Interim valuation template for subcontractors
Last updated 2026-11-10 · 6 min read
An interim valuation sets out the value of work done to a valuation date. For a subcontractor, the template needs the contract work by section with its percentage or quantity complete, agreed and submitted variations, signed dayworks, materials on site where allowed, the gross total, retention, previous payments and the amount now due. Copy the tables below.
A valuation that is easy to check is easier to agree and harder to argue with. The aim is that the main contractor's quantity surveyor can follow every figure back to the contract, a variation reference or a signed sheet, without phoning you to ask what a line means.
What goes into an interim valuation?
Build it in the same order every month:
- Contract work. Each section or BoQ item, its contract value, and how much is complete.
- Preliminaries. Access, supervision and other time-related items, valued as the subcontract allows.
- Variations. Agreed ones, then submitted ones, each with its reference.
- Dayworks. Signed sheets only, each with its number.
- Materials on site. Only if your subcontract allows them to be claimed, and on its conditions.
- Gross valuation. The total of all of the above.
- Deductions. Retention, then previous payments.
- Amount due. What you are asking to be paid this time.
The guide to payment applications and retention covers the dates and the covering application. This page is about the valuation behind it.
What does the blank template look like?
Copy these two tables into your spreadsheet. Value each line, then total it.
| Ref | Section or item | Contract value | % or qty complete | Value to date | Evidence |
|---|---|---|---|---|---|
| Preliminaries |
| Line | Value |
|---|---|
| Contract work to date | |
| Variations agreed | |
| Variations submitted, not yet agreed | |
| Dayworks signed | |
| Materials on site | |
| Gross valuation | |
| Less retention | |
| Less previous payments | |
| Amount due this valuation |
What does a filled-in valuation look like?
The example below is for illustration only, with assumed figures, for a package with a contract value of £90,000.
| Ref | Section or item | Contract value | % complete | Value to date |
|---|---|---|---|---|
| 1 | Level 1 partitions and linings | £24,000 | 100% | £24,000 |
| 2 | Level 2 partitions and linings | £26,000 | 80% | £20,800 |
| 3 | Level 3 partitions and linings | £26,000 | 25% | £6,500 |
| 4 | Deflection heads and linear items | £6,000 | 50% | £3,000 |
| 5 | Preliminaries | £8,000 | 50% | £4,000 |
| Contract work to date | £90,000 | £58,300 |
| Line | Value |
|---|---|
| Contract work to date | £58,300 |
| Variations agreed: V01, V03 | £3,650 |
| Variations submitted, not yet agreed: V04 | £1,800 |
| Dayworks signed: DW07, DW09 | £640 |
| Materials on site, as the subcontract allows | £2,500 |
| Gross valuation | £66,890 |
| Less retention at 5% | £3,344.50 |
| Less previous payments | £48,200 |
| Amount due this valuation | £15,345.50 |
All figures are before VAT and any CIS deduction. Keep the variation and daywork references matching your variations log and your daywork sheets, so each line is easy to check.
How do you value work that is part complete?
Use the method your subcontract sets. Where you have a choice, measured quantities are easier to defend than a percentage guessed on a site walk. If you do use percentages, base them on something you can show: areas boarded and taped, a marked-up drawing, or dated photos.
Value preliminaries the way the subcontract allows, often by time elapsed or by progress. Do not claim all of them early, and do not forget them at the end.
How do you reconcile the main contractor's assessment?
When the payment notice arrives, put it next to your valuation, line by line. The example below follows the one above, again for illustration only, with assumed figures.
| Line | Your valuation | Their assessment | Difference | Reason given | Action |
|---|---|---|---|---|---|
| Level 3 partitions | £6,500 | £3,900 | -£2,600 | Assessed at 15% | Send dated photos and marked-up drawing |
| V04 | £1,800 | £0 | -£1,800 | Not yet agreed | Chase the instruction and price |
| Materials on site | £2,500 | £0 | -£2,500 | No delivery notes seen | Send delivery notes and photos |
| All other lines | £56,090 | £56,090 | £0 | ||
| Gross | £66,890 | £59,990 | -£6,900 |
Carry each difference forward to the next valuation until it is resolved. A difference that is never raised again is usually never paid.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Can I download this valuation template?
There is no download. Copy the tables on this page into your own spreadsheet.
Is an interim valuation the same as a payment application?
They are closely linked. The valuation is the build-up of value; the application is the claim you send, usually with the valuation attached.
Should I include variations that are not agreed?
Show them on a separate line with their reference and evidence, if your subcontract allows. Only agreed value is secure.
Can I claim for materials on site?
Only if your subcontract allows it, and on its conditions, such as proof of delivery and ownership.