Pricing from a schedule of rates
Last updated 2026-11-10 · 6 min read
A schedule of rates lists items and units but gives no firm quantities, so every rate has to stand on its own. Price each item with its own labour, materials and margin, decide how fixed job costs are recovered if the volume never arrives, and state the conditions each rate assumes, such as height, location and minimum quantity per visit.
Schedules of rates turn up on term contracts, frameworks, refurbishment work in occupied buildings, and fit-outs where the design is not finished when the package is let. The arithmetic is the same as any rate. The risk is different, because the quantity is not yours to control.
How is a schedule of rates different from a bill of quantities?
In a bill of quantities the quantities are given, so your total price is fixed for the scope measured and only changes through variations or remeasurement. In a schedule of rates you price a unit, and the client instructs as much or as little work as it needs. Your income depends on the volume instructed, which may be far from what you expected.
That changes three things:
- Fixed costs cannot be spread over a known quantity
- Rates may be used for months or years, so price movements matter more
- Small orders carry the same set-up costs as large ones
Some enquiries give notional quantities so that tenders can be compared. Those quantities are for evaluation only unless the documents say otherwise. Read the preliminaries to find out whether any volume is promised.
What should each rate include?
Build each rate the same way you would build any drylining rate: materials with waste, labour from your own outputs, and your overheads and profit. On a schedule, also decide for every item:
- Whether access is included, and up to what height
- Whether distribution to the workface is included
- Which finish the rate covers, for example taped and jointed ready for decoration
- Whether small quantities are priced at the same rate or at a minimum charge
- Whether the rate applies in occupied areas, or out of hours
Write these as conditions in the schedule's notes or your covering offer, not in an email that gets lost.
Where do fixed job costs go?
Supervision set-up, site inductions, RAMS, initial access equipment and the first visit cost the same whether the client orders 50 m² or 500 m². On a bill of quantities you can spread them over the known area. On a schedule you have three choices:
- Spread them over an assumed quantity. Simple, but you under-recover if the volume is lower.
- Price them as separate items, such as a mobilisation charge or a per-visit attendance charge, if the schedule has a place for them.
- Set a minimum order value, below which a fixed charge applies.
The second and third options keep the risk visible. The first hides it inside the rate.
What happens if the quantity is lower than you assumed?
For illustration only, with assumed figures. A subcontractor has fixed job costs of £2,400 and spreads them over an assumed 400 m², adding £6.00 per m² to the rate.
| Quantity instructed | Fixed costs recovered | Fixed costs incurred | Difference |
|---|---|---|---|
| 600 m² | £3,600 | £2,400 | £1,200 over-recovered |
| 400 m² | £2,400 | £2,400 | Nil |
| 250 m² | £1,500 | £2,400 | £900 under-recovered |
| 150 m² | £900 | £2,400 | £1,500 under-recovered |
The rate itself never changes, but the job's margin does. If the fixed costs had been priced as a separate item, the £2,400 would be recovered at any volume, and the measured rate would be £6.00 per m² lower and easier to compare.
How should you handle price changes on a long schedule?
A schedule used across a term or framework may be in force long after you priced it. Check whether the rates are fixed for the term, reviewed annually, or adjusted by a formula. If they are fixed, your material and labour prices need to hold for that long, or the risk has to be priced in. The guide to fixed price vs fluctuations explains the clauses that move this risk.
What should you check before you submit?
- The measurement rules the schedule uses, and whether openings are deducted
- Item descriptions that cover more than one system or board type in a single rate
- Items you cannot price, which should be qualified rather than left blank
- Whether daywork rates are asked for alongside the schedule
- Conditions such as access, hours and minimum quantities, written down
Where a condition is essential, the guide to qualifications and exclusions shows how to word it so it survives into the order.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Is a schedule of rates a lump sum price?
No. You price units, and the total depends on the quantity the client instructs and measures. Check the documents for any promised volume.
Can I charge a minimum amount for small orders?
Only if the schedule or your agreed offer allows it. State any minimum order value or per-visit charge clearly when you tender.
Should notional quantities change my rates?
Use them to check that your total is sensible, but do not rely on them for cost recovery unless the documents commit to that volume.
How do I price an item I cannot cost?
Ask a tender query first. If there is no answer, price it on a stated assumption, or qualify it, rather than leaving the line blank.