Day rates vs price work for drylining gangs
Last updated 2026-11-10 · 6 min read
On a day rate, you pay a drylining gang for the time they spend on site, so you carry the risk of slow output. On price work, you pay an agreed amount for each unit of work completed, so the gang carries it. Price work needs careful measurement and quality checks. Day rates need supervision and output records.
Most drylining subcontractors use both, often on the same job. The question is which suits the work in front of you, the gang doing it and the records you can keep.
Who carries the risk of slow work?
That is the main difference. Your tender priced labour from an assumed output. If the gang works slower than that:
- On a day rate, every extra day is your cost. The tender allowance is used up early and the job margin falls.
- On price work, the gang earns less per day, but your labour cost for the measured work stays where it was priced.
The reverse is also true. If the gang works faster than your tender assumed, on a day rate the job keeps the gain, and on price work the gang does.
What does each one need from you?
| Area | Day rate | Price work |
|---|---|---|
| What you pay for | Time on site | Measured quantities completed |
| Productivity risk | Yours | Mostly the gang's |
| What you must record | Hours, by area and activity | Quantities, by area and stage |
| Supervision focus | Output and sequence | Quality and finish |
| Quality risk | Lower pressure to rush | Pressure to rush, and to leave snags |
| Work that cannot be measured | Paid as normal | Needs a day rate or agreed extra |
| Waiting time | Your cost | Disputed unless agreed in advance |
| Cost certainty at tender | Depends on your output figures | Higher, if the rates are agreed before start |
Price work only gives cost certainty when the measurement is clear. The guide to measuring work done for price-work gangs covers how to agree and record it.
How does the cost compare at different outputs?
For illustration only, with assumed figures. These are not market rates. A gang boards 600 m² of partition. The day rate is an assumed £250 per operative-day. The price-work rate is an assumed £5.00 per m² for the same boarding, so the gang earns £3,000 for the area whatever it takes.
| Output per operative-day | Operative-days needed | Day-rate cost | Price-work cost | Difference to you |
|---|---|---|---|---|
| 60 m² | 10 | £2,500 | £3,000 | Day rate £500 cheaper |
| 50 m² | 12 | £3,000 | £3,000 | The same |
| 40 m² | 15 | £3,750 | £3,000 | Price work £750 cheaper |
The break-even output is the day rate divided by the price-work rate: £250 / £5.00 = 50 m² per operative-day. If you expect better output than that, a day rate costs you less. If output is uncertain, because of access, sequence or other trades, price work moves that uncertainty to the gang.
Find your break-even from your own outputs, measured as the guide to drylining productivity shows.
When does a day rate make more sense?
- Work that is hard to measure: making good, alterations, small areas and fiddly details
- Early work while the sequence is still unclear, or access is stop-start
- Where finish quality matters more than speed
- Return visits and snagging, unless the price-work rate already covers them
A day rate is easier to agree, but it needs a supervisor who checks output every week.
When does price work make more sense?
- Large, repetitive areas of the same system and height
- Work with a clear measure, such as m² of boarding or metres of head track
- Gangs you know, whose quality you trust
- Jobs where labour cost certainty matters more than catching faster output
Agree what the rate covers before work starts: set-out, cutting, cleaning up, protection, return visits, and what happens when other trades stop the gang.
How do you mix the two on one job?
A common pattern is price work for the main measured items, with agreed extra work paid at a day rate on a signed sheet. Keep the two separate in your records, so day-rate hours do not hide slow price work. Use the same discipline as for daywork sheets with the main contractor: a written instruction, names and hours, and a signature on the day.
Whatever the basis of payment, price tender labour from its full cost, as the guide to setting your drylining labour rate explains. If you engage self-employed gangs, CIS applies to what you pay them, and you should check each worker's employment status against HMRC's guidance. This page does not cover how those rules apply to a particular gang.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Is price work always cheaper?
No. If the gang works faster than your break-even output, a day rate costs you less. Price work fixes the cost, it does not lower it.
Does price work affect quality?
It can. Paying by quantity rewards speed, so check finish and snags before you pay each measure, and agree who pays for return visits.
How do I pay for waiting time on price work?
Agree it before work starts, usually at a day rate on a signed sheet. Record the cause, because it may be a claim against the main contractor.
Should my tender assume a day rate or price work?
Price the labour you expect to pay. If you will use price work, price from the agreed rates plus supervision and extras. If day rates, use your measured outputs.