Handover documents for interiors subcontractors
Last updated 2026-11-10 · 6 min read
An interiors subcontractor's handover documents usually include marked-up as-built drawings, the system references and product data sheets for what was installed, installation and inspection records, photos of work before it was closed in, warranties and maintenance notes. Find out at the start exactly what the main contractor needs, collect it as the work progresses, and submit it complete.
Handover paperwork is easy to leave until the end, when the gangs have moved on and nobody remembers which board went where. Late or incomplete documents can hold up practical completion, your final payment or the release of retention, depending on your subcontract.
What goes into the O&M manual and handover file?
The operation and maintenance (O&M) manual tells the building owner what was installed and how to look after it. Your section of it, and of any wider handover file, typically covers:
- As-built information. Drawings marked up to show what was actually built, including partition types, heights and any changes.
- System and product data. The manufacturer's system reference for each partition and lining type, with product data sheets.
- Installation records. Inspection sign-offs, hold points and test results where the specification calls for them.
- Fire-related records. Where your package includes fire-rated partitions or fire stopping, the records of what was installed and where.
- Photos. Dated photos of each area before boarding, showing studs, insulation, fixings and services.
- Maintenance notes. Cleaning, repairing damaged board, and any limits on fixing heavy items to partitions.
- Warranties. Any product or installation warranties your subcontract requires.
The specification and your subcontract set the final list, so ask for the main contractor's handover requirements in writing before you start.
Who is the health and safety file for?
On projects under the Construction (Design and Management) Regulations 2015, there is also a health and safety file, which the principal designer prepares and which may pass to the principal contractor towards the end of the project. As a contractor, your part is to supply information about your work that someone would need to know for future maintenance, alteration or demolition safely. Ask the main contractor what it needs and in what format.
On higher-risk buildings, the information requirements under the building safety regime are stricter, and the main contractor may ask for more detail than usual. Follow its instructions and ask early.
Why do fire-rated partitions need more?
Fire-rated walls only perform as tested when they are built as tested. The handover record should show which system was installed in each location, the board layers, the head detail and any penetrations sealed within your package. The guide to pricing fire-rated partitions covers the records worth planning for from the start, and the time they take.
How do you keep track of what is outstanding?
Keep one tracker per job and review it at each progress meeting. The example below is for illustration only.
| Item | Areas covered | Who provides | Collected when | Status |
|---|---|---|---|---|
| As-built partition layout, marked up | Levels 1–3 | Our site manager | As each floor is completed | Levels 1–2 done |
| System references and data sheets | All partition types | Our office, from the merchant and manufacturer | Before first fix | Complete |
| Pre-boarding photos | Every room | Gang leader | Before each wall is closed | Level 3 missing two rooms |
| Inspection sign-offs | Fire-rated walls | Main contractor's inspector | At each hold point | 14 of 16 signed |
| Maintenance notes | All areas | Our office | Before practical completion | Draft |
| Health and safety file information | Whole package | Our office | Before practical completion | Not started |
Taking photos before boarding is the item most often missed, and it cannot be done later. Make it part of the gang's routine, and record it on the daily site report.
What do handover documents cost to produce?
They take office and site time: collecting data sheets, marking up drawings, chasing sign-offs and formatting the file to the main contractor's template. On a larger package that can be several days of someone's time. Allow for it in your price, or state in your offer what format you will provide.
For illustration only, with assumed figures: 3 days of a site manager's time at an assumed £300 a day, plus 2 days of office time at an assumed £180 a day, is £900 + £360 = £1,260 for the handover file on one job.
How do handover documents affect payment?
Some subcontracts make complete O&M information a condition of practical completion, or of releasing part of the retention. Others simply list it as an obligation. Read the clause, and include the documents in your programme so they do not become the last thing holding up your money. The guide to payment applications and retention covers how retention is released.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Does a subcontractor have to provide an O&M manual?
Usually you provide information for the main contractor's manual rather than a full manual of your own. Your subcontract and the specification set what is required.
When should I start collecting handover documents?
At the start of the job. Data sheets and photos are easiest to gather while the work is being done.
Can retention be held for missing O&M information?
It depends on your subcontract. Some link completion or retention release to handover documents, so check the clause.
What format should the documents be in?
Whatever the main contractor's handover requirements specify. Many projects use a digital platform with a set folder structure.