Main contractor payment terms and your cash flow

Last updated 2026-11-10 · 5 min read

Short answer

Longer payment terms do not change what a job earns, but they change how much cash you need to carry it. As a rough guide, each extra month between valuation and payment adds about one more month of costs to the most you will be out of pocket. Work out that figure and its finance cost before accepting.

A subcontract offering 60-day terms can look similar to one offering 30 days. Your wages and merchant accounts do not wait any longer, though, so the difference falls on your bank balance.

This guide gives general information, not legal or financial advice. Check your subcontract, and current guidance on gov.uk for any rules on payment terms that may apply to your work.

Where are the days counted from?

"60 days" can mean very different things. Before comparing offers, find in your subcontract:

  • The valuation or application date
  • The due date, and how it is fixed
  • The final date for payment, and how many days after the due date it falls

A subcontract that pays 30 days after a due date that is itself 14 days after your application gives you your money about 44 days after you apply, before any delay in the valuation. The guide to the Construction Act payment timetable explains each of these dates and the notices that go with them. This page is about what the gap does to your cash.

How much does a longer gap change the cash you need?

The comparison below is for illustration only, with assumed figures. A four-month job is valued at £30,000 a month. Costs of £26,000 a month are paid in the month they are incurred. Each payment is the valuation less 5% retention, so £28,500. Under terms A it arrives the month after valuation. Under terms B it arrives two months after. Both start from a zero balance.

MonthCosts paidReceived, terms ABalance, terms AReceived, terms BBalance, terms B
1£26,000£0-£26,000£0-£26,000
2£26,000£28,500-£23,500£0-£52,000
3£26,000£28,500-£21,000£28,500-£49,500
4£26,000£28,500-£18,500£28,500-£47,000
5£0£28,500£10,000£28,500-£18,500
6£0£0£10,000£28,500£10,000

Both jobs end in the same place: £10,000 in the bank and £6,000 of retention still to come, so the same £16,000 of profit. But under terms A the lowest balance is £26,000 overdrawn, and under terms B it is £52,000. The extra month doubled the cash needed to carry the job, and the balance was £28,500 lower for four months running.

What does the extra gap cost?

If the gap is funded by an overdraft or other borrowing, it has a cost. Continuing the example, at an assumed borrowing rate of 10% a year, £28,500 for four months costs about £28,500 x 10% x 4 / 12 = £950. That is close to 6% of the job's £16,000 profit, before any delay in payment.

The bigger risk is often not the interest but the limit. If the peak need is more than your facility, you may not be able to take on the job at all, or another job alongside it.

What can you do about long payment terms?

  • Price it. Include the finance cost of the gap in your tender, the same way you would any other cost of doing the job.
  • Ask for shorter terms. Payment terms can be negotiated at tender, especially if you can show the effect on your price.
  • Line up your own terms. Compare your merchant account terms with when you will be paid. The guide to payment applications and retention shows how to make sure applications go in on time, so the clock starts as early as it can.
  • Forecast the whole business. One job on long terms may be fine. Three at once may not be. Add each job you are likely to win to your cash flow forecast before you accept it.

Are there limits on how long payment terms can be?

The Construction Act requires an adequate payment mechanism and a final date for payment, but does not itself set a maximum period. Other rules may affect long terms, including late payment legislation and the payment requirements on public sector contracts and their supply chains. These rules change from time to time, so check current guidance on gov.uk, and take advice if a term looks unusually long or one-sided.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Do 60-day payment terms reduce my profit?

Not on paper, but the cost of funding the gap comes out of it. Work out the finance cost and decide whether to price it.

How do I compare two sets of payment terms?

Count the days from your application to the final date for payment under each, then model both in a monthly cash flow.

Can I refuse long payment terms?

You can ask for different terms at tender, and many subcontractors do. Whether they are accepted is a commercial negotiation.

Does retention make long terms worse?

Retention is separate, but it adds to the cash held back. Show both in your forecast.