Budget vs actual cost template for a drylining job

Last updated 2026-11-08 · 6 min read

Short answer

A budget vs actual template sets each cost line of a drylining job, as priced in the tender, against what the job has really cost. Use the same lines as your build-up: materials by group, labour by activity, access and job costs. The variance on each line shows where the margin is going, while there is still time to act.

A budget is only useful if the actual costs land on the same lines. If the tender priced boards, metal and labour separately but the costs come in as one heap of invoices and wages, the comparison tells you nothing about why.

What lines should the budget have?

Take them straight from the build-up that won the job:

  • Materials by group. Boards, metal, insulation, fixings and finishing, sundries.
  • Labour by activity. Framing, boarding, taping and jointing or skimming, and any specialist work.
  • Access and job costs. Towers, podiums, distribution, waste removal and supervision.
  • Variations. A separate line for each instructed variation, with its own budget once it is valued.

Keep the number of lines small enough to fill in every week. Ten honest lines are worth more than forty that nobody updates.

What does the template look like?

Copy this table into your spreadsheet, one sheet per job:

LineBudgetCommittedActual to dateForecast finalVariance
Boards
Metal
Insulation
Fixings and finishing
Sundries
Framing labour
Boarding labour
Taping and jointing labour
Access and job costs
Variations
Total

Committed is what you have ordered but not yet been invoiced for. Forecast final is actual to date plus what you expect it to cost to finish. Variance is forecast final minus budget.

What does a filled-in example look like?

Here is an example of the entries, with the amounts left out:

LineExample entry
BoardsBudget from the tender build-up, committed from open purchase orders, actual from checked invoices
MetalExtra studs ordered after a change to the head detail, noted against the line
Framing labourActual from timesheets for framing only, not the whole gang's week
Boarding labourSlower than priced on level two because of stop-start access
Access and job costsExtra tower hire for two weeks while the hoist was out of use
VariationsBulkhead to corridor, own budget once valued and instructed

Where do the actual figures come from?

Each column needs a source you trust:

  • Materials. Invoices checked against the order and the delivery, so you post what you really owe. The guide to checking supplier invoices covers how.
  • Committed. Purchase orders and call-offs not yet invoiced.
  • Labour. Timesheets or daily reports split by activity, not one total per week.
  • Job costs. Hire invoices, waste removal and any other cost charged to the job.

The ledger always lags behind the site. Add goods received but not yet invoiced, or the job will look better than it is.

How do you read the variance?

Look at each line, not just the total. A total close to budget can hide an overspend on labour covered by a lucky material price, and that will not happen twice.

For each line that has moved, ask whether it is a quantity problem, a rate problem or a timing problem. More board than budgeted points at the take-off or at waste. Labour over budget at the same quantity points at outputs or access. Costs that are only early will settle by the end.

For illustration only, with assumed figures: a job with a contract value of £50,000 is budgeted at £18,400 for materials, £22,600 for labour and £3,000 for job costs, so £44,000 in total and a margin of £6,000, or 12.0%. At completion the actual costs are £19,150, £24,350 and £2,900, so £46,400. Materials are £750 over, labour £1,750 over and job costs £100 under, a variance of £2,400. The margin is £3,600, or 7.2%.

How often should you update it?

Weekly on a busy job, and at least before every payment application. Update the forecast at the same time, because a forecast that only moves at the end gives no warning.

Use the result alongside the monthly figures for the job. The guide to tracking margin on a live interiors job covers what to watch between updates.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

What is the difference between committed and actual cost?

Committed cost is what you have ordered but not yet been invoiced for. Actual cost is what has been invoiced or paid, plus anything received and not yet invoiced.

Should variations go in the original budget?

No. Give each instructed variation its own line and budget, so the original budget stays a fair test of the tender.

How many lines should the budget have?

Usually ten to fifteen. Enough to match the build-up, few enough to update every week.

Can I download this budget vs actual template?

There is no download. Copy the tables on this page into your own spreadsheet, one sheet per job.