Qualifications and exclusions on a drylining quote

Last updated 2026-11-10 · 6 min read

Short answer

An exclusion names work your price does not include. A qualification states a condition the price depends on, such as access, programme or the drawings you priced. On a drylining quote, write each one specifically, tie it to a drawing, area or item where you can, and check that it is carried into the subcontract order before you sign.

Exclusions and qualifications decide what the price buys. Written well, they turn a later argument into a simple variation. Written badly, or lost when the order arrives, they leave you carrying risk you never priced.

What is the difference between a qualification and an exclusion?

The words are used loosely, but keep them apart:

  • Exclusion. Work outside your price. "Fire stopping to service penetrations is excluded."
  • Qualification. A condition the price depends on. "Our price assumes one continuous visit per floor."
  • Assumption. A fact you have relied on where the documents are silent. "We have assumed slab-to-slab heights do not exceed those shown on section A-301 rev B."
  • Clarification. How you have read something unclear. "We have read note 4 on A-210 as applying to corridor walls only."

Each tells the main contractor what would change the price.

Which exclusions are common on drylining packages?

The table gives example wording to adapt, not a standard list. Include only what is genuinely outside your price on this job.

ItemExample wordingWhy it matters
Fire stoppingFire stopping to service penetrations through our partitions is excluded.Often expected by the main contractor unless named
Builders' workForming openings for services after our boarding is complete is excluded.Return visits are slow and costly
CeilingsSuspended ceilings and bulkheads not shown on our priced drawings are excluded.Stops the package growing by implication
Making good to others' workMaking good damage caused by other trades is excluded.Otherwise it arrives as a contra charge
Protection after handoverProtection of our finished work after each area is handed over is excluded.Damage after handover is hard to resist
DesignDesign responsibility, other than selecting from the specified systems, is excluded.Design liability may not be covered by your insurance
Out-of-hours workWork outside normal working hours is excluded.Changes labour cost and supervision
On-site testingAcoustic and other on-site testing is excluded.Testing and any remedial work carry cost
AttendancesHoist, skips, welfare, power and lighting are by the main contractor.Each one has a real cost if it falls to you

For illustration only, with assumed figures: if fire stopping on a package would cost an assumed £4,200 and the exclusion is missing, the main contractor may treat it as included. The same item, clearly excluded, becomes a separate price for £4,200 plus your overheads and profit.

How should you write them?

  • Be specific. Name the item, the area, and the drawing or specification clause.
  • Avoid blanket wording such as "anything not shown". It is easy to challenge and often ignored.
  • Keep the list short. Boilerplate hides the items that matter.
  • Put them in the quote itself, not only in a covering email.
  • State how excluded work will be priced if it is instructed, for example at your quoted rates or daywork rates.

The guide to setting out a drylining quote shows where exclusions sit in the quote, and the drylining tender checklist helps you find them before you submit.

How do main contractors treat a qualified tender?

When comparing tenders, a main contractor will often price your exclusions at its own figure and add them to your total, so that every bid covers the same scope. Heavy qualification can therefore make a keen price look expensive. Where the tender clearly asks for an item, it is usually better to price it and state your assumption. If an exclusion is essential, say why in one line.

How do you make sure they survive into the subcontract?

This is where most qualifications are lost. When the order arrives:

  • Check whether it lists your quote, with its date and reference, as a contract document
  • Look for wording that cancels earlier correspondence or says all qualifications are withdrawn
  • Compare the scope description in the order with your exclusions, line by line
  • Raise any difference in writing before you sign or start work

What you actually agreed depends on the documents and the order of events, so take proper advice where the difference is large. Once on site, any excluded work you are asked to do should be recorded as a change, as the guide to recording variations explains.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Do the exclusions in my quote always form part of the contract?

No. It depends on the subcontract documents. Check that the order refers to your quote and does not withdraw its qualifications.

How many exclusions should a drylining quote have?

As many as the job needs and no more. A short, specific list is read. A long one of boilerplate is often ignored.

Can I exclude something the tender asks me to price?

You can, but expect it to be priced against you when tenders are compared. State the reason in one line if you do.

Should exclusions say how the work would be priced?

Yes, where you can. Referring to your quoted rates or daywork rates gives both sides a basis if the work is later instructed.