Metal stud partition cost per m²: building the rate

Last updated 2026-11-24 · 6 min read

Short answer

A metal stud partition cost per m² has four parts: the material for one square metre of the build-up, with waste; the labour to frame, board and finish it, from your own outputs; access and job costs over the area; then overheads and profit. Build one rate per partition type and height band, not one figure for every wall.

There is no single market price worth copying. The same wall costs more on a tall, stop-start job with poor access than on a clear open floor, and your merchant prices and gangs are your own. What you can do is build the rate the same way every time, so it can be checked.

What decides the cost of a metal stud partition?

The build-up and the conditions it is built in:

  • Board layers. One or two layers each side, and the board type the specification calls for.
  • Stud size and centres. Deeper studs and closer centres mean more steel per square metre.
  • Height. Taller walls need longer or extended studs, slow every activity down and need more access.
  • Insulation and sealant. Acoustic or fire-rated walls add insulation, sealant and extra care at the edges.
  • Head detail. A deflection head costs more in material and time than a fixed head.
  • Openings and junctions. Door openings, corners and abutments take time out of every square metre around them.

The guide to stud centres and deflection heads covers what the system itself requires.

How do you work out the material per m²?

List every component of the build-up for one square metre of wall: board, studs, head and floor track, screws, tape, jointing compound, and any insulation and sealant. Take the quantities from the manufacturer's data for that system, not from memory.

Price each component from your own merchant quote, in the same unit as the quantity. Then add a waste allowance from your own similar jobs. Short runs with lots of returns waste more than long straight walls.

How do you work out the labour per m²?

Split the work into activities, because each one runs at its own pace:

  • Setting out and framing
  • Boarding, each layer
  • Taping and jointing, or skimming
  • Sealing and insulation, where the wall needs them

For each activity, divide your day rate by the output per operative per day. Use outputs measured on your own jobs. The guide to drylining productivity shows how to measure them, and your day rate should carry the full cost of the operative, not wages alone.

How do height and access change the rate?

Every activity slows down when the gang works from towers or podiums, moves kit between floors or works around other trades. Price that in one of two ways:

  • Lower the outputs for the taller height band, so the labour per m² goes up.
  • Price towers, distribution and return visits as separate items in the BoQ.

Pick one way and use it on every job, so access is neither missed nor counted twice.

What does the build-up look like?

Lay it out so each line can be checked:

LineHow it is worked outUnit
BoardBoard area per m² of wall x price per m², plus wasteper m²
FramingStuds and track per m² of wall x price, plus wasteper m²
Fixings and finishingScrews, tape and jointing per m² x priceper m²
Insulation and sealantWhere the system calls for themper m²
Framing labourDay rate / framing output per operative per dayper m²
Boarding labourDay rate / boarding output per operative per dayper m²
Taping and jointing labourDay rate / taping output per operative per dayper m²
Access and job costsTowers, distribution and waste removal / areaper m²
Overheads and profitMarkup on the cost aboveper m²

For illustration only, with assumed figures for a single-layer partition in the lowest height band: board, studs, track, fixings, tape, jointing and sealant come to £13.50 per m², including waste. At an assumed £240 a day including on-costs, framing at 30 m², boarding at 40 m² and taping at 48 m² per operative per day give labour of £8.00 + £6.00 + £5.00 = £19.00 per m². Access and distribution add £1.25, so the cost is £33.75 per m². A 15% markup makes the rate £38.81, which is a margin of about 13.0%.

How do you check your rate?

Compare it with the same partition type on your last few jobs. If it has moved, find which line moved, starting with labour, which is usually the largest part.

After each job, compare the outputs and material you priced with what really happened, and update the lines before the next tender. The guide to building a drylining rate covers the same layers for linings and other systems.

FixMargin is software for UK drylining and interiors subcontractors. On a free account you can run the calculator for supported partition and wall lining systems and load one supplier price list, confirming or mapping the items it does not recognise. The library does not yet cover every manufacturer. You can start on a free account.

Frequently asked questions

What is the average cost of a metal stud partition per m²?

There is no average worth pricing from, because build-up, height, access and merchant prices change it from job to job. Build your own rate from materials, labour, access, overheads and profit.

Should a double-layer partition have its own rate?

Yes. A second layer adds board, screws and a full boarding activity to each side, so it needs its own line.

Should access go in the rate per m²?

Either put it in the rate or price it as separate items, but not both. Say which in your offer.

Should openings be priced separately?

Usually, yes. Price door openings and their framing as numbered items, so the rate per m² stays a rate for plain wall.

Related guides

How to build a drylining rate: labour, materials and overheadsSetting your drylining labour rate in the UKDrylining productivity: m² per operative per day, and how to measure it