Contra charges: how to check and challenge them

Last updated 2026-11-10 · 6 min read

Short answer

A contra charge is a cost the main contractor deducts from your payment because it says you caused it, such as cleaning, damage or rework. To check one, find the clause it relies on, whether notice was given as required, what shows you caused the cost, and whether the amount is reasonable. Dispute in writing what does not stand up.

Contra charges are often small and easy to let go. Over a job they add up, and because they come off the payment rather than being invoiced, they can quietly take the margin out of a well-priced package.

This guide sets out a general approach. It is not legal advice. Your subcontract decides what can be charged and how, so read its terms and take proper advice where a large sum is in dispute.

What usually turns up as a contra charge?

On drylining and interiors packages, common items are:

  • Cleaning and rubbish removal said to be left by your gangs
  • Damage to other trades' work, such as scuffed decorations or broken glazing
  • Making good to your own work carried out by others
  • Use of the main contractor's labour, plant or access
  • Costs said to flow from your delay

Some are fair. Many arrive as a share of a site-wide cost with no working shown.

What does your subcontract need to say?

A deduction should rest on a term of your subcontract, usually a set-off or contra charge clause. Look for:

  • What can be charged, and whether it is limited to costs actually incurred
  • Whether you must be given notice and a chance to put the problem right first
  • Any time limit for raising a charge
  • How shared site costs are split between trades

If a charge is taken off the notified sum, it will generally need to appear in a valid pay less notice under the Construction Act. A deduction that appears only on a remittance advice deserves a closer look, and a question in writing.

How do you check a contra charge?

Run every charge through the same five questions:

  1. Basis. Which clause allows it?
  2. Notice. Were you told at the time, and given the chance to fix it yourself where the clause requires that?
  3. Cause. What shows your gang caused it, rather than another trade?
  4. Amount. Is it the actual cost, with invoices or timesheets behind it?
  5. Share. If it is a shared cost, how was your share calculated?

Your own records do most of the work here. Dated photos at handover of each area, and daily site reports that record who was working where, are often what settles a cleaning or damage charge.

What should a contra charge register look like?

Keep one register per job, and update it each time a charge arrives. The example below is for illustration only, with assumed figures.

RefDate receivedDescriptionAmount chargedClause citedNotice given first?Evidence suppliedYour evidenceStatusAgreed amount
CC-013 OctCleaning, level 2£640Set-off clauseNoLabour sheet, all tradesHandover photos, area cleanDisputed
CC-0217 OctReplace damaged door lining£380Set-off clauseYes, by emailPhoto, invoiceGang was on that floor that dayAccepted£380
CC-0331 OctShare of skip hire£1,150None citedNoHire invoice onlySubcontract says skips by main contractorDisputed
CC-047 NovForklift time£220AttendancesNoPlant logUse confirmed, rate queriedPart agreed£150

Here, £2,390 has been charged and £530 agreed. Carry the £1,860 still in dispute into your cost value reconciliation as a provision, so the margin you report is not overstated. The guide to the CVR template shows where that line sits.

How do you challenge a contra charge?

Reply in writing, item by item, soon after the charge arrives:

  • Quote the charge reference and the payment it was taken from
  • Say whether you accept, dispute or part-accept it
  • For a dispute, give the reason: no basis, no notice, wrong party, or no evidence of the cost
  • Ask for the documents you have not seen
  • Offer a figure where you accept part of the cost

Then show the disputed amount separately on your next payment application, so it stays in front of the main contractor until it is resolved.

How do you stop contra charges before they start?

Most charges are easier to prevent than to argue. Clear your own waste to the agreed point every day, protect finished work and others' finishes near you, photograph each area when you hand it over, and get a signature where you can. If you are asked to clean or fix something, do it yourself, promptly, and record it.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Can a main contractor contra charge without warning?

That depends on your subcontract. Many clauses require notice and a chance to put things right first. Check the wording.

Should I accept small contra charges to keep the peace?

Decide case by case, but record every one. Small charges accepted without comment can become the pattern for the rest of the job.

How should shared cleaning charges be split?

The subcontract may set a method. If it does not, ask how your share was worked out and what records support it.

Do contra charges affect my retention?

They are separate deductions, but both reduce what you receive. Track each on its own line so you know what is still owed.