Short answer

On an NEC subcontract, an early warning is a notice you give as soon as you are aware of a matter that could increase the price, delay completion or a key date, or impair the finished work. It goes on a register for discussion at early warning meetings. A missed warning can reduce what a later compensation event is worth.

Early warnings are meant to solve problems while the cheapest answer is still available.

This guide describes the general mechanism in the NEC4 Engineering and Construction Subcontract and the NEC4 Engineering and Construction Contract, where early warnings sit in clause 15. Older NEC3 contracts work in a similar way but use different names and wording. It is not legal advice. Check which NEC edition, main option and amendments your subcontract uses, and read the clauses themselves.

Who gives an early warning, and to whom?

Under the subcontract, you and the Contractor, meaning the main contractor in its role as your client, each notify the other. Either party can and should give one. In the main contract, the same duty runs between the main contractor and the Project Manager.

Give it in writing, by the method your subcontract sets, often a project platform or a named email address. A comment in a site meeting is not a notice on its own.

What should you give an early warning about?

Anything that could, not only will, cause one of the listed effects. On interiors packages, common examples are:

  • Areas not ready on the programmed date
  • Services in walls or ceiling voids late or clashing with partitions
  • Design information missing, such as head details or fire stopping responsibilities
  • Specified products with long or uncertain lead times
  • Access, hoist or loading bay time shared with other trades
  • Survey findings that differ from the drawings

If in doubt, warn. The register then shows you raised the matter on that date.

What happens after a warning is given?

The matter goes on the early warning register. In NEC4 that register is kept by the party in the project manager role, which on your subcontract is usually the main contractor. NEC3 contracts call it a risk register.

At an early warning meeting, the parties look at ways to avoid or reduce the effect, decide what action to take and who does it, and the register is updated. Keep your own copy, and check that each warning you gave appears on the issued register in your words.

What if you did not give a warning you should have?

This is the commercial reason early warnings matter. Under NEC, if the client side decides that you did not give an early warning of an event that an experienced contractor could have given, it can say so when the event is being assessed as a compensation event. The event may then be assessed as if the warning had been given, which can leave out costs a timely warning could have avoided.

For illustration only, with assumed figures: late services on level 2 leave two operatives standing for three days. At an assumed £200 per operative day, that is £1,200. If an experienced subcontractor could have seen the clash a week earlier, and a warning would have let the gang start level 3 first, the standing time might not be included in the assessment.

An early warning is not the same as notifying a compensation event. A compensation event notice is a separate step, with its own time limit in your subcontract, and the warning does not replace it.

What does an early warning register look like?

Keep your own record alongside the official one. The example below is for illustration only.

RefDate notifiedMatterCould affectProposed actionOwnerStatus
EW-042 OctLevel 2 ceiling void services not completeProgramme, costResequence to level 3, revisit level 2 on 16 OctMain contractor M&E leadOpen
EW-053 OctHead detail to curtain wall not issuedProgramme, qualityDesigner to issue detail by 9 OctMain contractor design managerClosed 8 Oct
EW-067 OctAcoustic board lead time extended by merchantProgrammeConfirm alternative delivery date, consider early orderUsOpen

Your daily site reports should show the same dates. When a warned matter turns into a change, record the change too, as the guide to recording variations describes.

How do early warnings help your margin?

They put a problem on record while it is still small and cheap to solve. Review open warnings alongside your live job margin each week, so you know which ones carry cost.

FixMargin is software for UK drylining and interiors subcontractors. It works out material build-ups for supported partition and wall lining systems, and the library does not yet cover every manufacturer. The costed BoQ, call-offs, purchase orders, goods received notes and invoice checks are on the Starter plan and above. You can start with a free account, which includes the calculator and one price list: fixmargin.com/signup.

Frequently asked questions

Does an early warning mean I will be paid for the matter?

No. An early warning records a risk. Payment for a change depends on whether it is a compensation event under your subcontract and on how it is assessed.

Can the main contractor give me an early warning?

Yes. The duty runs both ways. Read and respond to warnings you receive, and attend the meetings you are invited to.

Is an email enough for an early warning?

It may be, if your subcontract allows notices by email. Check the communications clause, because many NEC projects require notices through a named system.

Do NEC3 subcontracts have early warnings?

Yes, in a similar form, with a risk register and risk reduction meetings. The wording and consequences differ in detail, so read your own edition.