Daily site reports for drylining: what to record
Last updated 2026-11-08 · 6 min read
A drylining daily site report should record who was on site and for how long, what work was done by area and activity, what was delivered, what held the gang up, and any instruction received. Add dated photos. Written the same day, it becomes the record you rely on for outputs, delays, variations and disputes.
Most of what goes wrong on a drylining job is argued about weeks later. By then memory has faded, and the party with the better record usually wins. A short report every day, in the same format, is that record.
Why keep a daily site report?
Because it answers questions that come up long after the day itself:
- Outputs. How much was framed, boarded and taped, against how many hours. The guide to drylining productivity shows how to turn this into outputs per operative per day.
- Delays. When the gang could not work, why, and for how long.
- Variations. When an instruction was given, by whom, and what it changed.
- Disputes. What state an area was in when you left it, and who was working there after you.
What should the report record?
Keep it to the facts that matter, so it gets filled in every day:
- Date, job and area. Which floor, zone or room the gang worked in.
- Labour. Names or numbers of operatives, start and finish times, and any hours lost.
- Work done. Quantity completed by activity, such as framing, boarding and taping.
- Deliveries. What arrived, what was short or damaged, and what was expected but did not come.
- Delays. Waiting for access, other trades, services, materials or information.
- Instructions. Any verbal or written instruction, with the name of the person who gave it.
- Health and safety. Any incident, near miss or toolbox talk.
- Photos. Dated photos of work done, problems found and areas handed over.
What does the template look like?
Copy this table into your own form or spreadsheet, one per day:
| Item | Entry |
|---|---|
| Date | |
| Job | |
| Area worked | |
| Operatives on site | |
| Start and finish times | |
| Hours lost and why | |
| Work done by activity | |
| Deliveries received | |
| Short or damaged deliveries | |
| Delays and their cause | |
| Instructions received, and from whom | |
| Health and safety | |
| Photos taken | |
| Report by |
What does a filled-in report look like?
Here is an example of the entries:
| Item | Entry |
|---|---|
| Area worked | Level two, east corridor and rooms beside it |
| Operatives on site | Four operatives and a supervisor |
| Hours lost and why | Two hours each in the morning, waiting for the hoist |
| Work done by activity | Boarding, first layer, to the corridor partitions |
| Deliveries received | Boards and studs, as on the call-off |
| Short or damaged deliveries | Six boards damaged, noted on the delivery note |
| Delays and their cause | Hoist out of use until mid-morning |
| Instructions received, and from whom | Main contractor's site manager asked for an extra bulkhead to the corridor |
| Photos taken | Corridor before boarding, damaged boards, hoist notice |
For illustration only, with assumed figures: four operatives boarded 105 m² in an eight-hour day, which is 26.25 m² per operative per day against 35 m² in the price. The report also shows that each of them lost two hours waiting for the hoist, so 8 of the 32 hours were lost. Over the 24 hours worked, which is three operative-days, the output was 105 / 3 = 35 m² per operative per day, in line with the price.
How do you record delays and instructions?
Be specific. Write the time the delay started and ended, what caused it, and who you told. A line that says "slow day" is no use later. A line that says the hoist was out of use from start of shift until mid-morning, and the main contractor was told at the start of the day, is.
For instructions, write what was asked, who asked and when, and whether it changes the scope. Then follow it up in writing. The guide to recording variations covers what that follow-up needs. Where extra work is paid by time, record it on a daywork sheet as well.
Who should fill in the report, and when?
The supervisor or site manager who ran the gang that day, before they leave site. A report written the same day is far easier to defend than one put together at the end of the week.
Keep the reports in one place for each job, in date order, so anyone can find a given day quickly.
FixMargin is software for UK drylining and interiors subcontractors. Daily site reports and variations are on the Growth plan, and site managers file the daily report from their phone. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
How long should a daily site report take to fill in?
A few minutes, if the format is the same every day. Keep it to the facts that matter, so it gets done before the gang leaves site.
Should a daily site report include photos?
Yes. Dated photos of work done, problems and handovers are often the clearest evidence when a dispute comes up later.
Is a daily site report the same as a daywork sheet?
No. The daily report records the whole day on site, while a daywork sheet records extra work paid by time and is signed by the client's representative.
What should I do with an instruction recorded in the daily report?
Confirm it in writing to the person who gave it, the same day if you can. Then record it as a variation if it changes the scope.