Deflection heads and stud centres: when each is required

Last updated 2026-11-24 · 4 min read

Short answer

Stud centres and deflection head details come from the manufacturer's tested system, not from habit. The system data sets the stud size, gauge and spacing for each wall height and board build-up, and the head detail needed where the structure above can move. Read them for each partition type, then price the studs, head track and extra labour they require.

Stud centres and head details are easy to treat as standard: 600 mm centres and a head track, every time. On many jobs that is wrong, and the difference shows up in materials, labour and sometimes in whether the wall meets its fire or height requirement.

Where do stud centres come from?

The manufacturer's published data for each system gives the frame: stud size and gauge, the spacing, and the maximum height that combination can reach. The spacing depends on the board, the number of layers, the height and the performance the wall must achieve.

Do not assume the spacing. A taller wall, a heavier board or a fire or acoustic requirement can each change it, and the system data tells you how.

Why do taller walls need more?

As a partition gets taller it needs a stronger frame to stay within its limits. Depending on the system, that can mean a deeper stud, a heavier gauge, closer centres, or boxed studs. Each of those changes the material quantity and the time to build.

Measure your walls in height bands, so each band can be checked against the system's limits and priced with the right frame.

What is a deflection head, and when is it required?

A deflection head lets the structure above a partition move, for example a concrete slab or steel deck deflecting under load, without crushing the wall or opening a gap. It is usually a deeper head track that allows the studs to slide, with the boards fixed so the movement can happen.

Where the wall is fire-rated, the deflection head must keep the rating, so it has to follow the tested detail exactly. The specification or the structural engineer should tell you how much movement to allow.

How do these details change the price?

Closer centres mean more studs and more screws. A deflection head means a different track, often a second track, and careful fixing that takes longer than a standard head.

For illustration only: a wall 15 m long at 600 mm centres needs about 26 studs, counting both ends (15 / 0.6 = 25 spaces, so 26 studs). At 400 mm centres the same wall needs about 39 studs (15 / 0.4 = 37.5, rounded up to 38 spaces, so 39 studs), half as many again. Your real centres must come from the system data for that height and build-up.

How do you check them before pricing?

For each partition type, write down the system, the height band, the stud size and centres, and the head detail. Check every row against the system data. If the drawings do not say whether a deflection head is needed, ask before you price it either way.

FixMargin is software for UK drylining and interiors subcontractors. A working estimator went from signup to a priced bill of quantities in under 15 minutes, with no help. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Are 600 mm stud centres always enough?

No. The spacing depends on the system, height, board and performance, so take it from the system data.

Does every partition need a deflection head?

No. It is needed where the structure above can move. The specification or the engineer should say where.

Can a fire-rated wall use any deflection head?

No. It must use the tested head detail for that system, or the rating may not apply.