Daily site reports for drylining: what to record

Last updated 2026-11-08 · 6 min read

Short answer

A drylining daily site report should record who was on site and for how long, what work was done by area and activity, what was delivered, what held the gang up, and any instruction received. Add dated photos. Written the same day, it becomes the record you rely on for outputs, delays, variations and disputes.

Most of what goes wrong on a drylining job is argued about weeks later. By then memory has faded, and the party with the better record usually wins. A short report every day, in the same format, is that record.

Why keep a daily site report?

Because it answers questions that come up long after the day itself:

  • Outputs. How much was framed, boarded and taped, against how many hours. The guide to drylining productivity shows how to turn this into outputs per operative per day.
  • Delays. When the gang could not work, why, and for how long.
  • Variations. When an instruction was given, by whom, and what it changed.
  • Disputes. What state an area was in when you left it, and who was working there after you.

What should the report record?

Keep it to the facts that matter, so it gets filled in every day:

  • Date, job and area. Which floor, zone or room the gang worked in.
  • Labour. Names or numbers of operatives, start and finish times, and any hours lost.
  • Work done. Quantity completed by activity, such as framing, boarding and taping.
  • Deliveries. What arrived, what was short or damaged, and what was expected but did not come.
  • Delays. Waiting for access, other trades, services, materials or information.
  • Instructions. Any verbal or written instruction, with the name of the person who gave it.
  • Health and safety. Any incident, near miss or toolbox talk.
  • Photos. Dated photos of work done, problems found and areas handed over.

What does the template look like?

Copy this table into your own form or spreadsheet, one per day:

ItemEntry
Date
Job
Area worked
Operatives on site
Start and finish times
Hours lost and why
Work done by activity
Deliveries received
Short or damaged deliveries
Delays and their cause
Instructions received, and from whom
Health and safety
Photos taken
Report by

What does a filled-in report look like?

Here is an example of the entries:

ItemEntry
Area workedLevel two, east corridor and rooms beside it
Operatives on siteFour operatives and a supervisor
Hours lost and whyTwo hours each in the morning, waiting for the hoist
Work done by activityBoarding, first layer, to the corridor partitions
Deliveries receivedBoards and studs, as on the call-off
Short or damaged deliveriesSix boards damaged, noted on the delivery note
Delays and their causeHoist out of use until mid-morning
Instructions received, and from whomMain contractor's site manager asked for an extra bulkhead to the corridor
Photos takenCorridor before boarding, damaged boards, hoist notice

For illustration only, with assumed figures: four operatives boarded 105 m² in an eight-hour day, which is 26.25 m² per operative per day against 35 m² in the price. The report also shows that each of them lost two hours waiting for the hoist, so 8 of the 32 hours were lost. Over the 24 hours worked, which is three operative-days, the output was 105 / 3 = 35 m² per operative per day, in line with the price.

How do you record delays and instructions?

Be specific. Write the time the delay started and ended, what caused it, and who you told. A line that says "slow day" is no use later. A line that says the hoist was out of use from start of shift until mid-morning, and the main contractor was told at the start of the day, is.

For instructions, write what was asked, who asked and when, and whether it changes the scope. Then follow it up in writing. The guide to recording variations covers what that follow-up needs. Where extra work is paid by time, record it on a daywork sheet as well.

Who should fill in the report, and when?

The supervisor or site manager who ran the gang that day, before they leave site. A report written the same day is far easier to defend than one put together at the end of the week.

Keep the reports in one place for each job, in date order, so anyone can find a given day quickly.

FixMargin is software for UK drylining and interiors subcontractors. Daily site reports and variations are on the Growth plan, and site managers file the daily report from their phone. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

How long should a daily site report take to fill in?

A few minutes, if the format is the same every day. Keep it to the facts that matter, so it gets done before the gang leaves site.

Should a daily site report include photos?

Yes. Dated photos of work done, problems and handovers are often the clearest evidence when a dispute comes up later.

Is a daily site report the same as a daywork sheet?

No. The daily report records the whole day on site, while a daywork sheet records extra work paid by time and is signed by the client's representative.

What should I do with an instruction recorded in the daily report?

Confirm it in writing to the person who gave it, the same day if you can. Then record it as a variation if it changes the scope.