How to price making good

Last updated 2026-11-10 · 5 min read

Short answer

Making good means repairing a surface so it matches the finish around it, usually after holes, damage or late changes. Price your own making good into your rates or as a counted item. Price making good after other trades as separate work: by size band, per visit, or as daywork. Say clearly in your offer which one your price includes.

On a drylining package, making good is rarely shown on the drawings. It turns up as service holes cut after boarding, damage from other trades, and areas left open for late work. Unpriced, it is spread thinly across the job and nobody sees what it costs.

What counts as making good on a drylining package?

There are two different kinds, and they need different treatment:

  • Your own making good. Repairs to your work before handover, finishing around your own openings, and snagging. This is part of doing the job and belongs in your price.
  • Making good after others. Patching boards cut for services, repairing damage by other trades, and re-taping after late changes. This is work caused by someone else.

Fire stopping around service penetrations is a separate specialist item, not making good. Keep it out of this price unless it is named in your package.

How do you price your own making good?

Most subcontractors add a small allowance to their rates for their own snagging and repairs, based on what it cost on past jobs. Track it on each job so the allowance reflects your actual experience, not a guess. It should cover:

  • Snagging walks and the labour to put right your own defects
  • Filling, sanding and re-taping before decoration
  • One return visit at the end to clear the main contractor's snagging list

How do you price making good after other trades?

Look at the services drawings and the programme to see where other trades will cut into finished boarding. Count the penetrations you can, sort them into size bands, and estimate the time for each band from your own records. Then add the cost of separate visits, because making good is rarely done in one continuous run.

For illustration only, with assumed figures. These are not standard outputs or market rates.

Size bandAssumed countAssumed minutes eachTotal minutes
Small holes, up to about 100 mm120101,200
Medium holes, up to about 300 mm40251,000
Large openings, frame and patch1060600
Total1702,800

2,800 minutes is about 46.7 hours. At an assumed £30 per hour, the labour is about £1,400. If the work is spread over an assumed six separate visits, each with an hour of travel and set-up, add 6 hours, or £180. Add materials such as board offcuts, filler, tape and fixings from your own records.

Counts from drawings are rarely complete, so treat this as an allowance and say what it covers.

Should you price it as an item, daywork or a provisional sum?

Each suits a different situation:

MethodWhen it suitsWhat to state
Priced item or rate per holePenetrations can be counted from the drawingsThe size bands, the number allowed and the rate for extra holes
DayworkThe extent cannot be known in advanceYour daywork rates and how sheets will be signed
Provisional sumThe main contractor names one in the enquiryThat it will be adjusted to the work actually instructed
ExcludedMaking good after others is not part of your packageThat it will be priced if instructed

If you use daywork, the guide to daywork sheets sets out what each sheet needs to get paid. If you exclude it, word the exclusion as the guide to qualifications and exclusions explains.

How do you protect yourself on site?

Record damage when you find it: photos, location and date, and who was working in the area. Report it in writing to the main contractor before you repair it, and ask for an instruction if you are to do the work.

Damage to your finished work can also come back to you as a contra charge if it is not recorded. The guide to contra charges explains how to check and challenge them.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Is making good included in a drylining price?

Your own making good usually is. Making good after other trades is only included if the enquiry or your offer says so.

Who pays for making good after other trades?

It depends on your subcontract and your offer. Where it is not in your price, record the damage and ask for an instruction before repairing it.

Is making good the same as fire stopping?

No. Fire stopping around service penetrations is specialist work with its own requirements. Price it only if it is in your package.

How do I price making good I cannot count?

Use daywork, or a provisional sum if the enquiry includes one. State your daywork rates in your tender.