Drylining BoQ example: a worked layout
Last updated 2026-11-08 · 7 min read
A drylining BoQ lists the work in sections by area and type, with a reference, a description naming the build-up and height, the unit, the quantity and the rate on each line. Square metres, linear metres and numbered items sit on separate lines. The worked layout below shows one floor, ready to copy into a spreadsheet.
A bill of quantities is what the main contractor reads, values and later remeasures against. If a line is vague, it is argued about. If units are mixed, it cannot be checked. The layout matters as much as the numbers.
What sections should a drylining BoQ have?
Split the BoQ the way the job is built, then by the kind of measurement:
- General items. Access, waste removal, protection and anything else priced as an item.
- Partitions. One line per partition type and height band.
- Wall linings. Linings, independent walls and shaft walls, each type on its own line.
- Linear items. Deflection heads, beads, trims and perimeter sealant, in metres.
- Numbered items. Door openings, access panels and similar, counted.
- Provisional sums and daywork. Anything you cannot measure yet, clearly marked.
If ceilings are in your package, give them their own section. Repeat the partition, lining, linear and numbered sections for each floor or zone if you will buy and build by area.
How should each line be described?
Write each description so another estimator could price it without the drawings:
- The system reference from the drawings or schedule
- Stud size and centres
- Board type, thickness and number of layers each side
- Insulation, where specified
- The height band, such as up to 3.0 m or 3.0 to 4.2 m
- Any fire or acoustic performance named in the specification
Keep heights apart. A taller wall can need a deeper stud, tighter centres and more access, and the guide to stud centres and deflection heads explains why that changes the price.
What does the worked layout look like?
Here is an example for one floor, with the rates and totals left out:
| Ref | Description | Unit | Qty | Rate | Total |
|---|---|---|---|---|---|
| Section A: General items, level 2 | |||||
| A1 | Mobile tower access for own use | item | 1 | ||
| A2 | Removal of drylining waste to main contractor's skip | item | 1 | ||
| Section B: Partitions, level 2 | |||||
| B1 | Partition type P1: 70 mm C stud at 600 mm centres, one layer 12.5 mm standard board each side, up to 3.0 m high | m² | 420 | ||
| B2 | Partition type P2: 92 mm C stud at 600 mm centres, two layers 15 mm fire-rated board each side, insulation in cavity, up to 3.6 m high | m² | 185 | ||
| Section C: Wall linings, level 2 | |||||
| C1 | Lining type L1: independent lining on 50 mm C stud, one layer 12.5 mm moisture-resistant board, up to 3.0 m high | m² | 140 | ||
| Section D: Linear items, level 2 | |||||
| D1 | Deflection head to partition type P2, to specification | m | 64 | ||
| D2 | Acoustic sealant to perimeter of partition type P2, both sides | m | 210 | ||
| D3 | Corner bead to external angles | m | 96 | ||
| Section E: Numbered items, level 2 | |||||
| E1 | Form opening for single door in partition type P1, including head and jamb reinforcement | nr | 12 | ||
| E2 | Access panel 600 x 600 mm in partition type P2, supply and fix | nr | 6 |
Notes at the foot should give the drawing numbers and revisions measured from, and say whether quantities are net or include waste.
What does the blank layout look like?
Copy this table into a spreadsheet and add a section heading row for each section and area.
| Ref | Description | Unit | Qty | Rate | Total |
|---|---|---|---|---|---|
| Section: | |||||
In a spreadsheet, make the total a formula, quantity times rate, and add a subtotal at the end of each section. A summary page that lists the section subtotals is what most main contractors read first.
How do you price the lines?
Each rate is built up from materials, labour, access and overheads for that system. The guide to pricing a drylining job sets out what the rate should hold.
For illustration only: if B1 is priced at an assumed £36.50 per m², the line total is 420 x £36.50 = £15,330. If B2 is an assumed £68.00 per m², it comes to 185 x £68.00 = £12,580. Showing both totals lets the client see where the money sits, and lets you check that the heavier system carries the heavier rate.
What sits underneath the BoQ?
The client sees system lines. Your buyer needs components. Keep the component quantities for each system line in your take-off, on a separate sheet or tab, so the BoQ stays readable and the material list stays traceable to it.
When a line changes after a drawing revision, change the take-off and the BoQ together, and note the revision against the line.
Which mistakes should you avoid?
- Adding square metres of different systems into one line
- Leaving out the height band, so tall walls are priced as short ones
- Counting a linear item both in the system rate and as its own line
- Leaving out drawing revisions, so nobody can tell what was measured
- Rates marked "inclusive" with no list of what they include
FixMargin is software for UK drylining and interiors subcontractors. The free calculator works out material quantities for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ is on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Should a BoQ show rates or only totals?
Show rates as well as totals where the tender allows. Rates give both sides an agreed basis for valuing changes and remeasuring the work.
How detailed should each description be?
Detailed enough that another estimator could price the line without the drawings. Name the system, the build-up, the height band and the area.
Should the BoQ quantity include waste?
Measure net quantities in the BoQ and carry waste in the rate or the component take-off. Say which in your notes, so the allowance is not deducted twice.
Can I copy this layout?
Yes. Copy the tables on this page into your own spreadsheet; there is no download.