Liquidated damages passed down to subcontractors
Last updated 2026-11-10 · 6 min read
Liquidated damages reach a subcontractor only through the terms of the subcontract. Some subcontracts state their own rate per day or week, often with a cap. Others leave the main contractor to claim the loss it actually suffers from your delay, which can include damages it pays the client. Read the clause at tender and price the exposure.
A few weeks of delay can take more out of a package than any pricing error, so the clause is part of the price.
This guide gives general information for England and Wales. It is not legal advice. The wording of your subcontract decides what you can be charged, so read it and take proper advice where real money is at stake.
What are liquidated damages?
Liquidated damages are a sum agreed in advance, usually a rate per day or per week, payable if the work finishes late. The main contract between the client and the main contractor will normally set one. The agreed sum stands in for proving the actual loss.
Courts in England and Wales generally uphold an agreed damages clause between commercial parties. A challenge that the rate is an unenforceable penalty is possible, but it is a legal question and rarely simple, so do not price on the hope of one.
How do they get passed down to you?
There are two common patterns, and the subcontract tells you which applies.
| What the subcontract says | What you could be asked to pay | What to check |
|---|---|---|
| A stated rate for subcontract delay | Usually that agreed rate for the period of your delay, often up to a cap | The rate, the cap, and whether it applies to sections or the whole package |
| No stated rate, but you are liable for losses caused by your delay | The main contractor's loss caused by your breach, which may include damages it pays the client, its own extra costs, and claims from other trades | Any cap, any exclusion of indirect loss, and what the main contractor must prove |
In the second pattern the main contractor generally has to show that your delay caused the loss. Where several causes of delay overlap, take advice.
What should you check before you sign?
Read the delay and damages clauses together with the programme they refer to:
- Is there a stated rate, and is it per day or per week?
- Is there a cap, and is it a figure or a percentage of the subcontract sum?
- Does the clause cover only your delay, or a share of the whole project's delay?
- Which completion dates apply: one date, sectional dates or a rolling programme?
- What notice must you give to get more time, and by when?
- Are indirect or consequential losses excluded?
If the terms are open-ended, say so in your offer. The guide to qualifications and exclusions on a drylining quote shows how to qualify a tender, for example by offering a capped rate.
What could a delay cost you?
Put a number on the risk. The table below is for illustration only, with assumed figures: a subcontract sum of £180,000, a stated rate of £1,500 per week of subcontract delay, and a cap of 5% of the subcontract sum, which is £9,000.
| Weeks of delay you cause | Damages at £1,500 a week | After the £9,000 cap | Share of an assumed £18,000 margin |
|---|---|---|---|
| 2 | £3,000 | £3,000 | 17% |
| 4 | £6,000 | £6,000 | 33% |
| 6 | £9,000 | £9,000 | 50% |
| 8 | £12,000 | £9,000 | 50% |
Even with a cap, six weeks would take half the assumed margin. Without a cap, or under a clause based on actual loss, there may be no upper figure at all.
How do extensions of time protect you?
Most subcontracts let you claim more time for delay you are not responsible for, such as late access, late information or a change to the work. More time moves your completion date and shortens or removes the damages period.
The protection only works if you follow the notice rules. Many subcontracts require written notice within a set period, and some treat late notice as losing the right to more time. Record the dates areas were actually handed over, and keep your daily site reports consistent with the programme you are measured against.
How are damages taken from your payment?
Damages for delay usually come off an interim or final payment rather than being invoiced. Under the Construction Act, a deduction from the notified sum generally needs a valid pay less notice given in time. The guide to checking a pay less notice covers what that notice must state. Treat any deduction for delay the same way you would treat a contra charge: ask for the clause, the period and the working behind the figure, in writing.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Can a main contractor pass its full liquidated damages on to me?
It depends on the subcontract and the facts. Where the subcontract bases your liability on the main contractor's actual loss, that loss may include damages it pays the client, if it can show your delay caused them. Take advice on a specific claim.
Is it reasonable to ask for a cap?
Yes. Asking for a stated rate and an overall cap is a normal commercial request at tender. Whether it is accepted is a matter for negotiation.
What if the delay was caused by other trades?
Record it at the time and give notice under your subcontract. Damages generally depend on showing that your delay caused the loss, so contemporaneous records matter.