Daywork sheets: what they need to get paid

Last updated 2026-11-05 · 4 min read

Short answer

A daywork sheet gets paid when it proves what was done, on whose instruction, and what it cost. It should show the instruction reference, the date and exact location, each operative's name and hours, the materials and plant used, and a signature from the main contractor's representative, ideally the same day. Price it at the daywork rates in your subcontract.

Daywork is how a lot of small extra work gets paid: making good after other trades, boxing in a pipe nobody drew, or standing time while access is sorted. It is also where money is most easily lost, because a sheet that arrives late or vague is easy to reject.

When should work be done as daywork?

Daywork suits work that cannot be measured or priced in advance: small, unplanned tasks, or work where the extent is unknown until you start. If the work can be measured, a priced variation is usually cleaner for both sides.

Check your subcontract first. It should say whether daywork needs a written instruction before you start, what rates apply, and how quickly sheets must be submitted. Follow those rules exactly.

What must a daywork sheet show?

Each sheet should stand on its own, so that someone who was not there can understand it:

  • Your sheet number and the instruction reference
  • Date, and the exact location: floor, gridline, room
  • A plain description of the work
  • Each operative's name, trade and hours, with start and finish times
  • Materials used, with quantities
  • Plant and access used, and for how long
  • Signature, printed name and date from the main contractor's representative

Add photos of the area before and after, and keep them with the sheet.

Why does the signature matter so much?

A signature on the day records that the work happened and took that time. It does not always mean the cost is agreed, but it makes the facts hard to dispute. A sheet presented weeks later, unsigned, invites an argument about whether the work was needed at all.

Make signing a routine: one sheet per task, completed by the chargehand and taken for signature before the end of the shift or the end of the week at the latest.

How do you price a daywork sheet?

Use the rates and percentages your subcontract sets for daywork, not your measured rates. Labour is usually charged by the hour at the agreed rate, with materials and plant at cost plus an agreed percentage.

For illustration only: 2 operatives for 6 hours each is 12 hours. At an assumed £32 per hour, labour is 12 x £32 = £384. Materials of £90 with an assumed 15% addition come to £103.50. The sheet total is £487.50 before any other agreed percentages. Your own rates and percentages must come from your subcontract.

How do you keep daywork from leaking?

Keep a daywork log next to the variation log: sheet number, date, value, signed or not, submitted, agreed and paid. Send the log with every application for payment so nothing drops off. Chase unsigned sheets within days, while people still remember the work.

FixMargin is software for UK drylining and interiors subcontractors. A working estimator went from signup to a priced bill of quantities in under 15 minutes, with no help. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Does a signed daywork sheet mean it will be paid?

Not always. It proves the facts, but payment still depends on your subcontract terms and the instruction behind it.

How soon should a daywork sheet be signed?

The same day if possible, and at the latest within the week. Late sheets are much easier to dispute.

Can I use daywork for work that could be measured?

You can, but a priced variation is usually clearer. Use daywork where the work cannot be measured in advance.