How to build a drylining rate: labour, materials and overheads

Last updated 2026-11-08 · 6 min read

Short answer

To build a drylining rate per m², add the material cost per m² of the system, including waste, to the labour cost per m² from your own outputs. Then add access and other job costs spread over the area, and finally overheads and profit. Build one rate per system and height band, and keep each part visible.

A rate that is one number with nothing behind it is hard to defend and harder to learn from. A rate built in layers can be checked, adjusted for the job in front of you and compared with what really happened once the work is done.

What goes into a drylining rate?

Every rate per m² has the same four layers:

  • Materials. Every component of the system for one square metre, with waste and sundries.
  • Labour. The time to frame, board, and tape and joint one square metre, at your day rate.
  • Job costs. Access, distribution, protection and waste removal, spread over the area or priced as items.
  • Overheads and profit. Your office, vehicles, insurance and management, plus the return you want.

Build a separate rate for each system and each height band. A double-layer partition and a single-layer one on the same floor are different rates, and so are short and tall walls of the same type.

How do you work out the material cost per m²?

Start from the system's component quantities per square metre, taken from the manufacturer's data for that build-up, not from memory. List boards, studs, track, screws, tape, jointing compound, insulation and sealant.

Price each component from your own merchant quote in the same unit as the quantity. If board is quoted per sheet and your quantity is per m², convert one to the other before you multiply. The guide to unit conversion in drylining quotes covers sheets, lengths and packs.

Add a waste allowance that reflects the work. Long open runs waste less than rooms full of short returns, so use the figures from your own similar jobs.

How do you work out the labour cost per m²?

Use outputs you have measured on your own jobs, split by activity: framing, boarding, and taping and jointing. One blended output for everything hides the slow parts. The guide to drylining productivity shows how to measure them.

For each activity, divide your day rate by the output per operative per day. Your day rate should include on-costs such as employer's National Insurance, holiday pay, travel and tools, or the labour line will look cheaper than it is.

Then adjust for the job. High work, stop-start access and lots of openings slow every activity down.

Where do access and job costs go?

Some costs belong to the job rather than the square metre: towers and podiums, moving boards to each floor, protection, waste removal and return visits.

You can spread them over the area and add them to the rate, or price them as separate items in the BoQ. Either works. What matters is doing one or the other consistently, and saying which in your offer, so they are neither missed nor deducted.

How do you add overheads and profit?

Add them last, on top of the cost. Know what your overheads are as a share of turnover, because that is the minimum the rate has to recover before any profit.

Be clear whether you are adding a markup or targeting a margin. Markup is added to cost. Margin is the share of the selling price you keep. The same number gives two different results, and the guide to pricing a drylining job explains the sum.

What does a worked rate look like?

Lay the rate out so every layer can be checked:

LayerHow it is worked outUnit
MaterialsComponent quantities per m² x merchant price, plus waste and sundriesper m²
Framing labourDay rate / framing output per operative per dayper m²
Boarding labourDay rate / boarding output per operative per dayper m²
Taping and jointing labourDay rate / taping output per operative per dayper m²
Job costsAccess, distribution and waste removal / area of the systemper m²
Overheads and profitMarkup on the cost aboveper m²

For illustration only, with assumed figures for a single-layer partition: materials come to £14.20 per m² including a 7% waste allowance. Framing at 30 m², boarding at 40 m² and taping at 45 m² per operative per day, at an assumed £240 a day including on-costs, gives labour of £8.00 + £6.00 + £5.33 = £19.33 per m². Job costs add £1.50, so the cost is £35.03 per m². A 12% markup makes the rate £39.23, which is a margin of about 10.7%.

How do you check the rate?

Compare it with the same system on your recent jobs. If it is well above or below, find out which layer moved. Look at the largest part first, usually labour.

After each job, compare the outputs and material use you priced with what really happened. Update the layers before the next tender, so the rate keeps up with your gangs, your merchants and the work you win.

FixMargin is software for UK drylining and interiors subcontractors. On a free account you can run the calculator for supported partition and wall lining systems and load one supplier price list, confirming or mapping the items it does not recognise. The library does not yet cover every manufacturer. You can start on a free account.

Frequently asked questions

Should I use one rate for all partitions?

No. Build one rate per system and height band, because double-layer and taller walls take longer and use more material.

Where should my labour outputs come from?

From your own jobs, measured by activity. A general figure rarely matches your gangs, your sites or your access.

Should the rate include access?

Either include it in the rate or price it as separate items, but not both. State which in your offer so it is not missed or deducted.

How often should I review my rates?

After every job closes, compare the outputs and material use you priced with what happened. Update the rate before your next tender, not once a year.