Measuring work done for price-work gangs

Last updated 2026-11-10 · 6 min read

Short answer

To measure work done for a price-work gang, agree the measurement rules before work starts: units, how openings and layers count, and how the rate splits between framing, boarding and taping. Then measure together each week, area by area, against the drawings. Record only completed stages, check quality, and get the measure signed before you pay.

Most disputes with price-work gangs are not about the rate. They are about what was measured, and whether a half-finished wall counts. A routine that both sides agreed at the start settles most of them before they begin.

What should you agree before the gang starts?

Write the rules down and give the gang a copy. They should answer:

  • Units. m² for partitions and linings, metres for heads, beads and bulkheads, number for openings or other items paid each.
  • Openings. Whether doors and other openings are deducted from the area, and above what size.
  • Layers. Whether a second layer of board is measured as extra area or covered by a higher rate.
  • Heights. Whether taller walls have their own rate, and where the height bands start.
  • Stages. How the rate is split between framing, boarding and taping, so part-finished work can be paid.
  • Included work. Set-out, cutting, clearing up, protection and return visits.
  • Extra work. How work outside the measure is paid, usually by an agreed day rate on a signed sheet.
  • Quality. What has to be right before a stage counts as complete, and who checks it.

Use the same measurement rules as your own drylining take-off wherever you can. If you measure the gang differently from the way you priced the job, comparing the two becomes guesswork.

How do you pay for part-finished work?

Split the rate into stages and pay each stage only when it is complete in an area. A wall that is framed but not boarded earns the framing stage only. A stage that is mostly done, but not checked, waits for the next measure.

Keep the split realistic. If too much of the rate sits in framing, the gang is paid well ahead of the value of the finished work, and you carry the risk if they leave before taping.

What should a weekly measure sheet show?

AreaItemUnitTotal quantityStageComplete to datePreviously paidThis weekStage rateAmount
Framed
Boarded
Taped
Extra work on signed sheets
Less agreed holdback, if any
Total this week

Add the date, the gang, who measured, and both signatures. Keep marked-up drawings or dated photos for each area with the sheet.

What does a measured week look like?

For illustration only, with assumed figures. These are not market rates. A gang's rate for a partition type is an assumed £10.00 per m², split 30% framing, 40% boarding and 30% taping. The area on level 2 has 400 m² of that partition. The gang has agreed a 5% holdback against snagging.

StageStage rateComplete to datePreviously paidThis weekAmount
Framed£3.00400 m²250 m²150 m²£450.00
Boarded£4.00220 m²100 m²120 m²£480.00
Taped£3.000 m²0 m²0 m²£0.00
Subtotal£930.00
Less 5% holdback-£46.50
Paid this week£883.50

The figure is before any CIS deduction. If the gang is self-employed, you deduct CIS at the rate HMRC gives you when you verify them, and report it in your monthly return. Check HMRC's CIS guidance on gov.uk, and check each worker's employment status against HMRC's guidance.

How do you keep the measure in step with your own valuation?

Compare the gang's measure with what you can claim from the main contractor for the same areas. If you are paying for more than you can value, either the gang is being paid ahead of the work, or your application is behind. Both are worth finding before the month end. The guide to the interim valuation template covers your side of that comparison.

Keep a running total per area: quantity paid by stage, against the total quantity in the area. When the total paid reaches the total quantity, that stage is finished, and any further claim for it needs explaining.

How do you handle disputes over the measure?

  • Measure together, on site or from a marked-up drawing both sides can see
  • Settle the week's differences within the week, while the work is visible
  • Use your daily site reports to check what the gang was doing and where
  • Pay the agreed part on time, and hold only the disputed quantity

A gang that is paid late or short without reason tends to leave, which costs more than most measure disputes are worth.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Should openings be deducted when measuring price work?

Only if your agreement says so. Write the rule down before work starts, with the size above which an opening is deducted.

How often should price work be measured?

Weekly is common, because it matches how gangs expect to be paid and keeps disputes small. Use the same day each week.

Can I hold money back from a price-work gang?

Only if it was agreed before work started. Say how much, what it covers and when it is released.

Who should do the measure?

Your supervisor or site manager, with the gang's leader, together. One side measuring alone invites dispute.