Interim valuation template for subcontractors

Last updated 2026-11-10 · 6 min read

Short answer

An interim valuation sets out the value of work done to a valuation date. For a subcontractor, the template needs the contract work by section with its percentage or quantity complete, agreed and submitted variations, signed dayworks, materials on site where allowed, the gross total, retention, previous payments and the amount now due. Copy the tables below.

A valuation that is easy to check is easier to agree and harder to argue with. The aim is that the main contractor's quantity surveyor can follow every figure back to the contract, a variation reference or a signed sheet, without phoning you to ask what a line means.

What goes into an interim valuation?

Build it in the same order every month:

  • Contract work. Each section or BoQ item, its contract value, and how much is complete.
  • Preliminaries. Access, supervision and other time-related items, valued as the subcontract allows.
  • Variations. Agreed ones, then submitted ones, each with its reference.
  • Dayworks. Signed sheets only, each with its number.
  • Materials on site. Only if your subcontract allows them to be claimed, and on its conditions.
  • Gross valuation. The total of all of the above.
  • Deductions. Retention, then previous payments.
  • Amount due. What you are asking to be paid this time.

The guide to payment applications and retention covers the dates and the covering application. This page is about the valuation behind it.

What does the blank template look like?

Copy these two tables into your spreadsheet. Value each line, then total it.

RefSection or itemContract value% or qty completeValue to dateEvidence
Preliminaries
LineValue
Contract work to date
Variations agreed
Variations submitted, not yet agreed
Dayworks signed
Materials on site
Gross valuation
Less retention
Less previous payments
Amount due this valuation

What does a filled-in valuation look like?

The example below is for illustration only, with assumed figures, for a package with a contract value of £90,000.

RefSection or itemContract value% completeValue to date
1Level 1 partitions and linings£24,000100%£24,000
2Level 2 partitions and linings£26,00080%£20,800
3Level 3 partitions and linings£26,00025%£6,500
4Deflection heads and linear items£6,00050%£3,000
5Preliminaries£8,00050%£4,000
Contract work to date£90,000£58,300
LineValue
Contract work to date£58,300
Variations agreed: V01, V03£3,650
Variations submitted, not yet agreed: V04£1,800
Dayworks signed: DW07, DW09£640
Materials on site, as the subcontract allows£2,500
Gross valuation£66,890
Less retention at 5%£3,344.50
Less previous payments£48,200
Amount due this valuation£15,345.50

All figures are before VAT and any CIS deduction. Keep the variation and daywork references matching your variations log and your daywork sheets, so each line is easy to check.

How do you value work that is part complete?

Use the method your subcontract sets. Where you have a choice, measured quantities are easier to defend than a percentage guessed on a site walk. If you do use percentages, base them on something you can show: areas boarded and taped, a marked-up drawing, or dated photos.

Value preliminaries the way the subcontract allows, often by time elapsed or by progress. Do not claim all of them early, and do not forget them at the end.

How do you reconcile the main contractor's assessment?

When the payment notice arrives, put it next to your valuation, line by line. The example below follows the one above, again for illustration only, with assumed figures.

LineYour valuationTheir assessmentDifferenceReason givenAction
Level 3 partitions£6,500£3,900-£2,600Assessed at 15%Send dated photos and marked-up drawing
V04£1,800£0-£1,800Not yet agreedChase the instruction and price
Materials on site£2,500£0-£2,500No delivery notes seenSend delivery notes and photos
All other lines£56,090£56,090£0
Gross£66,890£59,990-£6,900

Carry each difference forward to the next valuation until it is resolved. A difference that is never raised again is usually never paid.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Can I download this valuation template?

There is no download. Copy the tables on this page into your own spreadsheet.

Is an interim valuation the same as a payment application?

They are closely linked. The valuation is the build-up of value; the application is the claim you send, usually with the valuation attached.

Should I include variations that are not agreed?

Show them on a separate line with their reference and evidence, if your subcontract allows. Only agreed value is secure.

Can I claim for materials on site?

Only if your subcontract allows it, and on its conditions, such as proof of delivery and ownership.

Related guides

Payment applications and retention for drylining subcontractorsVariations log template for drylining subcontractorsCost value reconciliation (CVR) template for subcontractors