Weekly cost report for a drylining job
Last updated 2026-11-10 · 6 min read
A weekly cost report for a drylining job sets what the job cost last week against the tender allowance for the work actually completed that week, line by line: labour by activity, supervision, materials and plant. Add the quantities done, hours lost and new orders. Kept to one page and produced every Monday, it shows a problem within days.
The monthly cost value reconciliation tells you where the margin stands. The weekly report is shorter and rougher, and its job is different: to catch a gang running slow or a material overrun while there is still time to change something on site.
Why compare cost with work done, not time spent?
Because a job can be on budget for the time elapsed and still losing money. If the programme says you should have spent a third of the labour by week six, and you have, that looks fine. But if only a quarter of the work is finished, the labour is running a third over.
So the comparison in a weekly report is always against the allowance earned: what your tender allowed for the quantities completed this week. If you boarded 300 m² this week, the allowance is whatever your build-up allowed for boarding 300 m², not a sixth of the boarding budget.
Where do the weekly figures come from?
| Line | Cost this week from | Work done from |
|---|---|---|
| Labour, by activity | Timesheets or gang payments, split by activity and area | Quantities measured, or the price-work measure |
| Supervision | Supervisor's hours on this job | Not measured, compared with the weekly allowance |
| Materials | Delivery notes and goods received this week, at order prices | Quantities installed this week |
| Plant and access | Hire log: what is on site and the weekly rate | Not measured, compared with the weekly allowance |
| Other job costs | Skips, small tools, travel booked to the job | Compared with the weekly allowance |
The daily site reports are where the quantities, hours lost and their causes come from. If they are not filled in, the weekly report can only show cost, not whether it was worth it.
What does the template look like?
| Line | Cost this week | Allowance for work done this week | Variance this week | Cost to date | Allowance to date | Variance to date |
|---|---|---|---|---|---|---|
| Framing labour | ||||||
| Boarding labour | ||||||
| Taping and jointing labour | ||||||
| Supervision | ||||||
| Materials received | ||||||
| Plant and access | ||||||
| Other job costs | ||||||
| Total |
Under the table, add four short lines:
- Quantities completed this week, by activity and area
- Hours lost, with the cause: access, other trades, materials, weather, rework
- Orders placed this week that are not yet delivered
- Actions, with a name and a date against each one
What does a reported week look like?
For illustration only, with assumed figures.
| Line | Cost this week | Allowance for work done this week | Variance this week |
|---|---|---|---|
| Framing labour | £2,100 | £2,300 | £200 under |
| Boarding labour | £4,900 | £4,200 | £700 over |
| Taping and jointing labour | £1,200 | £1,250 | £50 under |
| Supervision | £1,000 | £1,000 | None |
| Materials received | £6,100 | £5,800 | £300 over |
| Plant and access | £650 | £500 | £150 over |
| Total | £15,950 | £15,050 | £900 over |
Notes for the week: 300 m² boarded on level 3, two operatives lost a morning waiting for the hoist, an extra tower hired for the stair core, and boards for level 4 ordered but not yet delivered.
Reading it: boarding labour is the line to look at. Part of the overrun is the lost morning, which is the main contractor's hoist and worth recording as a possible claim. The rest is output, and needs a word with the supervisor. The materials figure is probably timing, because boards arrived for the next area before they were installed. Check that next week, rather than assuming it.
How does the weekly report feed the monthly figures?
Each week's report adds to the cost to date. At the month end, check those totals against your accounts. Add any cost the weekly reports missed, such as hire or labour not yet booked, but not deliveries already counted from goods received, or they are counted twice. The result is the cost side of your CVR. The weekly view also feeds the cost-to-complete figure when you track margin on the live job, and the line totals carry into your budget vs actual.
Keep each week's report, rather than overwriting one file. A run of weeks shows whether a line is drifting or had one bad week.
Who should produce it, and when?
Whoever runs the job commercially, with the supervisor's quantities and timesheets in by Friday. Aim to have it with the director on Monday morning, so any change can be made that week. Spend no more than an hour on it. If it takes longer, the inputs need sorting out, not the report.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Is a weekly cost report the same as a CVR?
No. A CVR is monthly and reconciles value with cost, including accruals and provisions. The weekly report is a quicker check of cost against work done.
Should materials be counted when delivered or when installed?
Report cost when goods are received, and compare it with the quantity installed. The gap is stock on site, and it should clear within a week or two.
What if we do not measure quantities every week?
Then the report can only show cost against time. Even a rough weekly measure by area is better than none.
Can I download this weekly cost report template?
There is no download. Copy the table on this page into your own spreadsheet and keep one tab per week.