Plasterboard price rises: protecting a tender
Last updated 2026-11-10 · 6 min read
To protect a tender from plasterboard price rises, price from a dated merchant quote, keep your offer's validity no longer than the quote's, and state the date your material prices are based on. Work out what a rise would cost you before you submit, and agree a price hold with the merchant once the job is won.
Board and metal prices can move between the day you price and the day the lorry arrives. This guide is about the tender stage: what to do before and just after you submit. It does not predict prices, and the figures below are examples only.
Where does the risk actually sit?
The risk is the gap between two dates: the date of the prices in your tender, and the date you place the orders. Anything that widens that gap adds exposure:
- A long tender period before award
- A late start, or a programme that slips
- Work spread over many months with phased call-offs
- A tender that stays open for acceptance long after you priced it
Write down, for each tender, the date of your material prices and the expected order dates. The wider the gap, the more real the risk on that job.
How do you match validity periods?
Your offer should not stay open longer than the prices behind it. If the merchant's quote holds for 30 days and your offer says 90, you are carrying 60 days of price risk for nothing.
When you request the merchant quote, ask:
- How long the price is held, and whether that runs from the quote date or the order date
- Whether they have already announced any increase that will land within that time
- Whether they will hold the price for the length of the job if you order by a set date
Then set your own offer validity to suit, or state that material prices are subject to confirmation after a set date.
What should the offer say about prices?
Put the basis on the page, plainly. For example: "Material prices are based on merchant quotations dated 3 March. This offer is open for acceptance for 30 days. Orders placed after that date may be subject to revised material prices."
That is a qualification, and main contractors may push back on it. It is still better that it is discussed before you sign than found after. The guide to qualifications and exclusions on a drylining quote covers how to word them and how to make sure they survive into the subcontract.
Once a fixed-price subcontract is signed, a later price rise is normally your cost unless the subcontract says otherwise. Read the price and fluctuation terms in the order before you sign it, and take advice if the wording is unclear.
How much would a rise cost you?
Test the exposure before you submit. For illustration only, with assumed figures: a tender of £60,000 has total costs of £51,000, so the profit is £9,000 and the margin is 15%. Plasterboard makes up £12,000 of the cost.
| Assumed board price rise | Extra cost | Profit left | Margin on £60,000 |
|---|---|---|---|
| None | £0 | £9,000 | 15.0% |
| 5% | £600 | £8,400 | 14.0% |
| 10% | £1,200 | £7,800 | 13.0% |
| 15% | £1,800 | £7,200 | 12.0% |
These are not forecasts. They show how sensitive one job is to one material. If a modest rise would take the job close to break-even, shorten the validity, qualify the offer or look at the price again.
What can you do once the job is won?
Move quickly. A won tender is the best time to fix the material price:
- Confirm the quote in writing against the subcontract order, with the quantities and the order-by date
- Ask for a price hold for the phased call-offs, tied to the programme
- Place an early order for the main board quantity if the price hold is not available, but only if you have dry, secure storage and the cash flow to pay for it early
- Re-check the build-up if the merchant re-quotes, and know how much margin you have lost before work starts
Early buying swaps price risk for storage and cash risk. Make that trade on purpose.
Should you add a risk allowance instead?
Sometimes. If the main contractor will not accept a qualification and the programme is long, a visible allowance for material price risk is more honest than a hidden one buried in the rates. Keep it as its own line in your build-up, so you can see whether it was used. The guide to pricing a drylining job shows where it sits alongside your other allowances.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
How long should my tender be open for acceptance?
No longer than the merchant prices behind it, unless you have allowed for the risk. Match your validity to your quotes.
Can I pass a plasterboard price increase on to the main contractor?
Only if your subcontract allows it. On a fixed-price subcontract the risk usually sits with you, so check the terms before you sign.
Should I buy all the board as soon as I win the job?
Only if you have dry storage on site or nearby and can fund the early payment. Otherwise ask the merchant for a price hold.
How do I know if a price rise is coming?
Ask your merchants whether any increase has been announced, and get their answer in writing with the quote.