Payment timetable under the Construction Act for subcontractors

Last updated 2026-11-10 · 6 min read

Short answer

Under the Construction Act, each payment cycle runs in order: a due date, a payment notice within 5 days of it, an optional pay less notice before the final date for payment, then the final date itself. Your subcontract sets the actual periods. If it does not set workable ones, the Scheme for Construction Contracts fills the gaps.

Knowing the order matters as much as knowing the dates. Each step changes what you can expect to be paid, so read the timetable at the start of the job, not at the first short payment.

This guide describes the general rules in the Housing Grants, Construction and Regeneration Act 1996, as amended (the Construction Act), for England and Wales. Scotland has its own version of the Scheme, and Northern Ireland has its own legislation. It is not legal advice. Always check your own subcontract.

Which subcontracts does the Act cover?

Most drylining and interiors subcontracts are construction contracts under the Act. There are exceptions, the best known being work for a residential occupier on their own home. Where the Act applies, a subcontract expected to last 45 days or more must provide for interim or stage payments.

What are the steps in each payment cycle?

The Act sets the sequence. Your subcontract fills in the periods.

StepWho actsWhat it does
ApplicationYouYour claim for the value of work to the valuation date, if the subcontract asks for one
Due dateSet by the subcontractThe date the payment becomes due
Payment noticePayer, or a person the subcontract namesStates the sum considered due and how it was worked out; required no later than 5 days after the due date
Pay less noticePayer, or a named personOnly needed to pay less than the notified sum; must state the sum considered due and the basis
Final date for paymentSet by the subcontractThe last day to pay without being in breach

If the payer does not give a payment notice, your application, or a default notice you give under the Act, can become the notified sum. So follow the dates and the method for sending applications in your subcontract to the letter.

What happens if the subcontract does not set the dates?

Where a subcontract does not contain an adequate payment mechanism, the relevant parts of the Scheme for Construction Contracts apply instead. For interim payments under the Scheme in England and Wales:

  • Payment becomes due on whichever is later: 7 days after the end of the relevant period, or the date you make your claim
  • The final date for payment is 17 days after the due date
  • A pay less notice must be given no later than 7 days before the final date

Since the 2011 amendments, a subcontract also cannot make payment depend on obligations or decisions under another contract, such as the main contract being certified. Pay-when-paid clauses are generally ineffective, except where an upstream payer is insolvent.

What does a cycle look like in practice?

The timeline below is for illustration only, with assumed contract terms: an application on day 0, a due date 7 days later, a final date for payment 30 days after the due date, and a pay less period of 7 days. Your subcontract will have its own periods.

DayEventWhat you should do
0Application sentSend by the method the subcontract names and keep proof
7Due dateDiary the payment notice deadline
12Last day for the payment noticeIf none arrives, check whether your application stands as the notified sum
30Last day for a pay less noticeRead any notice the day it arrives and reply in writing
37Final date for paymentCheck the amount received against the notified sum

When counting days under the Act, Christmas Day, Good Friday and bank holidays are left out. Weekends are counted.

How should you use the timetable?

Put every date for the whole job into a calendar at the start, not month by month. Then:

  • Agree who sends applications and who receives notices on each side
  • Note the method of service, such as a named email address
  • Check each payment against the notified sum, not against your application
  • Keep a short register of applications, notices and payments for the job

The guide to payment applications and retention covers what goes into each application. If your quotes state payment terms, the guide to setting out a drylining quote shows where they belong, so the terms you priced on are the terms you later sign. For changes during the job, keep a variations record that feeds every application.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Does the Construction Act set a maximum payment period?

The Construction Act itself does not set a maximum payment period. It requires an adequate payment mechanism and a final date for payment, and the Scheme fills the gaps. Separate late-payment rules or public-sector policies may also apply, so check current guidance on gov.uk and your subcontract.

What is the difference between the due date and the final date for payment?

The due date is when the payment becomes due. The final date is the last day the payer can pay without being in breach.

Is a pay-when-paid clause valid?

Generally not, except where the party upstream is insolvent. Take advice if your subcontract contains one.

What if I miss my application date?

It may push your claim into the next cycle, depending on your subcontract. Diary every application date at the start of the job.