Independent wall lining: take-off and pricing

Last updated 2026-11-08 · 6 min read

Short answer

To take off an independent wall lining, measure each lining type by length and height, split by height band, and deduct openings as your measurement rules allow. List reveals, heads, bases and corners as linear items. Then price the net area with a rate built from the lining's components, your own labour outputs, access, and overheads and profit.

An independent lining is a free-standing frame of studs in head and floor track, set off the wall and boarded on one side. It is often used where the wall behind is uneven, where services or insulation need a cavity, or where the lining must not be fixed back to the structure. Because it stands on its own, height and the frame matter more than on a lining fixed direct to the wall.

What do you need from the drawings and specification?

Before you measure, collect:

  • The lining types. Board, layers, frame and insulation for each type, from the specification.
  • Cavity and frame size. The gap to the wall and the stud size, which set the steel per square metre.
  • Heights. Floor to soffit or to ceiling line, room by room, because taller linings may need intermediate restraint or a deeper frame.
  • Openings. Windows, doors and large service penetrations in each lining.
  • Finish. Tape and joint or skim, and any fire or acoustic performance.

Check the manufacturer's data for the maximum height of each frame and what it needs above that height. Do not assume the rules are the same as for a partition.

How do you measure the lining area?

Measure each lining type wall by wall: length times height. Group the results by lining type and height band, so each group can carry its own rate.

Deduct openings as your measurement rules or the contract say. Many firms deduct only larger openings and price the smaller ones as an allowance. Whatever you choose, apply it the same way on every job and say so in your offer. The guide to drylining take-off covers measuring by system in more detail.

What linear and numbered items should you list?

The area is only part of the job. Measure these separately:

  • Reveals. Head, sill and both jambs of every window and door in the lining, as linear metres.
  • External corners. Corner bead and the extra framing at returns.
  • Abutments. Junctions with partitions, columns and other linings, where sealant or extra track is needed.
  • Head and base details. Any special head, deflection or base detail on the lining.
  • Service boxes and pattresses. Numbered items where the specification calls for backing or boxing in.

Reveals take far more time per metre than plain lining, so they belong on their own line, not hidden in the rate per m².

How do you build the rate per m²?

Build it in the same layers as any drylining rate:

LayerHow it is worked outUnit
MaterialsBoard, studs, track, fixings, finishing, insulation and sealant per m², plus wasteper m²
Framing labourDay rate / framing output per operative per dayper m²
Boarding labourDay rate / boarding output per operative per dayper m²
Finishing labourDay rate / taping or skimming output per operative per dayper m²
RevealsMaterial and labour per linear metreper m
Access and job costsTowers, distribution and waste removal / area, or as itemsper m²
Overheads and profitMarkup on the cost aboveper m²

Labour outputs should come from your own linings, not from partitions. A lining is boarded on one side only, but working close to the wall and around services changes the pace. The guide to stud centres and deflection heads explains what the frame itself may need at height.

For illustration only, with assumed figures: a lining 18.0 m long and 3.0 m high is 54.0 m² gross. Two windows of 1.2 m by 1.5 m take off 3.6 m², leaving 50.4 m² net. Each window has a head, a sill and two jambs, which is 1.2 + 1.2 + 1.5 + 1.5 = 5.4 m of reveal, so 10.8 m in total, priced as a linear item. At an assumed material cost of £16.00 per m² and labour of £17.50 per m², the lining itself costs 50.4 x £33.50 = £1,688.40, before reveals, access, overheads and profit.

What gets missed when pricing linings?

The same few items come up again and again:

  • Reveals left in the rate per m² instead of priced by the metre
  • Taller walls priced at the same rate as low ones
  • Insulation in the cavity left out because it was on a different drawing
  • Sealant at abutments where the lining has an acoustic or fire rating
  • Time for working around services already fixed to the wall

Read your take-off against the specification one more time before it goes into the price. The guide to pricing a drylining job covers the rest of the offer around it.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

What is the difference between an independent lining and a direct-fixed lining?

An independent lining stands on its own frame in head and floor track, clear of the wall. A direct-fixed lining is fixed back to the wall itself, so it needs no free-standing frame.

Should I deduct windows from the lining area?

Follow your measurement rules or the contract. Many firms deduct only larger openings and price the reveals as linear items either way.

How do I price reveals?

Price them per linear metre, with their own material and labour. They are slower than plain lining and should not be hidden in the rate per m².

Does a tall lining need a different rate?

Yes. Taller linings may need a deeper frame or intermediate restraint and more access, so give each height band its own rate.