Subcontract order checklist before you sign

Last updated 2026-11-10 · 6 min read

Short answer

Before you sign a subcontract order, check that it names the right parties, lists the documents and revisions you priced, describes the same scope as your quote, and states the price, programme, payment dates, retention, discounts and tax treatment you expected. Then read the liabilities: damages, set-off, design and insurance. Raise every difference in writing before you sign or start.

The order is where the commercial deal becomes the contract. A price can be won on one set of terms and signed on another, and the differences are often in documents incorporated by reference that nobody on your side has read.

Why check the order line by line?

Orders are often drafted from the main contractor's standard template, with your price typed in. The template may cancel your quote, change the payment terms you tendered on, or pass down obligations from the main contract you have never seen. Once you sign, or in some cases once you start work, those terms may bind you.

This checklist covers the points that most often cause trouble for interiors subcontractors. It is a general guide, not legal advice. For a large or unusual order, take advice before you sign.

What should you check in the order?

AreaWhat to checkWhy it matters
PartiesThe correct legal names of both companiesYou need to know who you can claim against
Contract formThe standard form and edition, and every amendmentAmendments can reverse the standard position
DocumentsDrawings, specifications and revisions listedYou should be bound to what you priced
Your quoteListed as a contract document, with date and referenceOtherwise your qualifications may be lost
ScopeThe description matches your quote line by lineWide wording can add work at no extra price
Price basisLump sum, remeasure or schedule of rates; firm or with fluctuationsDecides who carries quantity and price risk
ProgrammeStart, completion and any sections or key datesSets the dates you can be held to
Damages for delayWhether damages are passed down, and at what rate or capA late finish can cost more than the margin
PaymentValuation dates, due dates, final dates and noticesYour cash flow depends on them
RetentionPercentage, any cap and release datesMoney held to the end of the defects period
DiscountsAny discount deducted from paymentsReduces every payment you receive
CIS and VATYour CIS status and the VAT treatment agreedAffects every invoice and payment
VariationsWho can instruct and whether it must be in writingUnwritten instructions are hard to get paid
Set-off and contra chargesWhat can be deducted and on what noticeDeductions come straight off your payment
AttendancesWhat the main contractor providesMissing facilities become your cost
DesignAny design responsibility beyond selecting specified systemsDesign liability may not be insured
InsuranceCover types and levels requiredCheck against your actual policies
Bonds and warrantiesAny bond, parent guarantee or collateral warrantyExtra cost and long-term liability

How do you check the payment terms?

Compare the dates and notices in the order with the cycle you expected when you priced. The guide to the Construction Act payment timetable explains the steps and what happens when a subcontract does not set workable dates. The guide to payment applications and retention covers applying for payment and getting retention released.

Check how retention and any discount are calculated, and on what figure, because the order of the deductions changes the amount you receive. Ask for a worked example if the wording is unclear.

How do you check CIS and VAT?

Confirm that the main contractor has your correct details for the Construction Industry Scheme, and that your status has been verified with HMRC, so the right deduction is made from your labour. Confirm whether the VAT domestic reverse charge applies to your invoices. The guides to CIS deductions and the VAT reverse charge explain the general rules. HMRC guidance on gov.uk and your accountant can confirm how they apply to you.

What about terms from the main contract?

Many orders say the subcontract is "back to back" with the main contract, or incorporate its terms. Ask for copies of any document the order refers to, especially the parts setting damages, design duties and programme. You cannot manage obligations you have not read.

What should you do when something does not match?

  • List every difference in one letter or email, item by item
  • Propose the wording you want, rather than just objecting
  • Wait for a written reply before you sign or start, where you can
  • Keep the agreed changes with the signed order

Your quote's qualifications only protect you if the order keeps them. The guide to qualifications and exclusions explains how to check that they survive.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Can I start work before the subcontract order is signed?

Many subcontractors do, but it can leave the terms uncertain or accepted by conduct. Agree the key terms in writing before you start.

What if the order says it replaces all earlier correspondence?

Your quote and its qualifications may then not form part of the contract. Ask for your quote to be listed as a contract document.

Do I have a right to adjudication under a subcontract?

Under the Construction Act, a party to a construction contract can generally refer a dispute to adjudication at any time. Check whether the Act applies to your subcontract and take advice on any dispute.

Related guides

Qualifications and exclusions on a drylining quotePayment timetable under the Construction Act for subcontractorsPayment applications and retention for drylining subcontractors