Setting your drylining labour rate in the UK
Last updated 2026-11-08 · 6 min read
To set a drylining labour rate, add up the full yearly cost of each operative: pay plus employer's National Insurance, holiday pay, pension, travel, tools, PPE and training. Divide that by the days they really produce on site, not the days they are paid for. The result is your cost per productive day, before any overhead or profit.
The labour rate is the figure every price leans on. If it only covers wages, every rate built from it is too low, and the job pays for the difference.
What goes into the cost of an operative?
Everything you pay because that person works for you, over a full year:
- Gross pay. Basic pay, plus any overtime, bonus or allowances you normally pay.
- Employer's National Insurance. On pay above the threshold, at the current rate.
- Holiday pay. Paid days when no work is done, at least the statutory entitlement.
- Pension. Your employer contribution under auto-enrolment, or more if your scheme pays it.
- Sick pay and other benefits. Statutory sick pay and anything you offer above it.
- Travel. Vans, fuel, parking or travel allowances to get to site.
- Tools and PPE. Power tools, hand tools, batteries, workwear and protective equipment.
- Training and cards. Courses, renewals and the time spent on them.
Use the current rates and thresholds from GOV.UK for National Insurance, holiday entitlement and pensions, because they change.
How many productive days are there in a year?
Fewer than the days you pay for. Start with the working weekdays in the year, then take off:
- Holiday, including bank holidays if your contracts count them in the entitlement.
- An allowance for sickness and training days, from your own records.
- Days lost on site: travel between jobs, waiting for access or materials, weather, and unpaid return visits.
The last item is the one most often left out. Your timesheets and daily reports will show how much time really goes on it.
How do you work out the cost per day?
Divide the full yearly cost by the productive days. Then check whether supervision is in the figure or priced separately.
| Item | How to work it out | Your figure |
|---|---|---|
| Gross pay | Basic pay plus normal overtime, bonus and allowances for a year | |
| On-costs | Employer's National Insurance + employer pension + sick pay and benefits | |
| Running costs | Travel + tools + PPE + training for a year | |
| Full yearly cost | Gross pay + on-costs + running costs | |
| Productive days | Working weekdays - holiday - sickness and training - days lost on site | |
| Cost per productive day | Full yearly cost / productive days | |
| Cost per hour | Cost per productive day / paid hours in a day |
Holiday pay does not need a line of its own if gross pay already covers the whole year. Taking holiday out of the productive days is what puts its cost into the rate.
For illustration only, with assumed figures: an operative with gross pay of £35,000 a year, on-costs of £7,000 and running costs of £3,000 costs £45,000 a year. With 225 days at work and 25 of those lost to travel, waiting and return visits, there are 200 productive days. The cost is £45,000 / 200 = £225 per productive day, or about £28.13 an hour over an 8-hour day.
What changes with labour-only gangs?
With a labour-only gang paid by the day or by the square metre, the gang carries its own pay, holiday and tools. You still carry other costs:
- Supervision and setting out, if your own staff do it.
- Travel or accommodation, if you pay it.
- Any downtime you pay for when the gang cannot work.
- Verifying each subcontractor, making any deductions under the Construction Industry Scheme and filing the monthly returns.
Check each worker's employment status against the HMRC guidance. A gang you control like employees may be treated as employed, with the on-costs that brings.
How does the day rate become a rate per m²?
Divide the cost per productive day by the output per operative per day for each activity, such as framing, boarding, and taping and jointing. Use outputs measured on your own jobs. The guide to drylining productivity shows how to measure them, and the guide to building a drylining rate shows how the labour cost per m² fits into the full rate.
Is your daywork rate the same as your labour rate?
No. The labour rate is your cost. A daywork rate is what you charge for time-based work, so it should add your overheads and profit on top of the cost, as the subcontract allows.
Agree the daywork rates before the job starts, and attach them to your offer. The guide to daywork sheets covers what each sheet needs to get paid.
FixMargin is software for UK drylining and interiors subcontractors. On a free account you can run the calculator for supported partition and wall lining systems and load one supplier price list, confirming or mapping the items it does not recognise. The library does not yet cover every manufacturer. You can start on a free account.
Frequently asked questions
Should my labour rate include overheads?
Keep the labour rate as the cost of the operative, and add overheads and profit later in the price. That way you can see each part and change one without guessing at the other.
How often should I update my labour rate?
Whenever pay, National Insurance or pension rates change, and at least once a year. Check your productive days against your timesheets at the same time.
Do I need a different rate for each operative?
Not always. Many firms use one rate per grade, such as improver, fixer and chargehand, built from the average cost of the people in each grade.
Why does my rate look higher than what I pay a day?
Because a day's pay leaves out the on-costs and the paid days with no output. The rate has to recover the whole year's cost from the days that produce work.