Variations log template for drylining subcontractors

Last updated 2026-11-08 · 5 min read

Short answer

A variations log is one table per job that lists every change with a reference, description and location, who instructed it and when, the evidence held, the value submitted and agreed, and its status. Copy the template below, add each variation the day it is instructed, and send the log with every application for payment so nothing drops off.

A variation you cannot evidence is often work done for free. The log does not replace the instruction, the photos or the daywork sheets. It is the index that shows what exists, what has been priced, and what is still waiting for an answer. The guide on recording variations covers how to capture each one in the first place.

What columns does a variations log need?

Keep the columns that answer the questions a QS or director will ask:

  • Ref. Your own number, never reused.
  • Description and location. What changed and where: floor, gridline, room.
  • Instructed by. Name and role of the person who asked.
  • Date instructed. The day the instruction was given.
  • Instruction. Written instruction, or verbal and confirmed by you in writing, with the date.
  • Type. Addition, omission, change of specification, or daywork.
  • Evidence. Where the photos, drawings, sheets and quantities are kept.
  • Date submitted. When you sent the price.
  • Value submitted. Your price.
  • Value agreed. The figure the main contractor accepts.
  • Status. Instructed, priced, agreed, paid or disputed.
  • Application. The payment application it was included in.

What does the template look like?

Copy this table into a spreadsheet or your job file. Add a row the day each variation is instructed.

RefDescription and locationInstructed byDate instructedInstructionTypeEvidenceDate submittedValue submittedValue agreedStatusApplication

In a spreadsheet, add two totals at the foot: value submitted and value agreed. The gap between them is money you have asked for but cannot yet count on.

How do you fill it in?

Here is part of an example log, with the values left out:

RefDescription and locationInstructed byDate instructedInstructionTypeEvidenceStatusApplication
V-001Additional bulkhead, level 2, gridline CSite manager3 NovVerbal, confirmed by email 3 NovAdditionPhotos, rev C drawing, hoursPricedApp 4
V-002Wall W14 omitted, level 3Project manager5 NovWritten instructionOmissionRev D drawing, delivery noteAgreedApp 4
V-003Making good after services, level 1Site manager6 NovVerbal, confirmed by email 6 NovDayworkSigned daywork sheet DW-012Instructed

For illustration only: if V-001 is submitted at £552 and V-002 is agreed as an omission worth £410, the log shows £552 submitted but not yet agreed. Count only the agreed figure as secure in your job cost, and show the £552 separately until it is accepted.

How do you keep the log working?

A log is only as good as its last update. Three habits keep it honest:

  • A row goes in the day the instruction is given, even before it is priced.
  • Every row points to its evidence, so anyone can find it without asking.
  • Rows that sit at "priced" or "instructed" for weeks get chased at the next site meeting.

Daywork belongs in the log too, with the sheet number as evidence. The guide to daywork sheets sets out what each sheet needs.

How does the log fit with payment applications?

Send the log with each application for payment, showing which variations are included and at what value. It makes it harder for an item to drop off quietly, and it gives both sides one list to agree at the final account.

Check your subcontract for notice periods and how variations must be submitted. The wording differs from job to job, and if a lot of money is at stake, take proper advice.

FixMargin is software for UK drylining and interiors subcontractors. Variations are on the Growth plan and above, alongside daily site reports and the planner. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Can I download this variations log template?

There is no download. Copy the table on this page into your own spreadsheet and add any columns your subcontract needs.

Should omissions go in the log?

Yes. Record them with any material already bought or labour already planned, as that cost may still be claimable.

When should a variation be added to the log?

The same day it is instructed, before it is priced. A row added weeks later is often missing the evidence.

How often should I send the log?

With every application for payment, usually monthly. Review it at each site meeting as well.

Related guides

Recording variations on drylining jobsDaywork sheets: what they need to get paidPayment applications and retention for drylining subcontractors