Pricing out-of-hours and night work
Last updated 2026-11-10 · 5 min read
Night and out-of-hours work costs more than the extra hourly pay. Price it from three parts: the enhanced pay rates you have agreed with your operatives, the output you lose to shorter productive time and set-up each shift, and the per-shift costs such as supervision, lighting and access to the building. Price it only for the areas and shifts the enquiry actually names.
Out-of-hours work is common on fit-outs in occupied offices, shops, hospitals and schools, where noisy or dusty work cannot run in the day. Priced at day rates, it is one of the quickest ways to lose money on a package.
Why is a night shift less productive?
The shift may be paid for eight hours, but less of it goes on fixing. Typical reasons:
- Set-up and clear-down. In an occupied building, the area may need to be cleared, cleaned and made safe for the morning, every shift.
- Restricted deliveries and lifts. Materials may only arrive at set times, or the goods lift may be shared or limited.
- Fewer people to sort problems. A missing detail or a service in the way can stop work until the day team answers.
- Fatigue. Output tends to drop through a night shift, and more so across a run of nights.
Use your own records of output where you have them. The guide to drylining productivity explains how to measure it.
How does a night shift compare with a day shift?
For illustration only, with assumed figures. These are not market rates. A gang of two operatives boards partitions on an eight-hour shift. The night rate is an assumed enhancement agreed with the gang, and the night output allows for clear-down and slower working.
| Day shift | Night shift | |
|---|---|---|
| Paid hours (2 operatives x 8 hours) | 16 | 16 |
| Assumed hourly rate | £30 | £40 |
| Labour cost per shift | £480 | £640 |
| Assumed output per shift | 30 m² | 22 m² |
| Labour cost per m² | £16.00 | £29.09 |
The hourly rate is a third higher, but the labour cost per square metre is about 82% higher, because the same shift produces less. Pricing night work as a percentage uplift on the hourly rate alone would miss most of the difference.
What per-shift costs should you add?
Some costs are incurred once per shift, however much work is done:
- Supervision, if a supervisor or chargehand must be present on every night shift
- Task lighting and power, if building lighting is off or limited
- Security and access, such as sign-in times, escorts or permits to work
- Travel and parking, which may cost more at night or need separate transport
- Protection and cleaning, so the area can be used the next morning
Price these per shift and multiply by the number of shifts in the programme.
What rules affect night work?
- Site and building rules. Permitted hours, noise limits and access arrangements may be set by the main contractor, the building's management or the local authority. Get them in writing before you price.
- Working time. If anyone you employ counts as a night worker under the Working Time Regulations, there are limits on average night hours and a duty to offer health assessments. Check the current guidance on gov.uk for the people you engage.
- Lone working and first aid. Smaller night teams still need emergency arrangements, first aid cover and safe ways of working.
- Your gang's agreement. Agree enhanced rates and shift patterns with your operatives before you tender, not after you win.
How should night work appear in your offer?
Be specific about what you have priced:
- Which areas or activities are priced as out-of-hours work
- The shift times and the number of shifts assumed
- How any further out-of-hours work would be priced, for example at stated enhanced rates
- Any conditions, such as the minimum notice needed to arrange night shifts
If out-of-hours work is not part of your price, exclude it clearly, as the guide to qualifications and exclusions shows. If you use price work for day shifts, decide whether night shifts are paid differently; the guide to day rates vs price work explains who carries the output risk under each.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Is there a standard rate for night work in construction?
Not one that applies to every subcontractor. Enhanced rates depend on your agreements with your operatives and any working rule agreement you follow.
Should I price night work as a percentage uplift?
Only if the uplift is worked out from lost output and per-shift costs, not just the higher hourly pay. Build it up for each job.
What if the main contractor asks for night work after the order is placed?
Treat it as a change. Record the instruction and price it from your stated out-of-hours rates, or as a variation under your subcontract.
Do weekend shifts count as out-of-hours work?
Usually, if your offer was priced on weekday working. State your assumed working hours in the quote so the difference is clear.