Pricing access equipment in a drylining job
Last updated 2026-11-10 · 5 min read
Price access from the drawings and the programme, not as a percentage. Split the job into zones by working height, choose the equipment each zone needs, count how many units each gang uses and for how many weeks, then add delivery, erection, moves and inspections. Check first what the main contractor provides, so you neither double price it nor miss it.
Access is one of the items most often under-priced on a drylining tender, because it is not on the drawing. A tower left on hire for six extra weeks, or a stairwell nobody priced, comes straight off the margin.
Who provides the access?
Read the enquiry before you price anything. The preliminaries or attendance schedule may say that the main contractor provides some access, such as scaffold to stairwells, atria or external walls, or a mobile elevating work platform for high areas. Where it is silent, assume you provide what your own operatives need, and say so in your offer.
Note for each item whether it is provided by the main contractor free of charge, available at a charge, or yours to provide. The guide to the drylining tender checklist lists access among the items to check before you submit.
How do you work out what access each area needs?
Zone the job by the height your operatives must reach to fix the top track and board the head of the wall:
- Standard floor-to-slab heights: podium steps or low platforms
- Taller rooms and feature walls: mobile towers
- Atria, stairwells and shafts: towers, scaffold or a MEWP, often with the main contractor
- Restricted areas: risers and plant rooms where only small platforms fit
Then count units per gang, not per floor. If two gangs work at the same time, each needs its own access for the full period they are on that zone.
How long will each piece be on hire?
Take the duration from your programme for each zone, then add time for delivery before the start and collection after the finish. Hire usually runs from delivery to collection, not only the days it is used.
Plan where equipment goes when a zone finishes. Moving it to the next zone is cheaper than off-hiring and re-hiring, but only if the next zone is ready. If the programme slips, hire keeps running.
What does an access build-up look like?
For illustration only, with assumed figures. These are not market rates. A drylining package on four floors with standard heights, and a double-height reception area. The main contractor provides scaffold in the stairwell.
| Item | Quantity | Duration | Assumed rate | Cost |
|---|---|---|---|---|
| Podium steps, two gangs | 6 units | 12 weeks | £12 per unit per week | £864 |
| Mobile tower for reception | 2 towers | 4 weeks | £90 per tower per week | £720 |
| Delivery and collection | 3 trips | £60 per trip | £180 | |
| Erecting, moving and dismantling towers, and checks | 20 hours | £30 per hour | £600 | |
| Stairwell scaffold | By main contractor | £0 | ||
| Total | £2,364 |
The total can be priced as a separate preliminary item or spread over the measured area. The guide to building a drylining rate explains both approaches. Whichever you choose, keep the build-up so you can check it against the hire invoices during the job.
What else does access cost besides hire?
- Labour to erect, move and dismantle. Towers are rebuilt or moved many times on a fit-out.
- Inspections. Equipment must be inspected as the Work at Height Regulations 2005 and the manufacturer's instructions require. Allow time for it.
- Training. Operatives need to be competent for the equipment they use, for example through PASMA training for mobile towers or IPAF training for MEWPs.
- Lower output. Working from a tower or platform is slower than working from the floor. Use your own outputs, measured as the guide to drylining productivity describes.
- Damage and loss. Hired equipment that is damaged or goes missing on site is usually charged to the hirer.
Should you hire or own access equipment?
Owning podiums and small towers can make sense if you keep them in use across jobs. Owned equipment still has a cost: purchase, storage, transport, inspection and repair. Charge it to each job at an internal hire rate, so a job using your own equipment is priced on the same basis as one using hired kit.
FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.
Frequently asked questions
Should access be priced in the rate or as a separate item?
Either can work. A separate item is easier to check and adjust if the programme changes. If you spread it over the rate, say so in your offer.
Who pays for access if the programme is extended?
It depends on why the programme changed and on your subcontract. Keep hire records so that, if the delay was not yours, you can show the extra cost.
Does the main contractor's scaffold count as access I can use?
Only if the enquiry or subcontract says you may use it. Check whether it will be adapted for your work and whether a charge applies.
Do I need to allow for tower inspections?
Yes. Allow time for the inspections the regulations and the manufacturer require, and for the people doing them to be competent.