Dayworks vs variations: which to use

Last updated 2026-11-10 · 5 min read

Short answer

Use a priced or measured variation when the extra work can be described and measured before or after you do it. Use daywork when it cannot: small, unplanned tasks, or work whose extent only shows once you start. The subcontract decides which route applies, and daywork usually needs agreement before the work starts, not after.

Both routes get you paid for a change. They differ in who carries the risk of the work taking longer, how much evidence you need, and how easy the claim is to challenge. Choosing the right one at the moment the instruction is given matters more than how well the paperwork is done afterwards.

What is the difference in plain terms?

A variation valued by measure or quotation pays an agreed figure for the change, built from your rates or a price agreed in advance. If it takes longer than you priced, that is your cost.

Daywork pays for the time, materials and plant actually used, at the daywork rates and percentages in your subcontract. If it takes longer, the payer carries that, but every hour has to be proved.

In both cases the change itself has to be instructed. Daywork is a way of valuing a variation, not a separate kind of extra work.

Which route fits which situation?

SituationUsual routeWhy
A wall moved on a revised drawingMeasured variationIt can be measured and valued at your rates
An extra bulkhead, fully detailedQuotation before startingThe scope is clear, so a price can be agreed in advance
Boxing in a pipe nobody drew, under an hourDayworkToo small and unpredictable to measure sensibly
Making good after other trades, extent unknownDayworkYou cannot see the scope until you open up
Standing time while access is sortedDaywork, or a delay claimThere is no work to measure, only time lost
Repeated small alterations across a floorAgree the route firstMany small items can be measured together, or recorded as daywork, but not both

If the subcontract says daywork is used only where work cannot properly be measured, expect a main contractor to revalue measurable work at your rates even if you recorded it as daywork.

Who carries the risk under each?

The example below is for illustration only, with assumed figures. Forming access openings in a finished partition is quoted as a variation before starting, then actually takes 34 hours.

LinePriced variationDaywork
Labour basis28 estimated hours at an assumed cost of £3034 recorded hours at an assumed daywork rate of £32
Labour value£840£1,088
Materials£220£220 plus an assumed 15%: £253
Overheads and profitAssumed 15% on £1,060: £159Assumed to be included in the daywork rate and percentage
Amount paid£1,219£1,341
Your actual labour cost34 hours at £30: £1,02034 hours at £30: £1,020

Under the priced variation, the six extra hours cost you £180 that you do not recover. Under daywork, they are paid, provided the sheets are signed and accepted. If the work had taken 22 hours instead, the priced variation would have paid you more for less time. Daywork moves the risk of overrun to the payer, which is why main contractors scrutinise it and often prefer a price.

What are the common mistakes?

  • Starting daywork without agreement. Many subcontracts require a written instruction that the work is to be valued as daywork. Without it, sheets may be revalued.
  • Daywork sheets for measurable work. These invite a revaluation at measured rates, and arguments over the hours.
  • Pricing a variation before the scope is known. A fixed figure for open-ended work puts all the risk on you.
  • Recording the same work twice. A task on a daywork sheet must not also appear in a measured variation.

How do you decide on site?

Ask three questions when the instruction is given:

  1. Can the work be described and measured now? If yes, price or measure it.
  2. If not, does the subcontract allow daywork, and has the instruction said so in writing?
  3. If neither is clear, confirm in writing how the work will be valued before you start.

Then follow the right process. The guide to daywork sheets covers what a sheet needs to get paid, and the guide to recording variations covers the instruction, evidence and pricing of a measured change. Every item, whichever route, belongs in one variations log that goes with each application.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Can daywork be turned into a measured variation later?

It can happen, especially where the work could have been measured. Check what your subcontract says about when daywork applies.

Is daywork always paid at a higher rate?

Not necessarily. Daywork rates are set in your subcontract and are paid on recorded time, so the total depends on the hours accepted.

Who decides whether work is daywork?

Usually the instruction, under the rules in your subcontract. Agree it in writing before you start.

Should daywork and variations be in the same log?

Yes. One log with every change, showing which route each item is on, keeps applications complete and avoids double counting.