Provisional sums vs PC sums

Last updated 2026-11-10 · 6 min read

Short answer

A provisional sum is an allowance for work that cannot be fully described at tender, replaced later by the value of the work instructed. A prime cost (PC) sum is an allowance for goods or work from a named supplier, replaced by the actual cost. Carry both as given, and add profit and fixing to a PC sum where asked.

Both appear in tender documents as fixed figures you did not set. They look like money in the price, but neither is yours until the work is instructed and valued. Knowing how each is adjusted stops you counting them as margin, or missing what you should add.

What is a provisional sum?

It is a sum the person preparing the tender puts in for work that exists but is not yet designed or measurable. On a drylining package, that might be making good after other trades, extra fire stopping, or partitions to an area still being designed.

Bills prepared under the RICS measurement rules (NRM2) split provisional sums into two kinds:

  • Defined. Enough is known about the work, such as its nature, scope and how it is fixed, for you to allow for it in your programme and preliminaries.
  • Undefined. Too little is known. Programme and preliminaries can be adjusted when the work is instructed.

Not every tender follows NRM2, so read how your documents describe each sum. When the work is instructed, it is usually valued under the subcontract's variation rules and the provisional sum is omitted.

What is a PC sum?

A prime cost sum is an allowance for goods or work to be supplied by a named supplier or specialist, where the price is not yet fixed. It comes from the older practice of nominating suppliers and subcontractors, and you still meet it in bills, often for items such as specialist boards, access panels or doors from a named source.

The PC sum covers the cost of the item itself. The bill usually gives you separate lines to price:

  • Profit. Often as a percentage on the PC sum.
  • Fixing or attendance. The labour and other costs of installing or handling the item.

When the actual cost is known, the PC sum is replaced by it, and the profit line is usually adjusted in proportion.

How do the two compare?

PointProvisional sumPC sum
What it coversWork not yet fully describedGoods or work from a named source
Who sets the figureThe tender documentsThe tender documents
What you addUsually nothing to the sum itselfProfit and fixing or attendance, where asked
How it is adjustedReplaced by the value of instructed workReplaced by the actual cost
If never instructedOmittedOmitted, with the profit and fixing
Effect on preliminariesDepends on defined or undefinedAllow for fixing and handling in your price

Contingency is different again. It is an allowance for risk, held by the client or main contractor, and not tied to any described work.

How are they adjusted on a real job?

The example below is for illustration only, with assumed figures.

At tender:

ItemAmount
Measured drylining work£84,000
Provisional sum (defined): making good after mechanical and electrical trades£3,000
Provisional sum (undefined): additional fire stopping£2,500
PC sum: access panels from a named supplier£1,800
Profit on PC sum at 5%£90
Fixing access panels£960
Tender total£92,350

When the work is valued:

ItemChange
Making good instructed and valued at £2,450-£550
Fire stopping never instructed-£2,500
Access panels actually cost £2,100+£300
Profit at 5% on £2,100, which is £105+£15
Adjusted total£89,615

The £5,500 of provisional sums at tender became £2,450 of work. Had that £5,500 been treated as secured turnover, the job would have looked bigger than it was.

What should you check when you price them?

  • Read the description of each sum and whether it is defined or undefined
  • Do not add your own margin to a provisional sum unless the documents ask you to
  • Price profit and fixing on PC sums where lines are given, and say if they are missing
  • Ask how instructed work will be valued, and check your rates cover it
  • Keep provisional sums apart from measured work in your bill of quantities

When a provisional sum is instructed, treat it like any other change and keep the same evidence, as the guide to recording variations explains. If you are adding profit to a PC sum, be clear whether the percentage is a markup or a margin.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Can I add profit to a provisional sum?

Not usually. You carry the sum as given, and when the work is instructed it is valued under the subcontract, which normally includes your overheads and profit.

Who decides what a provisional sum is spent on?

The work is instructed under the contract, usually by the main contractor or the contract administrator. Until then, it is only an allowance.

Are PC sums still used?

Less than they were, but you still meet them in bills and tender documents, often for goods from a named supplier.

What happens if a provisional sum is never spent?

It is omitted, and the total goes down by that amount.