Cash flow forecast template for subcontractors
Last updated 2026-11-10 · 6 min read
A cash flow forecast for a subcontractor shows, month by month, when money will actually arrive and leave: receipts from applications after retention, wages and labour, merchant and plant payments, overheads, then the running bank balance. Its main job is to show the lowest point that balance reaches, before a job is won, not after.
A job can make a profit and still run you out of cash. You pay wages weekly and merchants on account, while the main contractor pays weeks after each valuation and holds back retention until the end. The forecast puts those timings side by side, so the gap is a number you can plan for.
What is the difference between profit and cash flow?
Profit compares what a job earns with what it costs. Cash flow is about when each of those happens. Your budget against actual costs tells you whether the job is making money. The forecast tells you whether you can afford to carry it while it does.
What goes into the forecast?
Set one column per month and these rows:
- Work valued. The gross value you expect to apply for each month.
- Receipts. What you expect to be paid, in the month you expect it, after retention.
- Labour. Wages and payments to labour-only gangs, in the month they are paid.
- Materials. Merchant payments, in the month your account terms make them due.
- Plant and access. Hire costs, in the month they are paid.
- Overheads. Office, vehicles, insurance and the rest, every month.
- Tax timing. CIS, VAT and other tax payments or refunds, where they fall.
- Net cash flow, opening balance and closing balance.
Use your subcontract's payment terms to place each receipt. The guide to payment applications and retention explains how the dates and retention work.
What does a worked forecast look like?
The example below is for illustration only, with assumed figures. One job is valued at £110,000 over four months. Payment arrives the month after each valuation, less 5% retention, merchants are paid the month after delivery, and overheads are £3,000 a month. CIS and VAT are left out to keep the table readable. Add them in your own.
| Line | Month 1 | Month 2 | Month 3 | Month 4 | Month 5 | Month 6 |
|---|---|---|---|---|---|---|
| Work valued | £20,000 | £35,000 | £35,000 | £20,000 | £0 | £0 |
| Receipts, after 5% retention | £0 | £19,000 | £33,250 | £33,250 | £19,000 | £0 |
| Labour | -£10,000 | -£17,000 | -£17,000 | -£10,000 | £0 | £0 |
| Materials | £0 | -£8,000 | -£10,000 | -£7,000 | -£2,000 | £0 |
| Plant and access | -£1,000 | -£1,500 | -£1,500 | -£1,000 | £0 | £0 |
| Overheads | -£3,000 | -£3,000 | -£3,000 | -£3,000 | -£3,000 | -£3,000 |
| Net cash flow | -£14,000 | -£10,500 | £1,750 | £12,250 | £14,000 | -£3,000 |
| Opening balance | £5,000 | -£9,000 | -£19,500 | -£17,750 | -£5,500 | £8,500 |
| Closing balance | -£9,000 | -£19,500 | -£17,750 | -£5,500 | £8,500 | £5,500 |
Two things stand out. The balance is below zero for four months and reaches its lowest point, £19,500 overdrawn, at the end of month 2. That is the peak funding requirement: the cash you need from somewhere to carry this job. And £5,500 of retention is still to come after month 6, so it is not in the bank when the next job starts.
Where do CIS and VAT fit?
Both change timing more than they change profit, so they belong in the forecast.
- CIS. If you are paid net of CIS deductions, receipts are lower than the agreed amount. How and when you recover them depends on how your business is set up. If you pay your own subcontractors, you deduct and pay CIS to HMRC as well.
- VAT. Under the domestic reverse charge, most main contractors no longer pay you VAT, but you still pay it to merchants and reclaim it later. Many subcontractors are in a repayment position as a result.
Check HMRC's guidance on gov.uk and ask your accountant how each applies to you. This page is not tax advice.
How do you keep the forecast useful?
- Update it monthly, with actual receipts and payments replacing the forecast
- Add each tender you are likely to win as a separate block, so you can see its effect before you accept
- Move receipts later when a payment notice shows a short payment
- Keep a list of retention due, with dates, under the main table
- Set a lowest balance you are prepared to accept, and look at any month that goes below it
The forecast works best alongside a live view of each job. The guide to tracking margin on a live job covers that side.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Can I download this cash flow template?
There is no download. Copy the table on this page into your own spreadsheet and add a column for each month.
How far ahead should a subcontractor forecast?
At least as long as your longest job, plus the retention period you are waiting on. Many businesses look six to twelve months ahead.
Why does a profitable job go overdrawn?
Because costs are paid before income arrives. Wages go out weekly, while receipts follow each valuation by weeks and retention waits until the end.
Should retention be in the forecast?
Yes, in the month you realistically expect it, not the month the subcontract says it is due. Keep a separate list of retention owed.