How main contractors compare subcontract tenders
Last updated 2026-11-10 · 6 min read
Main contractors compare subcontract tenders in stages: they check each bid is compliant, level the prices so that every bid covers the same scope, review qualifications to the terms, then look at programme, resources and quality. The lowest headline price often does not survive levelling. The bid that wins is usually the one that is easiest to compare.
This is often called tender adjudication. Knowing what happens to your price after you send it helps you write a tender that reads the way you meant, and makes sense of feedback when you lose.
What happens first when a tender arrives?
A compliance check. Before anyone compares prices, the buyer or commercial manager checks that each bid:
- Arrived by the return date, in the format asked for
- Priced the documents and revisions issued, including any addenda
- Used the pricing document or bill of quantities provided, filled in completely
- Answered the pre-qualification questions, with insurances and health and safety information
- Stated whether the subcontract terms are accepted, or listed the changes asked for
A bid that fails here may be set aside, or sent back with questions. Either way, it starts behind.
What does levelling a tender mean?
Levelling makes the bids comparable. The main contractor works out what each bid would cost if it covered exactly the scope in the enquiry. They typically:
- Add for exclusions and omissions, at their own estimate of the cost
- Adjust for documents, where a bid priced an older revision or missed a drawing
- Check arithmetic and quantities, and query errors with the bidder
- Compare like items, line by line, to find prices far above or below the others
- Separate provisional sums and dayworks, so they are treated the same in every bid
The guide to qualifications and exclusions explains why an essential exclusion needs a reason, and the guide to provisional sums vs PC sums covers how those sums are handled.
What does a levelled comparison look like?
For illustration only, with assumed figures. Three drylining bids for the same package, with the main contractor's own estimates for each adjustment.
| Line | Bidder 1 | Bidder 2 | Bidder 3 |
|---|---|---|---|
| Headline price | £152,000 | £158,000 | £149,500 |
| Deflection heads excluded | +£6,500 | ||
| Distribution from loading bay excluded | +£3,000 | ||
| Making good excluded | +£4,000 | ||
| Return visits excluded | +£2,500 | ||
| Level 3 priced from an old drawing revision | +£5,000 | ||
| Levelled price | £161,500 | £158,000 | £161,000 |
| Programme | Meets the programme | Two weeks longer than asked | Meets the programme |
| Terms | Asks for shorter payment terms | Accepts | Accepts |
The lowest headline price, bidder 3, becomes the second highest once levelled. Bidder 2 is now lowest, but its longer programme is the question for the next stage. Bidder 1's exclusions may cost less in reality than the main contractor's estimate, but nobody is there to argue it.
How are qualifications to the terms judged?
Changes you ask for to payment terms, retention, discounts, liabilities or programme move risk back to the main contractor. Some put a value on that risk and add it to your levelled price. Others treat a long list of changes as a reason to go elsewhere. A short list of changes that really matter is easier to accept.
What beyond price do they look at?
- Programme and resources: whether you can meet the sequence with the labour you have, and your lead-in
- Experience: similar jobs, references and the supervisors you would put on site
- Method: how you would handle access, distribution and other trades
- Track record: how you performed on their last job, including paperwork, valuations and snagging
- Financial standing: whether you can carry the job's costs until payments arrive
On larger or public projects, quality may be scored against stated criteria and weighted against price. Where the enquiry sets out how bids are scored, answer each criterion directly.
What happens after the comparison?
The main contractor usually shortlists one or two bidders, asks clarification questions, and may meet them to go through scope and programme. Some ask for a best and final offer. Answer clarifications in writing, record them in your tender register, and make sure anything agreed in a meeting is carried into the subcontract order.
How do you make your tender easy to compare?
- Price in the format asked for, and complete every line
- List the drawings and revisions priced
- Price items the enquiry asks for, and state your assumptions, rather than excluding them
- Keep qualifications and exclusions short, specific and explained
- State your programme, resources and lead-in in plain terms
- Run the drylining tender checklist before you submit
When you lose, ask where your bid ranked once levelled. Tracked over time, that shows whether you lose on price or on how the bid reads.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Does the lowest subcontract tender always win?
No. Bids are usually levelled for scope first, and programme, terms and quality are weighed as well. The lowest headline price is often not the lowest levelled one.
What is tender levelling?
Adjusting each bid so that every one covers the same scope, by adding for exclusions and omissions and correcting errors, so the prices can be compared fairly.
Will a main contractor tell me why I lost?
Many will give some feedback if asked, such as your ranking or whether price was the deciding factor. Ask every time.
Can I change my price after the return date?
Only if the main contractor invites it, for example after clarifications or in a request for a best and final offer.