Defects period costs for interiors subcontractors

Last updated 2026-11-10 · 6 min read

Short answer

The defects period is the time after completion when you must return to put right defects in your own work. For an interiors subcontractor it costs return visits, labour, access, small quantities of material and supervision, often months after the job was closed. Price an allowance, log every reported item, and book the cost to the original job.

A job that looked finished at handover can keep costing money for a year. Because the visits are small and spread out, they rarely get costed properly, and the profit reported for the job ends up higher than it really was.

This guide gives general information. It is not legal advice. The length of the period, what counts as a defect and how retention is released are all set by your subcontract, so read it.

What is the defects period?

It is a fixed period after practical completion, or after completion of your package, during which defects that appear must be notified to you and put right. Many contracts now call it a rectification period. Its length is set in your subcontract and often follows the main contract's period, so your period may not start or end when your own work finished.

Retention is often linked to it. Part of the retention is commonly released at completion and the balance at the end of the period, or when the defects are signed off. The guide to payment applications and retention covers how retention is worked out and claimed back.

What is the difference between snagging and defects?

Snagging is finishing and correcting incomplete or faulty work before handover. It belongs in your main programme and price.

Defects are faults in your work that appear after handover, such as joint cracking, nail popping, a door lining out of true, or a partition that fails an inspection.

Damage by others is neither. A wall dented by a furniture installer is not your defect. If you repair it, it should be instructed and paid as extra work, not absorbed as a defect.

What does the defects period cost?

The costs come from going back, more than from the repairs themselves:

  • Travel and remobilising a small gang
  • Labour that is slower than in the main works, because the jobs are scattered
  • Access: a tower or podium for a day
  • Small quantities of material, often at a worse price than the main order
  • Supervision to agree the list and get items signed off
  • Decoration around repairs, if your subcontract makes it yours

How do you price a defects allowance?

Build it from visits rather than from a percentage. The example below is for illustration only, with assumed figures, for a £150,000 interiors package.

ItemBasisCost
Labour3 visits x 2 operatives x 1 day, at an assumed £220 per operative day£1,320
Travel and parking3 visits at an assumed £60£180
Access3 days of tower hire at an assumed £90£270
MaterialsAssumed allowance£150
Supervision3 half days at an assumed £150£450
Defects allowance£2,370

Set against an assumed 5% retention of £7,500, of which half, £3,750, is held until the end of the period, the allowance looks modest. It becomes a real cost when the job needs five visits rather than three, or when attendance is late and the main contractor sends someone else at your expense.

What should a defects log record?

Keep one log per job from the day of handover. The example below is for illustration only.

RefDate reportedLocationDescriptionOur defect?EvidenceAttendedSigned off
D-0112 JanLevel 2, room 2.14Cracked joint above door headYesPhoto from main contractor19 Jan19 Jan
D-0212 JanLevel 3 corridorDent at trolley heightNo, damage after handoverHandover photos show wall intactQuoted as extra work—
D-033 MarLevel 1, room 1.06Screw pops in ceilingNot our packageCeilings by othersReplied in writing—

Reply to every item in writing, say whether you accept it, and record when it was put right and who signed it off. Handover photos are often what settles whether an item is a defect or later damage.

How do you keep the cost under control?

  • Attend within the period your subcontract sets. If you do not, the main contractor may bring in others and charge you, which the guide to contra charges explains how to check.
  • Group items into as few visits as the subcontract allows.
  • Ask for a final defects inspection near the end of the period, and diary the date retention should be released.
  • Book every defects-period cost to the original job's cost code, so the profit per job report shows the true result.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

How long is a defects liability period?

It is set by your subcontract and often follows the main contract. Check the stated period and when it starts for your package.

Do I have to fix damage caused by other trades?

Not as a defect. Repairs to damage you did not cause should be instructed and paid as extra work, if you agree to do them.

When is the rest of my retention released?

When your subcontract says, which is often at the end of the defects period or once defects are signed off. Diary the date and apply for it in writing.

Should defects costs go to the original job?

Yes. Booking them elsewhere overstates the job's profit and hides what the defects period really costs.