Pay less notices: what a subcontractor should check
Last updated 2026-11-10 · 6 min read
A pay less notice is the payer's written notice that it intends to pay less than the notified sum. When one arrives, check it was given in time, that it states the sum the payer considers due and how that sum was worked out, and that each deduction has a contractual basis and evidence. Then reply in writing.
Under the Construction Act, the payer cannot simply pay a smaller amount without saying why. The pay less notice is how it says why, and it shows exactly which part of your application is in dispute. Read it carefully the day it arrives.
This guide describes the general rules in the Housing Grants, Construction and Regeneration Act 1996, as amended (the Construction Act), for England and Wales. Scotland has its own version of the Scheme for Construction Contracts, and Northern Ireland has its own legislation. It is not legal advice. Check your subcontract, and take proper advice on any dispute with real money at stake.
What is the notified sum?
The notified sum is the amount the payer must pay by the final date for payment unless it gives a valid pay less notice. Which document sets it depends on what happened earlier in the cycle:
- If the payer gave a valid payment notice, the notified sum is usually the sum in that notice.
- If it did not, your application, or a default notice you gave under the Act, can stand in its place.
So find the notified sum before you read the pay less notice.
Was the notice given in time?
The Act requires a pay less notice to be given no later than a set period before the final date for payment. Your subcontract should state that period. Where it does not, the Scheme for Construction Contracts fills the gap, and the Scheme period is 7 days before the final date for payment.
Check when it was actually received, by the method of service your subcontract sets. When counting days under the Act, Christmas Day, Good Friday and bank holidays are left out.
What must a pay less notice say?
It must state the sum the payer considers to be due on the date of the notice, and the basis on which that sum has been calculated. A notice that gives a figure with no explanation, or lists deductions without arriving at a sum, may not meet the requirement. Whether a notice is valid is a legal question, so treat any doubt as a reason to take advice, not to assume you will be paid in full.
Which deductions should you challenge?
Put each deduction into a simple table. The example below is for illustration only, with assumed figures.
| Item in the notice | Amount | Contractual basis | Evidence supplied | Your position |
|---|---|---|---|---|
| Your application, gross to date | £86,400 | Subcontract valuation clause | Your application | Starting point |
| Variation 14 not accepted | -£2,850 | Says no written instruction | None | Disagree: instruction confirmed by email on the day |
| Level 3 measured work cut from 90% to 75% | -£4,200 | Valuation clause | Site walk note | Partly agree: photos support 82% |
| Cleaning contra charge | -£1,100 | Set-off clause | Invoice, no allocation | Ask how it was split between trades |
| Retention at 5% of the reduced gross, £79,350 | -£3,967.50 | Retention clause | Calculation | Rate agreed; amount follows the gross |
Record the deductions you accept too, so the next valuation starts from an agreed figure. The guide to recording variations covers the evidence that makes items like Variation 14 hard to strike out, and daily site reports are often what supports a disputed percentage complete.
How should you respond?
Reply in writing within days, not weeks. Keep it factual:
- Identify the notice by date and the application it relates to
- State which deductions you accept and which you do not, item by item
- Attach or point to the evidence for each item you dispute
- Ask for the evidence behind any deduction that arrived without it
- Restate the amount you say is due
Then carry the disputed items forward, shown separately, on your next application. The guide to payment applications and retention shows how to lay out that application.
What if no valid notice was given?
If no valid pay less notice was given in time, the general rule is that the notified sum must be paid by the final date for payment. The Act also gives a right to suspend work for non-payment after giving at least 7 days' written notice of the intention to suspend, and a right to refer a dispute to adjudication at any time. Take advice before using either.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Is a payment notice the same as a pay less notice?
No. A payment notice states the sum the payer considers due. A pay less notice says it intends to pay less than the notified sum, and why.
Can a main contractor deduct contra charges without a pay less notice?
Generally, a deduction from the notified sum needs a valid pay less notice. Check your subcontract's set-off clause, and take advice on a specific deduction.
Does a pay less notice have to come from the main contractor itself?
It can come from the payer or from a person the subcontract names to give it. Check who your subcontract specifies.
What if the pay less notice arrives after the deadline?
A late notice may not be valid. Check the dates against your subcontract, keep the evidence of when it arrived, and take advice before acting on it.