Cost value reconciliation (CVR) template for subcontractors
Last updated 2026-11-08 · 6 min read
A cost value reconciliation (CVR) compares the value you have really earned on a job with the cost of earning it, at the same valuation date. Adjust the value for over- or under-valuation and realistic variations, and the cost for accruals and provisions. The difference is your margin to date, which you compare with the margin in the tender.
A payment application tells you what you asked for. A CVR tells you what the job is really making. Done every month on every live job, it shows a problem while there is still time to act on it.
What goes into a CVR?
Two sides, both taken to the same date:
- Value. The gross valuation, adjusted to what you expect to be paid for the work done, plus variations at the value you realistically expect to agree.
- Cost. Every cost posted to the job, plus costs incurred but not yet invoiced, plus provisions for known risks.
- Margin. Value minus cost, as an amount and as a share of value.
- Forecast. The expected final value and final cost, and the margin at completion.
Value is taken before retention. Retention is money held back, not value you have lost.
What does the template look like?
Copy this table into your spreadsheet, one sheet per job, and fill in the right-hand columns each month.
| Line | What it covers | This month | Last month | Change |
|---|---|---|---|---|
| Gross valuation | The latest application or certificate, before retention | |||
| Over or under valuation | Adjustment so the value matches the work really done | |||
| Variations agreed | Variations valued and accepted | |||
| Variations not yet agreed | At the value you realistically expect to agree | |||
| Adjusted value | Gross valuation + adjustments + variations | |||
| Costs posted | Materials, labour, plant and subcontractors in the ledger | |||
| Accruals | Goods received not invoiced, labour worked not yet paid | |||
| Provisions | Known defects, contra charges, disputed items | |||
| Adjusted cost | Costs posted + accruals + provisions | |||
| Margin to date | Adjusted value - adjusted cost | |||
| Margin share | Margin to date / adjusted value | |||
| Tender margin | The margin the job was priced at |
Then add the forecast to completion:
| Line | What it covers | Your entry |
|---|---|---|
| Final value forecast | Contract sum + variations expected to be agreed | |
| Cost to complete | Remaining materials, labour and job costs | |
| Final cost forecast | Adjusted cost + cost to complete | |
| Final margin forecast | Final value forecast - final cost forecast |
What does a filled-in CVR look like?
Here is an example of the entries, with the amounts left out:
| Line | Example entry |
|---|---|
| Gross valuation | Application 4 as certified, levels 1 to 3 |
| Over or under valuation | Level 3 boarding applied for as complete, taping still to do |
| Variations agreed | Extra bulkhead to corridor, instruction 07 |
| Variations not yet agreed | Rework after late service changes, at the value we expect to agree |
| Costs posted | Merchant invoices and labour paid to the valuation date |
| Accruals | Board delivered last week, invoice not yet in, plus labour for the final week |
| Provisions | Contra charge raised for cleaning, under dispute |
| Tender margin | As in the final build-up of the offer |
For illustration only, with assumed figures: at month four the gross valuation is £120,000 and agreed variations add £8,000. You judge that £3,000 of the application is ahead of the work done, so the adjusted value is £125,000. Costs posted are £98,000, board delivered but not yet invoiced is £6,500 and labour worked but not yet paid is £4,000, so the adjusted cost is £108,500. The margin to date is £16,500, which is 13.2% of value, against 15.0% in the tender.
How do you keep the value honest?
Value the work done, not the work applied for. If the application ran ahead of site, take the difference off. If it fell behind, add it back.
Put unagreed variations in only at the value you expect to agree, and keep a record of each one. The guide to recording variations covers what that record needs. Leave out claims that have no agreement in sight.
How do you make sure the cost is complete?
The ledger always lags behind the site. Before you close the month:
- Check deliveries received against invoices posted, and accrue the rest.
- Accrue labour for days worked but not yet paid.
- Add provisions for known defects, contra charges and disputed items.
- Make sure costs belong to this job and not another one.
A CVR that leaves out accruals looks better than the job really is, and the next month pays for it.
How often should you run a CVR?
Monthly, on every live job, with the valuation date in line with your payment application. Compare each month with the last, and look into any line that moved more than the work on site explains.
Read the margin share alongside the trend on the job. The guide to tracking margin on a live interiors job covers what to watch between CVRs, and the guide to payment applications and retention covers the value side in more detail.
FixMargin is software for UK drylining and interiors subcontractors. On a free account you can run the calculator for supported partition and wall lining systems and load one supplier price list, confirming or mapping the items it does not recognise. The library does not yet cover every manufacturer. You can start on a free account.
Frequently asked questions
What does CVR stand for?
Cost value reconciliation. It compares the value earned on a job with the cost of earning it, at the same date.
Is a CVR the same as a payment application?
No. The application is what you ask the client for, and the CVR is your own internal check of what the job is really making.
Should retention be taken off the value?
No. Use the gross value before retention, because retention is money held back, not value lost.
Can I download this CVR template?
There is no download. Copy the tables on this page into your own spreadsheet, one sheet per job.