Distribution and hoisting on multi-storey jobs
Last updated 2026-11-10 · 5 min read
Distribution is the work of moving materials from the delivery point to the floor and room where they are fixed. On a multi-storey job, find out who does it, which hoist or lift you can use and when, and what the floors can carry. Then price it from a trip count: how many loads, how long each takes, and how many people move them.
It is easy to price boards delivered to site and forget the boards still have to reach level 6. On a tall or tightly programmed job, distribution can take as much planning as the fixing.
Who is responsible for distribution?
Read the enquiry, the preliminaries and any attendance schedule. Distribution may be:
- By the main contractor, as an attendance or through a distribution team it employs
- By a specialist distribution contractor, appointed by the main contractor or by you
- By the supplier, where a merchant or manufacturer delivers to floor level for an extra charge
- By you, using your own labour and the main contractor's hoist or lifts
If the documents are silent, ask a tender query. If there is still no answer, state what you have priced. Getting this wrong is a common cause of disputes, and a main contractor levelling tenders will add for it if your bid excludes it.
What limits how materials get up the building?
Check each of these with the main contractor before you price:
- Hoist or lift car size. Long boards and lengths of stud or track may not fit inside a hoist car or goods lift. Get the internal dimensions and compare them with your longest items.
- Load limits. Each hoist or lift has a safe working load. It sets how many boards travel per trip.
- Hoist time. On a busy site, hoist time is booked in slots shared between trades. Waiting time is real cost.
- Crane or loading bay access. Some jobs can crane packs onto a loading platform at each floor. Others rely on the hoist alone.
- Floor loading. Ask where stacks can be placed and how much each area can carry. Do not assume a slab can take a full pack anywhere.
- Storage space. A floor full of other trades' materials leaves no room to land a full delivery.
How do you price distribution?
Count the loads, estimate the time per trip including loading, travel, unloading and stacking, and multiply by the gang size and labour rate. Add an allowance for waiting time if hoist slots are shared.
For illustration only, with assumed figures. These are not market rates or standard outputs. A six-storey fit-out, materials delivered to a ground-floor loading bay, distributed by two of your operatives using a shared hoist.
| Material | Quantity | Assumed items per trip | Trips |
|---|---|---|---|
| Plasterboard | 1,800 boards | 20 | 90 |
| Studs and track | 240 bundles | 12 | 20 |
| Insulation | 300 packs | 15 | 20 |
| Sundries and fixings | 10 | ||
| Total trips | 140 |
At an assumed 15 minutes per trip, 140 trips take 35 hours. With two operatives, that is 70 labour hours. At an assumed £30 per hour, distribution labour is £2,100. Adding an assumed 10% for waiting for hoist slots gives £2,310 for this package.
Your own figures depend on the hoist, the distance from hoist to work area, and how the deliveries are split. Time a few loads on your next job to build your own allowances.
How do deliveries affect distribution?
Distribution and delivery planning go together. One large delivery may be cheaper from the merchant but leave materials on the ground floor for weeks, in the way and at risk of damage. Smaller deliveries, called off floor by floor, can go straight up and be stored near where they are used.
The guide to drylining call-offs covers planning deliveries against the programme. Match each call-off to a hoist slot, and tell the main contractor what is arriving and when.
What should your offer say about distribution?
State plainly:
- Who distributes, and from where to where
- Which hoist, lift or crane you have assumed, and that it is provided free of charge
- Any assumption about hoist availability or working hours
- That materials will be stored on each floor in areas the main contractor provides
The guide to pricing a drylining job lists distribution among the costs around the work. The drylining tender checklist helps you confirm it has been priced before you submit. If the main contractor provides distribution as an attendance, the guide to subcontract attendances explains what to check.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Is distribution included in a supply-and-fix drylining price?
Only if the enquiry or your offer says so. State in every tender who moves materials from the delivery point to the work area.
Can merchants deliver plasterboard to upper floors?
Some can, usually for an extra charge and subject to site access. Confirm what is offered in writing with the delivery arrangements.
Who pays for waiting time at the hoist?
It depends on your subcontract and what you stated in your tender. Record lost time when hoist access is not as agreed.
How do I stop boards being damaged during distribution?
Plan deliveries close to when the boards are needed, store them flat on bearers in dry areas, and agree protected storage areas on each floor.