Specification review before pricing a drylining package

Last updated 2026-11-10 · 6 min read

Short answer

Before pricing a drylining package, read the whole specification, not only the partition types. Note named products and whether alternatives are allowed, any design or performance duties, the finish standard, samples and mock-ups, testing, interfaces such as fire stopping, and the general clauses on protection and handover. Log each item that costs money and decide how to price it.

Most estimators open the specification to find the build-up for each wall type. The drylining take-off guide covers that step. This guide is about the rest of the document: the clauses that add cost without changing a single board.

How is a specification usually set out?

Many UK specifications are written in NBS format, with clauses grouped by work section. A drylining package often draws on more than one section: the partitions and linings themselves, plus sections or general clauses covering ceilings, fire stopping, decoration interfaces, and the project's general requirements.

Ask for every section that applies to your package, and the general or preliminaries sections as well, because they often hold the clauses that matter most to the price.

Which clauses carry the most cost?

What to look forThe question to askPossible price effect
Named productsAre alternatives allowed, and with whose approval?You may not be able to use the products you priced from your merchant
Performance requirementsWho is responsible for meeting the fire or acoustic performance?Design duty, evidence and possibly professional indemnity cover
Finish standardWhat level of finish is required, and where?More jointing, more board, more inspection time
TolerancesHow flat and how plumb must the wall be?Slower installation and packing to suit poor structure
Samples and mock-upsIs a sample panel or benchmark area required?Labour, materials and time before the main work starts
TestingIs on-site acoustic or other testing required, and who pays for re-tests?Test costs, remedial work, programme risk
SubmittalsWhat data sheets, drawings or calculations must be submitted?Office time before you can order
InterfacesWho does fire stopping, access panels, fixing support and sealing?Items you may have assumed were by others
Protection and cleaningMust you protect your finished work until handover?Labour and materials after your gang has finished
HandoverWhat records, certificates and manuals are required?Office time at the end of the job

Not every clause will apply. The point is to find them before you price, not when the site manager quotes them back to you.

How do you handle named products and "or equivalent"?

If the specification names a product and allows "or equivalent", an alternative usually still needs approval, and you may have to show it matches the tested performance of the named one. Allow time for that, and do not assume approval.

If it names a product with no alternative, price that product, and get a merchant quote for it specifically. A cheaper system you prefer to use is an alternative offer, not your main price. Put it as a separate option so the comparison is fair.

What if the specification gives a performance rather than a system?

A performance specification, such as a required fire resistance or sound insulation rating with no named system, may pass the choice of system to you. Read carefully whether that also passes design responsibility to you. If it does, you need tested evidence for the system you choose, and you should check your insurance covers design work. The guide to pricing acoustic partitions shows how the required rating drives the build-up.

If the responsibility is unclear, ask, and state your assumption in the offer.

What does a review log look like?

Keep a short log as you read. For illustration only, with assumed figures:

ClauseWhat it saysHow it is priced
FinishHigher finish standard to the reception wallsExtra jointing labour, 2 days at £240 a day: £480
Mock-upOne sample bay of each partition type before startingTwo types, assumed £350 each: £700
TestingPre-completion acoustic testing by others; re-tests at the subcontractor's costTesting excluded; re-test risk noted as a qualification
Fire stoppingService penetrations through partitionsExcluded, stated in the offer
ProtectionProtect finished linings until handoverAssumed 1 day a floor for 4 floors at £240: £960

In this example, the specification adds £2,140 of priced items and two items for the offer that cost nothing to write but could cost a lot to leave out. The guide to qualifications and exclusions shows how to word them.

When should you send questions?

As soon as the review is done, not the day before the tender returns. Group your questions by clause, quote the clause reference, and say what you will assume if you get no answer. Keep a copy with the tender, so the assumptions you priced are on record if the specification is revised later.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Do I need to read the preliminaries section as a subcontractor?

Yes, at least the parts passed down to you. They often set out protection, cleaning, working hours and handover duties that cost money.

Can I price a different system from the one specified?

Price the specified one as your main offer. Put an alternative as a separate option and say it needs approval.

What does "or equivalent" mean for a subcontractor?

Usually that you can propose another product, but it needs approval and evidence that it performs the same way.

What if the specification and drawings disagree?

Raise it as a question with both references, and state the assumption you priced in your offer.