listed in the tender?

Yes. List every exclusion and assumption in the offer, so the price can be defended when the scope is questioned later.

How long should a merchant quote be valid for a tender?

Long enough to cover the tender period and the likely start date. Ask the merchant for the validity in writing with the quote.

Who should check a tender before it is submitted?

Someone other than the estimator who priced it. A second reader is more likely to spot a missing system or a total that looks out of line.