Preliminaries a drylining subcontractor should price

Last updated 2026-11-10 · 5 min read

Short answer

A subcontractor's preliminaries are the costs of running your package on site that are not part of any measured rate: supervision, site set-up, vans and travel, paperwork, small tools and waste handling. Split them into fixed costs and time-related costs per week, price them from the programme, and keep them separate from your head office overheads.

Main contractors have long preliminaries sections in their tenders. Subcontractors often have none, and the same costs end up spread loosely through the rates, or missed. Pricing them as their own list makes the price easier to check and easier to adjust when the programme changes.

How are preliminaries different from overheads?

  • Preliminaries are costs caused by this job: the supervisor on this site, the van going to it, the inductions for it.
  • Overheads are the costs of running the business, whatever jobs you have: the office, the accounts, the estimators.

Overheads are recovered across all jobs through a rate, as the guide to overhead recovery explains. Preliminaries belong to one job and should be priced from its own programme and conditions.

Which preliminaries should a drylining package include?

Check each against the enquiry and the attendances the main contractor provides. Price only what is yours.

Fixed costs, incurred once:

  • Mobilisation, site set-up and final clearance
  • RAMS, inductions and the start-of-job paperwork
  • Training or cards required for this site
  • Handover documents at the end

Time-related costs, incurred for each week you are on site:

  • Supervision, full time or part time
  • Vans, fuel, travel and parking
  • Small tools, consumables and safety equipment
  • Labour for clearing and bagging your own waste
  • Storage, if you need a container or secure area

Access equipment and distribution are often large enough to price as their own build-ups. The guide to pricing a drylining job lists them with the other costs around the work.

What does a preliminaries build-up look like?

For illustration only, with assumed figures. These are not market rates. A 16-week drylining package in a city centre, with welfare, power and skips provided by the main contractor.

ItemBasisCost
Supervisor, three days a week16 weeks x 3 days x £220£10,560
Site set-up and final clearanceFixed£600
RAMS, inductions and paperworkFixed£800
Vans and fuel16 weeks x £150£2,400
Parking and congestion charges16 weeks x £75£1,200
Small tools and consumables16 weeks x £40£640
Waste clearing to the main contractor's skips16 weeks x 4 hours x £30£1,920
Total£18,120

Of this, £1,400 is fixed and £16,720 is time-related, about £1,045 for each week on site. That weekly figure is worth knowing: it tells you what each extra week costs if the programme stretches.

Where do preliminaries go in your price?

You can show them as a separate section in the tender, if the enquiry has a place for them, or spread them over the measured rates. The guide to building a drylining rate explains the choice for job costs generally.

Showing them separately has two advantages. The main contractor can see what you have allowed for the programme. And if the programme is extended for reasons that are not yours, your time-related costs per week are already set out. Whether you can recover them depends on your subcontract and the cause of the delay, so check the terms and keep records.

Spreading them over the rates keeps the tender simple, but if quantities are reduced, the preliminaries go with them.

What do subcontractors most often miss?

  • Supervision for the full programme, not just the busy weeks
  • Return visits for snagging after the main team has left
  • Parking and travel in city centres
  • Time for site meetings, valuations and progress reports
  • Waste labour where skips are provided but loading is not
  • A longer programme than your own estimate of the work, when the main contractor's programme sets the dates

Price from the main contractor's programme for your package, not the shortest time in which your gangs could do the work.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Do subcontractors price preliminaries?

Many do, either as a separate section or within their rates. Either way, the site costs of running the package need to be in the price.

Are preliminaries the same as overheads?

No. Preliminaries are the site costs of one job. Overheads are the business's running costs, recovered across all jobs.

Should preliminaries be a percentage of the price?

A percentage is a rough check, not a build-up. Price them from the programme and the conditions on the job.

Can I claim extra preliminaries if the job overruns?

Possibly, depending on your subcontract and why the job overran. Keep weekly records of time-related costs and notify delays as the subcontract requires.