Metal stud spacing: 600 or 400 centres?
Last updated 2026-11-10 · 6 min read
Many UK metal stud partitions with 12.5 mm or 15 mm board are built at 600 mm centres. Walls move to 400 mm centres when the board is thinner, the finish is heavy, the wall carries fixtures or hard knocks, or the height needs a stiffer frame. The manufacturer's system data decides, and the drawings should say which.
Both spacings divide evenly into a 1200 mm wide board, which is why these two figures come up so often. The guide to stud centres and deflection heads covers where centres come from in general. This page is about choosing between the two common ones, and what the choice does to your quantities.
Why are 600 and 400 the usual spacings?
Vertical board joints have to land on a stud, so the spacing has to suit the board width. A 1200 mm board covers exactly two 600 mm spaces or three 400 mm spaces, so the joints always fall on a stud as you work along the wall.
Other spacings do appear in some systems and for some board widths. If the system data gives a different figure, use it.
What pushes a wall to 400 mm centres?
Look for these when you read the partition schedule and the specification:
- Thinner board. Thinner board spans less between supports, so it is commonly fixed at closer centres. The board's data sheet gives the maximum spacing it can be fixed at.
- Heavy finishes. Tiling, especially with large or heavy tiles, can call for closer centres or a stronger board. Check both the board data and the tile and adhesive guidance.
- Fixtures and impact. Walls that carry wall-hung units, handrails or heavy traffic, such as school or hospital corridors, are often specified at closer centres, with extra backing where items fix.
- Height. As walls get taller, some systems close the centres to keep the wall within its limits. Others use a deeper or heavier stud instead. The system data says which.
- Fire and acoustic performance. A tested system states its centres. You cannot open them up without test evidence for the change.
When is 600 mm enough?
When the system data for that board, number of layers, height and performance gives 600 mm, and nothing in the specification adds load, impact or a heavy finish. Plain office partitions with a decorated finish are often in this group, but check each type rather than assuming it.
What does the change do to the quantities?
Closer centres change the frame and the fixing, not the board. Per square metre of plain wall, before ends, openings and waste:
| Item | 600 mm centres | 400 mm centres | Change |
|---|---|---|---|
| Stud, linear metres per m² of wall | 1.67 | 2.50 | About 50% more |
| Board, m² per m² of each face | 1.00 | 1.00 | None |
| Head and floor track | Same | Same | None |
| Studs each 1200 mm board is fixed to | 3 | 4 | One more line of screws per board |
For illustration only, with assumed figures: a job has 220 m² of partition at 2.7 m high. At 600 mm centres that is about 220 x 1.67 = 367 linear metres of stud, or 136 lengths of 2.7 m before ends, openings and waste. At 400 mm centres it is 220 x 2.5 = 550 linear metres, or 204 lengths. That is 68 more studs to buy, cut and fix, plus an extra line of screws on every board. Price the difference from your own merchant prices and your own framing outputs.
What should you do when the drawings say nothing?
Do not price 600 mm and hope. Raise a query with the main contractor or designer before you submit, naming the partition types where the centres are not shown.
If no answer comes in time, price the spacing the system data gives for that build-up and height, and state it as an assumption in your offer. The guide to qualifications and exclusions shows how to word it so it carries into the subcontract.
How do you keep both spacings apart in the take-off?
Treat them as different partition types. "Type A at 600 mm" and "Type A at 400 mm behind tiling" may look the same on plan, but they need different stud quantities and different framing rates.
Measure each one by height band, as the drylining take-off guide describes, so a tall wall at 400 mm centres does not end up priced as a short wall at 600 mm. The guide to metal stud partition cost per m² shows where the framing line sits in the rate.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Is 600 mm or 400 mm stud spacing stronger?
Closer centres give the board more support, so a wall at 400 mm centres is stiffer than the same wall at 600 mm. Whether a wall needs it depends on the system data for its board, height, finish and performance.
Do 400 mm centres need more plasterboard?
No. The board area stays the same. You need more studs and more screws, and more framing time.
Can I tile onto a partition at 600 mm centres?
Sometimes. It depends on the board, the tile weight and the system data. Check the board and tile guidance before you price it.
What if the specification and the system data disagree?
Raise it before you price. Where the specification asks for closer centres than the system data, the specification is usually adding a requirement, so price what it asks and confirm it.