How to calculate margin on a drylining subcontract

Last updated 2026-11-08 · 6 min read

Short answer

To calculate margin on a drylining subcontract, take the net subcontract value after any discount the main contractor deducts, subtract every cost of doing the work, and divide what is left by that net value. Work out gross margin before overheads and net margin after them, and recalculate at tender, at award and when the account closes.

Margin is a simple sum. The work is in getting both sides of it right: the value you will really be paid, and every cost the job will really carry. Most margin that disappears on a subcontract was never in the sum to begin with.

What is the formula for margin on a subcontract?

Margin is what you keep as a share of what you are paid:

  • Margin = (net subcontract value - total cost) / net subcontract value
  • Gross margin uses the costs of the job only: materials, labour, access and job preliminaries.
  • Net margin also takes off the share of your company overheads the job has to carry.

Always divide by the value, not by the cost. Dividing by cost gives you markup, which is a different and larger number for the same job.

What counts as the subcontract value?

Start from the figure in the subcontract order, not the one in your quote. They are often different by the time the order arrives.

Then take off anything the main contractor deducts before it pays you. Read the order and its terms for:

  • A discount taken from every payment, sometimes called a main contractor's discount.
  • Contributions to site costs such as skips, welfare, cleaning or insurance.
  • Items you priced that have been omitted from the order.

Retention is not a deduction from the value. It is part of what you will be paid, but later. Keep it in the value and treat the delay as a cash question, which the guide to payment applications and retention covers.

Which costs go into the calculation?

Every cost the job causes, whether or not it is on the drawings:

  • Materials. All system components, with waste, sundries, delivery charges and any part loads.
  • Labour. Your own operatives at their full cost, including on-costs, plus any labour-only gangs.
  • Supervision. The time of the chargehand or supervisor who runs the job.
  • Access and plant. Towers, podiums and anything hired.
  • Job preliminaries. Waste removal, protection, distribution, travel and return visits.

If your price was built properly, these lines are already in your build-up. The guide to pricing a drylining job sets out what that build-up should hold.

How do overheads change the answer?

Overheads are the costs of running the business that no single job causes: the office, vehicles not on site, insurance, accounts and your own time. Every job has to carry a share of them.

Decide how you share them out, for example as a share of each job's value, and use the same method on every job. A job can show a healthy gross margin and still lose money once its share of overheads comes off.

What does the calculation look like laid out?

Set it out in this order, so each line can be checked:

LineHow it is worked out
Subcontract valueThe figure on the subcontract order
DeductionsDiscounts and contributions taken from each payment
Net subcontract valueSubcontract value - deductions
Direct costsMaterials + labour + supervision + access + job preliminaries
Gross profitNet subcontract value - direct costs
Gross marginGross profit / net subcontract value
Overhead shareYour overhead method applied to this job
Net profitGross profit - overhead share
Net marginNet profit / net subcontract value

For illustration only, with assumed figures: a subcontract order for £120,000 with a 2.5% discount taken from each payment has a net value of £117,000. Materials of £38,000, labour of £52,000 and access and job preliminaries of £6,500 make direct costs of £96,500. Gross profit is £20,500, a gross margin of about 17.5%. An overhead share of £9,000 leaves net profit of £11,500, a net margin of about 9.8%.

When should you recalculate the margin?

At least three times on every job:

  • At tender, from your build-up, so you know what you are offering.
  • At award, against the order you actually received, with its deductions and omissions.
  • At final account, against what you were paid and what the job really cost.

Between award and final account, the margin moves every week with labour, materials and variations. The guide to tracking margin on a live interiors job shows how to keep that forecast up to date.

Why does margin on paper differ from what you keep?

Because the sum at tender assumes things that change. Common reasons are:

  • Labour outputs lower than you priced, through access, sequencing or return visits.
  • Materials bought at prices other than the ones in your build-up.
  • Variations carried out but not agreed or valued.
  • Deductions in the subcontract terms that were not in the tender.

Compare the final margin with the tender margin on every closed job, line by line. The difference tells you which part of your next price needs to change.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Is margin the same as markup?

No. Margin divides profit by the selling price, while markup divides it by the cost, so the same job always shows a lower margin than markup.

Should retention come off the subcontract value?

No. Retention is still yours, just paid later, so keep it in the value and plan for the cash it holds back.

Should I include my own time in the costs?

Yes. If you supervise or manage the job, include that time either in the direct costs or in the overhead share, but not in both.

What margin should a drylining subcontract make?

There is no single right figure. Work out the gross margin you need to cover your overheads and leave a profit, then check every price against it.