Profit per job: a simple report for directors

Last updated 2026-11-10 · 6 min read

Short answer

A profit per job report puts every job on one line: value including variations, forecast final cost, forecast profit and margin, the margin it was tendered at, and the gap between the two in pounds. Directors read it monthly to see which jobs, clients and types of work make money, and where the business is losing what it priced.

Each job's commercial figures tell you how that job is going. The director's question is wider: across everything we are doing, where is the profit coming from, and where is it leaking? That needs every job in one table, worked out the same way.

What goes on each line?

One row per job, live and recently finished, with these columns:

  • Job and client
  • Type, such as labour-only or supply-and-fix, and the sector
  • Status: live, or complete with the date
  • Value: the subcontract sum plus variations you realistically expect to agree
  • Forecast final cost: cost to date plus cost to complete
  • Forecast profit and margin
  • Tender margin: the margin the job was priced at
  • Profit against tender: forecast profit minus what the tender margin would have made on the same value
  • Retention held: what is still to come back

Take each job's figures from its latest monthly reconciliation, so that the report repeats numbers already checked. The CVR template sets those out. If a job has no forecast this month, show it as missing rather than carrying last month's figure.

What does the blank report look like?

JobClientTypeStatusValueForecast final costForecast profitForecast marginTender marginProfit against tenderRetention held
Total

What does a filled-in report look like?

For illustration only, with assumed figures.

JobStatusValueForecast final costForecast profitForecast marginTender marginProfit against tender
A: office fit-outLive£240,000£206,400£33,60014.0%15.0%-£2,400
B: schoolComplete£96,000£88,300£7,7008.0%14.0%-£5,740
C: hotelLive£410,000£369,000£41,00010.0%12.0%-£8,200
D: retail unitComplete£28,000£22,960£5,04018.0%16.0%£560
E: residentialLive£155,000£137,950£17,05011.0%13.0%-£3,100
Total£929,000£824,610£104,39011.2%-£18,880

The profit against tender for each job is its forecast profit minus its value times its tender margin. For job A, that is £33,600 - (£240,000 x 15%) = -£2,400.

How do you read it?

Start with the last column, in pounds, not the margin column. Job B has the worst margin, but job C has lost the most money against its price, because it is the biggest job. A two-point slip on a large job outweighs a bad small one.

Then look for patterns rather than single jobs:

  • By client. Does one main contractor's work slip every time? It may be their contra charges, their programme or their valuations.
  • By type. Do supply-and-fix jobs hold their margin better or worse than labour-only?
  • By size. Do small jobs do better because they are simple, or worse because return visits are never priced?
  • By stage. Do margins drop in the last months of a job? Snagging, return visits and late contra charges usually land then.

In the example, every live job is forecasting below its tender, and the only job above tender is the smallest. That points to something in how larger jobs are priced or run, rather than bad luck on one site.

Where do overheads come in?

The report shows forecast profit for each whole job, before overheads, so it is not the profit for one month: a long job's profit would appear in every month's total. For a month, take the profit earned on work done that month from your CVR and subtract that month's overheads. For the year, compare the forecast job profit on the year's work with the year's overheads. If it will not cover them, no single job looks like the problem, but the business is losing money. The guide to margin on a drylining subcontract explains gross and net margin.

How do you keep it honest?

  • Use forecast final figures, not cost to date, or every early job looks profitable
  • Count only variations you realistically expect to agree
  • Keep finished jobs on the report until the retention is back and the account is settled
  • Note any big movement since last month in one line beside the job
  • Keep each month's report, so you can see whether forecasts were too hopeful

The live view behind each line comes from tracking margin on the live job. This report only works if those forecasts are kept up to date.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

How often should directors see a profit per job report?

Monthly, after the job reconciliations are done. A weekly version is rarely worth it, because forecasts do not move that fast.

Should finished jobs stay on the report?

Yes, until the retention is released and the account is agreed. Finished jobs are where late costs and contra charges show up.

Why compare against tender margin and not a company target?

Because the tender margin is what each job was priced to make. The gap shows where pricing or delivery went wrong on that job.

Can I download this report template?

There is no download. Copy the table on this page into your own spreadsheet, one row per job.