How to calculate your overhead recovery rate
Last updated 2026-11-10 · 6 min read
Your overhead recovery rate is your overhead budget for the year divided by the base you recover it over, usually expected turnover, direct cost or labour days. Add that rate to every price, before profit. Then check each month how much overhead your work has actually recovered against what the overheads cost, because a quiet month leaves a shortfall.
Every job has to carry a share of the costs of running the business. The recovery rate is how you set that share in advance, so that each price carries enough, and so you notice early in the year if it is not.
What goes into the overhead budget?
Overheads are the costs that no single job causes. Start from last year's accounts, then adjust for what you know is changing.
| Overhead line | What it covers |
|---|---|
| Office staff | Estimators, buyers, accounts and admin, with on-costs |
| Directors | Salaries or drawings for running the business, not site work |
| Premises | Rent, rates, utilities, the yard |
| Vehicles | Company vehicles not costed to one job |
| Insurance | Employer's and public liability, other business cover |
| Professional fees | Accountant, legal, accreditations and memberships |
| Systems | Software, phones, IT |
| Finance | Bank charges, interest, credit insurance |
| Other | Training not booked to jobs, marketing, tender costs |
Leave out anything you code to jobs, such as supervision on site, hire or job travel. Counting a cost in both places overprices your work. The guide to margin on a drylining subcontract covers where the line between direct cost and overhead sits.
Which base should you recover overheads over?
| Base | Rate is | Suits | Watch out for |
|---|---|---|---|
| Turnover | Overheads / expected turnover, as a share of price | A steady mix of similar work | Material-heavy jobs carry more overhead than they cause |
| Direct cost | Overheads / expected direct cost, as an addition to cost | Pricing from cost build-ups | Needs a realistic forecast of direct cost |
| Labour days | Overheads / expected productive labour days | A mix of labour-only and supply-and-fix work | Needs reliable records of labour days |
Pick one, use it on every price, and write down which it is. A rate set as a share of turnover is not the same as the same figure added to cost. The guide to markup vs margin explains the difference.
What does the calculation look like?
For illustration only, with assumed figures. A subcontractor budgets £180,000 of overheads for the year. It expects £1,500,000 of turnover, £1,260,000 of direct cost, and 3,600 productive labour days from its own and engaged labour.
| Base | Calculation | Recovery rate |
|---|---|---|
| Turnover | £180,000 / £1,500,000 | 12% of the selling price |
| Direct cost | £180,000 / £1,260,000 | 14.3% added to direct cost |
| Labour days | £180,000 / 3,600 | £50 per productive labour day |
Each one recovers £180,000 if the year goes to plan. They differ in which jobs carry the most of it. A supply-and-fix job with heavy materials carries more under a turnover or direct cost base than under a labour-day base.
Where does the rate sit in a price?
After direct costs and before profit. Work out the direct cost of the job, add overheads at your recovery rate, then add profit. If you price to a target margin on the selling price, make sure the margin covers overheads as well as profit, or add overheads first. The guide to building a drylining rate shows how each layer goes on.
How do you spot under-recovery?
Each month, compare the overhead your work has recovered with what the overheads actually cost.
For illustration only, continuing the example with a 12% turnover rate and overheads of £15,000 a month:
| Month | Turnover | Overhead recovered at 12% | Actual overheads | Running shortfall |
|---|---|---|---|---|
| 1 | £130,000 | £15,600 | £15,000 | £600 over |
| 2 | £105,000 | £12,600 | £15,000 | £1,800 short |
| 3 | £95,000 | £11,400 | £15,000 | £5,400 short |
Turnover has fallen below the plan of £125,000 a month, and the overheads have not. The shortfall comes straight out of the profit the jobs were priced to make. The answer is not usually to raise the rate on the next tender, which makes you less competitive when work is short. Look first at whether the overheads or the turnover forecast need to change.
How often should you review the rate?
At least once a year, when you set the budget, and again if turnover or overheads move a long way from the plan. Use the same rate for every tender in between, so that prices are comparable and the estimator is not guessing.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
What is a typical overhead recovery rate?
It depends on the size of the business, its mix of work and its base. Work out your own from your accounts rather than using someone else's figure.
Should the overhead rate change for a large job?
Some businesses use a lower rate on a large job that adds little to overheads. Decide that deliberately, and check the year still recovers the full budget.
Is supervision an overhead?
Site supervision on a particular job is usually a direct cost of that job. General management across all jobs is an overhead.
What happens if I over-recover overheads?
The surplus adds to profit for the year. If it keeps happening, your prices may be higher than they need to be.