Attendances: what a subcontract usually includes

Last updated 2026-11-10 · 6 min read

Short answer

Attendances are the facilities and services the main contractor provides for a subcontractor's work. General attendance usually covers shared items such as welfare, common lighting and power points, existing scaffold and skips. Special attendance covers items for one package, such as unloading, hoisting or dedicated storage. Your subcontract decides what is provided, so agree a written schedule before you sign.

Attendances are a quiet source of cost. If you priced on the basis that the main contractor provides power, a hoist and skips, and one of them is not there, you pay for it. A short schedule agreed at the start avoids most of the argument.

What is the difference between general and special attendance?

  • General attendance is what the main contractor provides to all subcontractors as part of running the site. It is usually priced in the main contractor's own preliminaries.
  • Special attendance is something provided for a particular package. It is usually described in the enquiry, and may be priced separately by the main contractor.

The exact lists vary between contracts and companies. Do not rely on custom. Read the enquiry, the preliminaries and the subcontract order, and ask where they are silent.

What does each one typically cover?

The table shows a typical split for an interiors package. It is a starting point for your own checks, not a rule.

ItemTypicallyWhat to check
Welfare, canteen and toiletsGeneralCapacity for your peak gang size
Site security and secure accessGeneralWorking hours the site is open
Common lightingGeneralWhether it is adequate for boarding and finishing
110V power at distribution pointsGeneralDistance to the work area and who provides leads
Use of existing scaffoldGeneralWhether it needs adapting for your work
Skips at a central pointGeneralWho loads them and whether waste must be segregated
Hoist or goods lift, sharedGeneral or specialBooking slots and car size
Unloading deliveriesSpecial, if agreedWho unloads, and with what equipment
Distribution to each floorSpecial, if agreedFrom where to where
Dedicated storage areaSpecial, if agreedDry, secure and close to the work
Task lightingOften yoursLighting levels needed for finishing work
Cleaning your own work areasOften yoursHow often, and where the waste goes

Distribution on tall jobs is covered in detail in the guide to distribution and hoisting.

What should an attendance schedule look like?

Agree a schedule like this one before you sign, and attach it to the subcontract order. Fill in one line per item. The entries below are examples only.

AttendanceProvided byWhere and whenCharge, if anyYour cost if not provided
WelfareMain contractorGround floor, site hoursNone
Power, 110VMain contractorEach floor, distribution boardNone
HoistMain contractorBooked slots, 07:30 to 17:00None
SkipsMain contractorCentral compoundNone
UnloadingSubcontractorLoading bay
StorageMain contractorAgreed area on each floorNone

The last column is for your own build-up. Pricing what each attendance would cost you if it were missing shows which ones matter most to your price.

What happens if an attendance is not provided?

For illustration only, with assumed figures. A subcontractor priced on the basis of a main contractor's hoist for its 140 distribution trips. The hoist is not available for four weeks, and the gang carries materials up the stairs instead. Each trip takes an assumed 30 minutes longer for two operatives, and 40 trips fall in that period: 40 x 0.5 hours x 2 operatives = 40 labour hours. At an assumed £30 per hour, that is £1,200 of extra cost.

Whether you can recover it depends on what the subcontract says about attendances, and on your records. Note the dates, the trips affected and the time lost, and notify the main contractor in writing as your subcontract requires.

How do attendances affect a tender?

When a main contractor compares tenders, an exclusion such as "hoist by others" is normal, but a long list of attendances you expect can be priced against you. The guide to how main contractors compare tenders explains how this is done. State the attendances you rely on, briefly, and in the same terms the enquiry uses.

Can the main contractor charge you for attendances?

Some subcontracts allow charges for services such as cleaning, waste removal or use of plant, or deduct the cost if you do not clear your own waste. These often appear as contra charges. Check the clauses before you sign, and read the guide to contra charges for how to check any that arrive. The guide to qualifications and exclusions shows how to word the attendances you have assumed.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

What is general attendance in construction?

The shared facilities the main contractor provides to all subcontractors, such as welfare, common lighting, power points, existing scaffold and skips. Check your subcontract for the exact list.

What is special attendance?

A service provided for one package, such as unloading, hoisting, distribution or dedicated storage. It should be named in the enquiry or subcontract.

Should my tender list the attendances I need?

Yes, briefly, and in the enquiry's own terms. That way the main contractor knows what your price relies on.

Can attendances change after I sign?

Only as the subcontract allows. If an agreed attendance is withdrawn, record the effect and notify the main contractor in writing.